Monthly State Let Maintenance Report For Dallas District As Of Apr 12, 2024 Page 3 Of 7

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6415-68-001
Proj IDRMC - 641568001
Work TypePOTHOLE REPAIR
 
0.010429350.0095030.75100.0
Work Order02-21-23
Work Began02-28-23
Work Completed03-08-24
Time Computed02-28-23
Contract Working Days365
Addl Days Granted0
Working Days Charged363
Percent Time Used99
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6415-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224208
Totals429350.0011562.9595030.75100.0

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN THE WEST DALLAS
ToCOUNTY MAINTENANCE SECTIONS
CSJ6416-32-001
Proj IDRMC - 641632001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010738925.00617888.0083.6
Work Order02-24-23
Work Began02-24-23
Work Completed
Time Computed02-24-23
Contract Working Days365
Addl Days Granted180
Working Days Charged396
Percent Time Used72
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6416-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224009
Totals738925.0018425.00617888.0083.6

CountyDALLAS
HighwayIH0020
FromVARIOUS LOCATIONS IN THE EAST DALLAS
ToCOUNTY MAINTENANCE SECTIONS
CSJ6416-34-001
Proj IDRMC - 641634001
Work TypeTRAFFIC CONTROL SERVICES
 
0.010720035.00409433.7556.8
Work Order02-17-23
Work Began02-26-23
Work Completed
Time Computed02-26-23
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
FC TRAFFIC CONTROL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6416-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224209
Totals720035.000.00409433.7556.8

CountyDALLAS
HighwayIH0035E
FromVARIOUS LOCATIONS IN NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6416-50-001
Proj IDRMC - 641650001
Work TypeVEGETATION MANAGEMENT
 
0.010707234.00505944.00100.0
Work Order02-22-23
Work Began03-01-23
Work Completed03-08-24
Time Computed03-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged360
Percent Time Used98
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6416-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224210
Totals707234.000.00505944.00100.0

CountyDALLAS
HighwayIH0020
FromVARIOUS LOCATIONS IN EAST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6417-10-001
Proj IDRMC - 641710001
Work TypeVEGETATION MANAGEMENT
 
0.010925595.00649562.00100.0
Work Order03-16-23
Work Began03-01-23
Work Completed03-13-24
Time Computed03-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6417-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224011
Totals925595.000.00649562.00100.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6417-34-001
Proj IDRMC - 641734001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010883358.00547739.3062.0
Work Order09-14-23
Work Began09-24-23
Work Completed
Time Computed09-21-23
Contract Working Days365
Addl Days Granted0
Working Days Charged184
Percent Time Used50
Contractor(s)
DIGG COMMERCIAL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6417-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234604
Totals883358.0083277.60547739.3062.0

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN
ToNORTHWEST DALLAS COUNTY MAINTENANCE
CSJ6419-66-001
Proj IDRMC - 641966001
Work TypeCRASH CUSHION ATTENUATOR REPAIR
 
0.0101053913.001008801.0095.7
Work Order03-03-23
Work Began03-10-23
Work Completed
Time Computed03-10-23
Contract Working Days730
Addl Days Granted0
Working Days Charged382
Percent Time Used52
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6419-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234025
Totals1053913.006434.001008801.0095.7

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN DENTON COUNTY
ToDENTON COUNTY MAINTENANCE SECTION
CSJ6420-31-001
Proj IDBPM - 642031001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010700820.00222825.5731.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-04-24
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged11
Percent Time Used12
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6420-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234020
Totals700820.00222825.57222825.5731.7

CountyNAVARRO
HighwayIH0045
FromVARIOUS ROADWAYS IN THE
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6421-55-001
Proj IDRMC - 642155001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.0101683810.00896730.0053.2
Work Order05-16-23
Work Began05-23-23
Work Completed
Time Computed05-23-23
Contract Working Days730
Addl Days Granted0
Working Days Charged304
Percent Time Used41
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6421-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234243
Totals1683810.000.00896730.0053.2

CountyDALLAS
HighwayIH0045
FromON IH 45 IN
ToSOUTHEAST DALLAS COUNTY MAINTENANCE
CSJ6422-53-001
Proj IDRMC - 642253001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0101038731.00942654.37100.0
Work Order03-16-23
Work Began04-02-23
Work Completed03-15-24
Time Computed04-02-23
Contract Working Days365
Addl Days Granted0
Working Days Charged355
Percent Time Used97
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6422-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234026
Totals1038731.000.00942654.37100.0

CountyDALLAS
HighwayIH0030
FromVARIOUS ROADWAYS IN THE DALLAS
ToCOUNTY MAINTENANCE SECTIONS
CSJ6422-71-001
Proj IDRMC - 642271001
Work TypeDAY LABOR
 
