The scope of this study is 13.7 miles of I-10 from FM 359 in Waller County to FM 3538 in Austin County.

Proposed Improvements

  • Rebuilding overpasses to provide additional clearance
  • Replacing mainlane overpasses
  • Converting the existing two-way frontage road system to one-way
  • Replacement of the bridges over the Brazos River
  • No additional right of way is needed

Partners

This study is a partnership between TxDOT and the Federal Highway Administration.