Monthly Local Let Maintenance Report For Atlanta District As Of Apr 12, 2024 Page 1 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBOWIE
HighwayIH0030
FromVARIOUS
To.
CSJ6240-43-001
Proj IDRMC - 624043001
Work TypeDEBRIS REMOVAL (NORTH)
 
124.00041600.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days306
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BENNIE JOHNSON CO.
SUBCONTRACTOR(S) FOR CCSJ: 6240-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05121901
Totals41600.000.000.000.0

CountyCASS
HighwaySH0155
FromVARIOUS ROADWAYS
ToIN THE LINDEN MAINTENANCE SECTION
CSJ6354-79-001
Proj IDMMC - 635479001
Work TypeMATERIALS ONLY, HMAC
 
0.001268150.00285284.00100.0
Work Order00-00-00
Work Began05-01-20
Work Completed04-25-21
Time Computed05-01-20
Contract Working Days120
Addl Days Granted240
Working Days Charged360
Percent Time Used100
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6354-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02201905
Totals268150.006582.44285284.00100.0

CountyBOWIE
HighwayIH0030
FromVARIOUS LOCATIONS IN THE NORTH
To.
CSJ6356-69-001
Proj IDRMC - 635669001
Work TypeCALLOUT CABLE SAFETY SYSTEM REPAIR
 
52.000189275.00802377.8799.9
Work Order00-00-00
Work Began05-01-20
Work Completed
Time Computed05-01-20
Contract Working Days613
Addl Days Granted613
Working Days Charged1,171
Percent Time Used95
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6356-69-001
TIMBERTEX, INC. (9.50)
Contract #02201910
Totals189275.00601.33802377.8799.9

CountyHARRISON
HighwayIH0020
FromVARIOUS LOCATIONS IN THE SOUTH
To.
CSJ6356-70-001
Proj IDRMC - 635670001
Work TypeCALLOUT CABLE SAFETY SYSTEM REPAIR
 
58.000238975.00796171.4099.9
Work Order04-24-20
Work Began05-01-20
Work Completed
Time Computed05-01-20
Contract Working Days613
Addl Days Granted613
Working Days Charged1,178
Percent Time Used96
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6356-70-001
TIMBERTEX, INC. (8.36)
Contract #02201907
Totals238975.0014821.15796171.4099.9

CountyMARION
HighwayUS0059
FromVARIOUS
ToVARIOUS
CSJ6358-67-001
Proj IDMMC - 635867001
Work TypeMATERIALS ONLY EMULSION
 
0.001190700.00272880.91100.0
Work Order00-00-00
Work Began06-01-20
Work Completed05-26-21
Time Computed06-01-20
Contract Working Days120
Addl Days Granted240
Working Days Charged360
Percent Time Used100
Contractor(s)
ERGON ASPHALT & EMULSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6358-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04201901
Totals190700.007064.85272880.91100.0

CountyUPSHUR
HighwayUS0271
From.
To.
CSJ6396-35-001
Proj IDSUP - 639635001
Work TypeGROUNDS MAINTENANCE
 
0.01012767.109612.7275.2
Work Order02-01-22
Work Began02-01-22
Work Completed
Time Computed02-01-22
Contract Working Days365
Addl Days Granted731
Working Days Charged790
Percent Time Used72
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-35-001
RUCON, INC. (100.00)
Contract #12211932
Totals12767.10286.769612.7275.2

CountyHARRISON
HighwaySL0390
From.
To.
CSJ6396-36-001
Proj IDSUP - 639636001
Work TypeGROUNDS MAINTENANCE
 
0.01022348.1230312.0799.9
Work Order02-01-22
Work Began02-01-22
Work Completed
Time Computed02-01-22
Contract Working Days365
Addl Days Granted731
Working Days Charged790
Percent Time Used72
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-36-001
RUCON, INC. (100.00)
Contract #12211933
Totals22348.122110.0030312.0799.9

CountyHARRISON
HighwaySL0390
From.
To.
CSJ6396-37-001
Proj IDSUP - 639637001
Work TypePICNIC AREA MAINTENANCE
 
0.01076353.90130835.7599.9
Work Order02-01-22
Work Began02-01-22
Work Completed
Time Computed02-01-22
Contract Working Days365
Addl Days Granted731
Working Days Charged790
Percent Time Used72
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6396-37-001
RUCON, INC. (100.00)
Contract #12211934
Totals76353.905556.85130835.7599.9

CountyMORRIS
HighwayUS0259
From.
To.
CSJ6399-69-001
Proj IDSUP - 639969001
Work TypeGROUNDS MAINTENANCE
 
0.0107440.008680.0099.9
Work Order03-30-22
Work Began04-01-22
Work Completed
Time Computed04-01-22
Contract Working Days365
Addl Days Granted731
Working Days Charged731
Percent Time Used66
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6399-69-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #02221931
Totals7440.00620.008680.0099.9

