LBJ Express - Project History: Timeline
As the I-635 Managed HOV Lanes Project advances, a summary of project activity and public information documents will be available through this page.

Early 2016

  • Estimated completion date

January 2011

  • Construction begins on Jan. 18, 2011.

December 2010

  • Approval to being detailed work on Dec. 19, 2010

June 2010

  • LBJ Infrastructure Group obtains financial close on June 22, 2012.

September 2009

  • Comprehensive Development Agreement executed with LBJ Infrastructure Group on Sept. 4, 2009.

May 2009

  • Financial Disclosure Public Hearing on May 7, 2009

March 2009

February 2009

January 2009

June 2008

March 2008

February 2008

November 2007

October 2007

September 2007

August 2007

June 2007

November 2006

August 2006

May 2006

January 2006

November 2005

May 2005

  • TxDOT issues Request for Qualifications for LBJ Managed HOV Lanes Project

June 2004

I-635 Corridor Coalition requests TxDOT deliver LBJ managed HOV lanes as a CDA

December 2002 - April 2004

  • TxDOT receives Environmental Clearance for the LBJ Managed Lanes Projects