2004 English Special Provisions by Item (All)
|
Specification Information
|
Search For a Special Provision or Specification
|
|
SP008-072 |
PDF |
RTF |
- For project 1200-05-014 in Travis County. Incentive Using Road-User and Lost Toll Revenue Costs, Contract Administration Liquidated Damage Values, and Disincentive Using Road-User Cost and Lost Toll Revenue.
One-Time Use.
|
SP008-071 |
PDF |
RTF |
- For project 1200-05-014 in Travis County. Before starting work on a construction Contract, prepare and submit your progress schedule based on the sequence of work and traffic control plan shown in the Contract.
One-Time Use.
|
SP008-070 |
PDF |
RTF |
- Providers for incentives using Road-User Cost or Contract Administration Liquidated Damages and disincentives using Road-User Cost. May used at the districts option.
Replaces SP008-001 SP008-004 SP008-005 SP008-025 SP008-026 . (Change Memo: de-08-07). Statewide Use.
|
SP008-069 |
PDF |
RTF |
- Providers for no excuse incentives using Road-User Cost or Contract Administration Liquidated Damages and disincentives using Road-User Cost. May be used at the districts option.
Replaces SP008-001 SP008-004 SP008-005 SP008-025 SP008-026 . (Change Memo: de-08-07). Statewide Use.
|
SP008-068 |
PDF |
RTF |
- For project 0014-16-257 in Tarrant County. Incentives for early Contract completion using contract administration liquidated damage. Disincentives for late substantial completion of work using daily road-user costs.
One-Time Use.
|
SP008-067 |
PDF |
RTF |
- For project 3050-03-005 in Harris County. The Department may suspend all or part of the work under this contract, due to right-of-way acquisitions and/or utilities adjustment for a maximum of 60 days.
One-Time Use.
|
SP008-066 |
PDF |
RTF |
- For project 0039-17-148 in Hidalgo County. The contractor to perform all the Prep ROW work in 40 days and will get CALD damages over the 40 days. After ROW, then have have 120 day utility delay. Once utilities are relocated after the 120 days, the contract time charges will resume.
One-Time Use.
|
SP008-065 |
PDF |
RTF |
- For project 0291-10-079 in Bexar County. Should the Contractor substantially complete the project or any interim milestone under the number of working days stipulated in the proposal, a credit, in the amount per working day stipulated on the plans.
One-Time Use.
|
SP008-064 |
PDF |
RTF |
- For project 0748-05-035 in Atascosa County. Failure to substantially complete the project within the established number of working days stated in the Contract will result in assessment of liquidated damages at daily cost as shown for each working day in excess of that stated number.
One-Time Use.
|
SP008-063 |
PDF |
RTF |
- Clarifies that time charges begin when the plans specify a start work date.
Replaces SP008-003 . (Change Memo: de-35-06). Statewide Use.
|
SP008-061 |
PDF |
RTF |
- For project 2374-05-065 in Tarrant County. Failure to complete Milestone 2 listed below within the established number of working days, will result in liquidated damages being assessed for every working day in excess of the stated number.
One-Time Use.
|
SP008-060 |
PDF |
RTF |
- For project 6137-01-001 in Dallas County. To allow assessment fee for Rountine Maintenance Contracts for the Dallas District.
One-Time Use.
|
SP008-059 |
PDF |
RTF |
- For project 2075-02-055 in Smith County. Lump sum no excuse incentive for substantial completion of milestone 1 by Nov. 1, 2007
One-Time Use.
|
SP008-058 |
PDF |
RTF |
- For project 0025-02-164 in Bexar County. Milestones with incentive/disincentive
One-Time Use.
|
SP008-057 |
PDF |
RTF |
- For project 0054-06-083 in Brown County. Milestone completion is defined as occurring when traffic is following the lane arrangement as shown on the plans for the constructed and or existing roadway as specified in the TCP (Phase) and or the final lane configuration.
One-Time Use.
|
SP008-056 |
PDF |
RTF |
- For project 0920-38-177 in Jefferson County. The Department will suspend work under this contract, due to drainage ditch realignment (work to be performed by Jefferson County Drainage District No. 6), for a maximum of 30 days.
One-Time Use.
|
SP008-055 |
PDF |
RTF |
- For project 0177-05-057 in Montgomery County. Prosecute the work continuously to completion within the working days specified except for as follows. The Department may suspend work under this contract, due to right-of-way acquisitions.
One-Time Use.
|
SP008-054 |
PDF |
RTF |
- For project 0086-14-022 in Webb County. Working days will be charged Monday through Sunday, excluding national holidays, the listed additional days, and floating non-work days, regardless of weather conditions or material availability.
One-Time Use.
|
SP008-053 |
PDF |
RTF |
- For project 0610-07-085 in Bowie County. Failure to complete the milestones listed below within the established number of working days will result in liquidated damages.
One-Time Use.
|
SP008-052 |
PDF |
RTF |
- For project 0028-02-044, 0028-02-054 in Harris County. Prosecute the work continuously to completion within the working days specified except for as follows.