CountyMARION
HighwaySH0049
From.
To.
CSJ6406-45-001
Proj IDSUP - 640645001
Work TypeGROUNDS MAINTENANCE
 
0.01035075.0422652.6364.5
Work Order05-31-22
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged670
Percent Time Used91
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-45-001
RUCON, INC. (100.00)
Contract #04221931
Totals35075.041461.4622652.6364.5

CountyCASS
HighwaySH0008
From.
To.
CSJ6406-47-001
Proj IDSUP - 640647001
Work TypeGROUNDS MAINTENANCE
 
0.01016412.647864.3947.9
Work Order05-31-22
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged670
Percent Time Used91
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-47-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (100.00)
Contract #04221932
Totals16412.64341.937864.3947.9

CountyBOWIE
HighwaySH0008
From.
To.
CSJ6406-51-001
Proj IDSUP - 640651001
Work TypeGROUNDS MAINTENANCE
 
0.01026460.0019293.7572.9
Work Order05-31-22
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days731
Addl Days Granted0
Working Days Charged670
Percent Time Used91
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04221933
Totals26460.00551.2519293.7572.9

CountyHARRISON
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6406-53-001
Proj IDSUP - 640653001
Work TypeLITTER REMOVAL
 
0.010159221.37265464.3599.9
Work Order05-31-22
Work Began06-01-22
Work Completed
Time Computed06-01-22
Contract Working Days365
Addl Days Granted366
Working Days Charged670
Percent Time Used91
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6406-53-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #04221934
Totals159221.37770.40265464.3599.9

CountyTITUS
HighwayUS0271
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6411-91-001
Proj IDSUP - 641191001
Work TypeLITTER REMOVAL
 
0.010119265.66180874.7899.9
Work Order07-01-22
Work Began07-01-22
Work Completed
Time Computed07-01-22
Contract Working Days365
Addl Days Granted366
Working Days Charged640
Percent Time Used87
Contractor(s)
WORKQUEST
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6411-91-001
CAMP COUNTY SERVICE INDUSTRIES (100.00)
Contract #06221932
Totals119265.6620247.23180874.7899.9

CountyUPSHUR
HighwayUS0271
From.
To.
CSJ6411-99-001
Proj IDSUP - 641199001
Work TypeJANITORIAL MAINTENANCE
 
0.01013400.0420950.0799.9
Work Order06-15-22
Work Began07-01-22
Work Completed
Time Computed07-01-22
Contract Working Days365
Addl Days Granted366
Working Days Charged640
Percent Time Used87
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6411-99-001
A LIFT FOR LIFE OUTREACH, INC. (64.17)
Contract #06221931
Totals13400.041566.6720950.0799.9

CountyPANOLA
HighwayBU0059D
From.
To.
CSJ6414-19-001
Proj IDSUP - 641419001
Work TypeGROUNDS MAINTENANCE
 
0.01020027.6417830.6489.0
Work Order07-25-22
Work Began08-01-22
Work Completed
Time Computed08-01-22
Contract Working Days365
Addl Days Granted366
Working Days Charged609
Percent Time Used83
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6414-19-001
RUCON, INC. (100.00)
Contract #07221932
Totals20027.641024.5217830.6489.0

CountyHARRISON
HighwaySL0390
From.
To.
CSJ6416-45-001
Proj IDSUP - 641645001
Work TypeJANITORIAL MAINTENANCE
 
0.01028520.0040040.0099.9
Work Order07-27-22
Work Began08-01-22
Work Completed
Time Computed08-01-22
Contract Working Days365
Addl Days Granted366
Working Days Charged609
Percent Time Used83
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6416-45-001
A LIFT FOR LIFE OUTREACH, INC. (100.00)
Contract #07221933
Totals28520.001680.0040040.0099.9

CountyBOWIE
HighwayIH0030
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6432-40-001
Proj IDSUP - 643240001
Work TypeLITTER REMOVAL
 
0.01099455.09108369.7099.9
Work Order01-01-23
Work Began01-01-23
Work Completed
Time Computed01-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged456
Percent Time Used62
Contractor(s)
WORKQUEST
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6432-40-001
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS, INC. (100.00)
Contract #12221931
Totals99455.091227.61108369.7099.9

CountyMARION
HighwayUS0059
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6437-95-001
Proj IDRMC - 643795001
Work TypeTREE REMOVAL
 
0.010142028.00142023.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-11-23
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged18
Percent Time Used24
Contractor(s)
CEHAND SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6437-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231901
Totals142028.000.00142023.0099.9

CountyUPSHUR
HighwaySH0154
FromVARIOUS ROADWAYS
ToVARIOUS ROADWAYS
CSJ6438-01-001
Proj IDRMC - 643801001
Work TypeTREE TRIMMING
 
0.010140275.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
2H, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6438-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06231904
Totals140275.330.000.000.0

page 1 | page 2 | page 3