0.010564021.00300723.8053.3
Work Order03-27-23
Work Began04-03-23
Work Completed
Time Computed04-03-23
Contract Working Days730
Addl Days Granted0
Working Days Charged358
Percent Time Used49
Contractor(s)
RHINO EQUITY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6422-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234225
Totals564021.0030969.00300723.8053.3

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN
ToEAST DALLAS COUNTY MAINTENANCE SECTIONS
CSJ6422-93-001
Proj IDRMC - 642293001
Work TypeREPAIR/REPLACE CONCRETE BARRIER
 
0.0101082175.00962587.9688.9
Work Order03-27-23
Work Began03-29-23
Work Completed
Time Computed03-29-23
Contract Working Days730
Addl Days Granted0
Working Days Charged363
Percent Time Used49
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6422-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234226
Totals1082175.00175.00962587.9688.9

CountyNAVARRO
HighwayFM3041
FromVARIOUS ROADWAYS IN THE
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6423-05-001
Proj IDRMC - 642305001
Work TypeREMOVAL AND DISPOSAL OF DRIFTWOOD
 
0.010385634.0094315.2224.4
Work Order04-14-23
Work Began04-21-23
Work Completed
Time Computed04-21-23
Contract Working Days730
Addl Days Granted0
Working Days Charged340
Percent Time Used46
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6423-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234020
Totals385634.003268.0094315.2224.4

CountyNAVARRO
HighwaySH0031
FromVARIOUS ROADWAYS IN THE
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6423-48-001
Proj IDRMC - 642348001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010691800.0079335.4511.4
Work Order05-04-23
Work Began05-11-23
Work Completed
Time Computed05-11-23
Contract Working Days730
Addl Days Granted0
Working Days Charged320
Percent Time Used43
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6423-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03234202
Totals691800.008451.3379335.4511.4

CountyCOLLIN
HighwayFM0544
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6424-60-001
Proj IDRMC - 642460001
Work TypeREFLECTIVE PAVEMENT MARKINGS (LONG LINE)
 
0.010745022.00633828.0885.0
Work Order09-11-23
Work Began09-25-23
Work Completed
Time Computed09-18-23
Contract Working Days50
Addl Days Granted0
Working Days Charged31
Percent Time Used62
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6424-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06234409
Totals745022.000.00633828.0885.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6424-64-001
Proj IDRMC - 642464001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
1156768.00906229.6878.3
Work Order01-26-23
Work Began02-02-23
Work Completed
Time Computed02-02-23
Contract Working Days730
Addl Days Granted0
Working Days Charged418
Percent Time Used57
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6424-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224217
Totals1156768.0049154.24906229.6878.3

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN KAUFMAN
ToMAINTENANCE SECTION
CSJ6424-80-001
Proj IDRMC - 642480001
Work TypeVEGETATION MANAGEMENT
 
0.0101475750.00690824.0046.8
Work Order03-29-23
Work Began03-29-23
Work Completed
Time Computed04-05-23
Contract Working Days730
Addl Days Granted0
Working Days Charged363
Percent Time Used49
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6424-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234024
Totals1475750.0010951.00690824.0046.8

CountyKAUFMAN
HighwayUS0175
FromVARIOUS ROADWAYS IN KAUFMAN
ToMAINTENANCE SECTION
CSJ6424-82-001
Proj IDRMC - 642482001
Work TypeVEGETATION MANAGEMENT
 
0.0101242886.00659985.0053.1
Work Order03-29-23
Work Began03-29-23
Work Completed
Time Computed04-05-23
Contract Working Days730
Addl Days Granted0
Working Days Charged363
Percent Time Used49
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6424-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234213
Totals1242886.000.00659985.0053.1

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN ROCKWALL
ToMAINTENANCE SECTION
CSJ6424-84-001
Proj IDRMC - 642484001
Work TypeVEGETATION MANAGEMENT
 
0.010755832.00344164.7045.5
Work Order04-19-23
Work Began04-19-23
Work Completed
Time Computed04-26-23
Contract Working Days730
Addl Days Granted0
Working Days Charged342
Percent Time Used46
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6424-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234214
Totals755832.009311.50344164.7045.5

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN
ToDALLAS COUNTY
CSJ6425-18-001
Proj IDRMC - 642518001
Work TypeGRAFFITI REMOVAL
 
0.010257050.00208108.1080.9
Work Order04-03-23
Work Began04-10-23
Work Completed
Time Computed04-10-23
Contract Working Days730
Addl Days Granted0
Working Days Charged351
Percent Time Used48
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6425-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234025
Totals257050.0016812.30208108.1080.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7