One-Time Use.
|
SP008-051 |
PDF |
RTF |
- VOID - DO NOT USE. Modifies the existing special provisions to limit use to the 3.1 version of Primavera or SureTrac softwares until the compatibility issue is resolved. Special provision 008---051 has been removed from statewide use. Future use will require district submission for approval of one time use or districtwide use.
Replaces SP008-037 . (Change Memo: de-10-08). Statewide Use.
|
SP008-050 |
PDF |
RTF |
- Modifies the existing special provisions to limit use to the 3.1 version of Primavera or SureTrac softwares until the compatibility issue is resolved.
Replaces SP008-010 .Replaced by SP008-086 . (Change Memo: de-20-06). Statewide Use.
|
SP008-049 |
PDF |
RTF |
- Modifies the existing special provisions to limit use to the 3.1 version of Primavera or SureTrac softwares until the compatibility issue is resolved.
Replaces SP008-002 .Replaced by SP008-086 . (Change Memo: de-20-06). Statewide Use.
|
SP008-048 |
PDF |
RTF |
- For project 0284-02-022 in Throckmorton County. Failure to complete the milestones listed below within the established number of working days, plus any additional working days granted, will result in liquidated damages.
One-Time Use.
|
SP008-047 |
PDF |
RTF |
- For project 6143-84-001 in Hays County. Failure to complete the milestone listed below within the established number of days, will result in liquidated damages being assessed for every day in excess of the stated number.
One-Time Use.
|
SP008-046 |
PDF |
RTF |
- For project 0932-01-091 in Jefferson County. Disincentive and incentive
One-Time Use.
|
SP008-045 |
PDF |
RTF |
- For project 6137-85-001 in Harrison County. Failure to substantially complete the project within the established number of working days stated in the contract, plus any additional working days granted, will result in a payment deduction of $5,000 per day as a disincentive.
One-Time Use.
|
SP008-044 |
PDF |
RTF |
- For project 2374-01-153 in Dallas County. Failure to substantially complete the project within the established number of working days stated in the contract, plus any additional working days granted, will result in the daily road-user cost (RUC).
One-Time Use.
|
SP008-043 |
PDF |
RTF |
- For project 0912-71-657 in Harris County. City of Houston is paying an incentive.
One-Time Use.
|
SP008-042 |
PDF |
RTF |
- For project 6138-47-001 in Hays County. Failure to Complete Work on Time. Will result in liquidated damages being assessed for every hour in excess of the stated number.
One-Time Use.
|
SP008-041 |
PDF |
RTF |
- For project 2374-01-153 in Dallas County. Disincentive, Incentive. Failure to Complete Work on Time is supplemented by the following.
One-Time Use.
|
SP008-040 |
PDF |
RTF |
- For project 0546-08-010, 0734-02-016 in Cass County. Computation of Contract Time for Completion. Working day charges will begin 360 calendar days after the date of the written authorization to begin work.
One-Time Use.
|
SP008-039 |
PDF |
RTF |
- For project 0048-01-057 in Dallas County. Failure to substantially complete the milestones within the established number of working days stated in the contract. Will result in the daily road-user cost (RUC).
One-Time Use.
|
SP008-038 |
PDF |
RTF |
- For project 0048-01-057 in Dallas County. The Department will pay an incentive for the substantial completion of milestone work, as determined by the Engineer.
One-Time Use.
|
SP008-037 |
PDF |
RTF |
- Provides for full CPM schedule and is stricter than 008---010.
Replaced by SP008-051 . (Change Memo: de-54-05). Statewide Use.
|
SP008-035 |
PDF |
RTF |
- For project 2250-01-021 in Denton County. Daily Intersection Rental Charge
One-Time Use.
|
SP008-034 |
PDF |
RTF |
- For project 0394-01-056, 0428-02-019 in Panola County. Computation of Contract Time for Completion.
One-Time Use.
|
SP008-033 |
PDF |
RTF |
- For project 0009-11-202 in Dallas County. Failure to complete the milestone listed below within the established number of hours, will result in liquidated damages being assessed for every hour in excess of the stated number.
One-Time Use.
|
SP008-032 |
PDF |
RTF |
- For project 1047-03-060 in Dallas County. Failure to substantially complete the project by August 31, 2006 will result in daily road-user cost.
One-Time Use.
|
SP008-031 |
PDF |
RTF |
- For project 1047-03-060 in Dallas County. The Department will pay the Contractor a No- Excuse bonus for completion of the milestone in this project by August 31, 2006.
One-Time Use.
|
SP008-030 |
PDF |
RTF |
- Clarifies that liquidated damages will be imposed if call out work is not completed on time. Use at the districts option.
(Change Memo: de-38-05). Statewide Use.
|
SP008-029 |
PDF |
RTF |
- For project 0208-04-011 in Harrison County. Working day charges will begin 360 calendar days after the date of the written authorization to begin work, or the first day of construction activity if the work is initiated with in the 360 day period.
One-Time Use.
|
SP008-028 |
PDF |
RTF |
- For project 0394-01-056 in Panola County. Working day charges will begin 360 calendar days after the date of the written authorization to begin work, or the first day of construction activity if the work is initiated with in the 360 day period.
One-Time Use.
|
SP008-027 |
PDF |
RTF |
- For project 0014-24-049 in Hill County. Failure to Complete Work on Time is voided and replaced by the following:
One-Time Use.
|
SP008-026 |
PDF |
RTF |
- Provides for a no excuse incentive that is based on the completion of the project and the contract administration liquidated damages rate (CALD).
Replaced by SP008-069 SP008-070 . (Change Memo: de-32-05). Statewide Use.
|
SP008-025 |
PDF |
RTF |
- Provides for a no excuse incentive that is based on the substantial completion of the project and the road user costs (RUC).
Replaced by SP008-069 SP008-070 . (Change Memo: de-31-05). Statewide Use.
|
SP008-024 |
PDF |
RTF |
- For project 6131-33-001 in Taylor County. Assess LD's on response time for callout work.
(Change Memo: de-28-96). One-Time Use.
|
SP008-023 |
PDF |
RTF |
- For project 0314-01-072 in Parker County. Incentive and disincentive for listed milestones.
One-Time Use.
|
SP008-022 |
PDF |
RTF |
- For project 0014-24-049 in Hill County. Roadway closures or ramp closures in phased construction need to be minimized due to their impacts to the traveling public.
One-Time Use.
|
SP008-021 |
PDF |
RTF |
- For project 6131-15-001 in Fisher County. Provides the ability to access liquidated damages on callout work.
One-Time Use.
|
SP008-020 |
PDF |
RTF |
- For project 6118-54-001 in Bowie County. If work is not completed within the specified time until completion, liquidated damages may be assessed
One-Time Use.
|
SP008-019 |
PDF |
RTF |
- For project 0720-03-084 in Harris County. Allows the State to suspend work without additional compensation to the Contractor.
One-Time Use.
|
SP008-018 |
PDF |
RTF |
- For project 0924-00-057 in Pecos, Presidio Counties. Outlines warranty requirements.
One-Time Use.
|
SP008-017 |
PDF |
RTF |
- Allows for a lane rental charge for each lane or lanes closed or obstructed by Contractor.
(Change Memo: de-02-05). Statewide Use.
|
SP008-016 |
PDF |
RTF |
- For project 1718-01-024 in Midland County. Incentives and disincentives of milestones.
One-Time Use.
|
SP008-015 |
PDF |
RTF |
- For project 1300-02-023 in Newton County. Update completion of work requirements for Phase 2 Construction.
One-Time Use.
|
SP008-014 |
PDF |
RTF |
- For project 1300-02-023 in Newton County. Credit for completion of work ahead of time for Phase 2 Construction.
One-Time Use.
|
SP008-013 |
PDF |
RTF |
- Lane closure assessment fees
Districtwide Use. Houston District, Austin District, Dallas District.
|
SP008-012 |
PDF |
RTF |
- For project 6113-59-001, 6117-37-001 in Taylor County. Provides for ability to charge LD's for response time on callout or work order contracts.
One-Time Use.
|
SP008-011 |
PDF |
RTF |
- Provides for open season for application of asphalt for selected projects. To be used for surface treatment-only, asphaltic-concrete-overlay-only and micro-surfacing-only contracts
(Change Memo: de-33-04). Statewide Use.
|
SP008-010 |
PDF |
RTF |
- Provides for full CPM schedule. May be used at the districts option.
Replaced by SP008-050 . (Change Memo: de-33-04). Statewide Use.
|
SP008-009 |
PDF |
RTF |
- Modifies Item 8 to allow work to start 180 days after authorization.
(Change Memo: de-22-04). Statewide Use.
|
SP008-008 |
PDF |
RTF |
- Modifies Item 8 to allow work to start 120 days after authorization.
(Change Memo: de-22-04). Statewide Use.
|
SP008-007 |
PDF |
RTF |
- Modifies Item 8 to allow work to start 90 days after authorization.
(Change Memo: de-22-04). Statewide Use.
|
SP008-006 |
PDF |
RTF |
- Modifies Item 8 to allow work to start 60 days after authorization.
(Change Memo: de-22-04). Statewide Use.
|
SP008-005 |
PDF |
RTF |
- Provides an incentive for early completion.
Replaced by SP008-069 SP008-070 . (Change Memo: de-20-04). Statewide Use.
|
SP008-004 |
PDF |
RTF |
- Provides for assessment of liquidated damages at the daily road user cost.
Replaced by SP008-069 SP008-070 . (Change Memo: de-20-04). Statewide Use.
|
SP008-003 |
PDF |
RTF |
- Provides for the start date for work to be shown on the plans.
Replaced by SP008-063 . (Change Memo: de-20-04). Statewide Use.
|
SP008-002 |
PDF |
RTF |
- Provides for a basic CPM schedule.
Replaced by SP008-049 . (Change Memo: de-20-04). Statewide Use.
|
SP008-001 |
PDF |
RTF |
- Provides for an incentive for substantially completing the project and or phases ahead of time.
Replaced by SP008-069 SP008-070 . (Change Memo: de-20-04). Statewide Use.
|