Monthly Local Let Maintenance Report For Fort Worth District As Of Apr 12, 2024 Page 2 Of 4

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayIH0020
FromSOUTH TARRANT OFFICE
ToSOUTH TARRANT OFFICE
CSJ6419-30-001
Proj IDSUP - 641930001
Work TypeGROUNDS MAINTENANCE
 
0.01011635.987033.3060.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6419-30-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #11220237
Totals11635.98362.017033.3060.4

CountyTARRANT
HighwayIH0030
FromVARIOUS LOCATIONS IN
ToSOUTH TARRANT
CSJ6421-23-001
Proj IDRMC - 642123001
Work TypeDELINEATORS
 
0.010114984.2566829.5058.1
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed05-15-23
Contract Working Days365
Addl Days Granted0
Working Days Charged238
Percent Time Used65
Contractor(s)
RHINO EQUITY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6421-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12220201
Totals114984.250.0066829.5058.1

CountyERATH
HighwayUS0067
FromVARIOUS LOCATIONS WITHIN
ToERATH, HOOD AND SOMERVELL COUNTIES
CSJ6435-64-001
Proj IDSUP - 643564001
Work TypePICNIC AREA MAINTENANCE
 
0.010116953.5484660.3872.3
Work Order00-00-00
Work Began02-15-23
Work Completed
Time Computed02-13-23
Contract Working Days365
Addl Days Granted0
Working Days Charged353
Percent Time Used96
Contractor(s)
WORKQUEST
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6435-64-001
FRESH START OF MONROE INC. (0.00)
Contract #01230231
Totals116953.540.0084660.3872.3

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER COUNTY
CSJ6438-21-001
Proj IDRMC - 643821001
Work TypeCLEANING AND SEALING CRACKS
 
0.010241000.00341591.6299.9
Work Order00-00-00
Work Began12-11-23
Work Completed
Time Computed12-11-23
Contract Working Days60
Addl Days Granted0
Working Days Charged48
Percent Time Used80
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6438-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10230201
Totals241000.0098591.62341591.6299.9

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER COUNTY
CSJ6440-18-001
Proj IDMMC - 644018001
Work TypeWINTER WEATHER MATERIAL
 
0.01032463.0031335.46100.0
Work Order00-00-00
Work Began09-26-23
Work Completed03-18-24
Time Computed09-21-23
Contract Working Days180
Addl Days Granted0
Working Days Charged180
Percent Time Used100
Contractor(s)
NSG LOGISTICS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6440-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08230203
Totals32463.000.0031335.46100.0

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToPARKER COUNTY
CSJ6440-34-001
Proj IDMMC - 644034001
Work TypeWINTER WEATHER MATERIAL
 
0.01054832.003427.00100.0
Work Order00-00-00
Work Began10-03-23
Work Completed03-22-24
Time Computed09-25-23
Contract Working Days180
Addl Days Granted0
Working Days Charged180
Percent Time Used100
Contractor(s)
THE BARGAIN SOURCE
SUBCONTRACTOR(S) FOR CCSJ: 6440-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08230204
Totals54832.000.003427.00100.0

CountyJOHNSON
HighwayFM2331
FromJOHNSON COUNTY
ToVARIOUS LIMITS
CSJ6442-44-001
Proj IDRMC - 644244001
Work TypeCRACK SEAL
 
0.010285232.11212469.0274.4
Work Order00-00-00
Work Began02-06-24
Work Completed
Time Computed01-15-24
Contract Working Days33
Addl Days Granted0
Working Days Charged22
Percent Time Used66
Contractor(s)
CRACKSEAL OF TEXAS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6442-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09230203
Totals285232.1159349.01212469.0274.4

CountyTARRANT
HighwayFM1220
FromNORTH TARRANT COUNTY
ToVARIOUS LIMITS
CSJ6442-80-001
Proj IDRMC - 644280001
Work TypeTURN LANE
 
0.010460484.50437531.0195.0
Work Order00-00-00
Work Began10-30-23
Work Completed
Time Computed10-30-23
Contract Working Days66
Addl Days Granted2
Working Days Charged42
Percent Time Used61
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6442-80-001
KING GEORGE TRAFFIC SOLUTIONS LLC (4.36)
TEXAS BOMANITE (4.83)
Contract #08230202
Totals460484.507380.00437531.0195.0

CountyTARRANT
HighwayIH0020
From2501 SW LOOP 820
To2501 SW LOOP 820
CSJ6444-92-001
Proj IDSUP - 644492001
Work TypeJANITORIAL MAINTENANCE
 
0.01087611.20142233.2099.9
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed05-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged214
Percent Time Used58
Contractor(s)
WORKQUEST
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6444-92-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #07230235
Totals87611.2019131.20142233.2099.9

CountyTARRANT
HighwayIH0020
From2501 SW LOOP 820
To2501 SW LOOP 820
CSJ6444-94-001
Proj IDSUP - 644494001
Work TypeJANITORIAL MAINTENANCE
 
0.01010028.0426741.4499.9
Work Order00-00-00
Work Began05-01-23
Work Completed
Time Computed06-01-23
Contract Working Days360
Addl Days Granted153
Working Days Charged245
Percent Time Used47
Contractor(s)
WORKQUEST
RISING STAR RESOURCE DEVELOPMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6444-94-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #07230231
Totals10028.043342.6826741.4499.9

CountyPARKER
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6445-51-001
Proj IDSUP - 644551001
Work TypeJANITORIAL MAINTENANCE
 
0.01026600.0022700.0085.3
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6445-51-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #07230238
Totals26600.001950.0022700.0085.3

CountyPALO PINTO
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6445-55-001
Proj IDSUP - 644555001
Work TypeJANITORIAL MAINTENANCE
 
0.01030300.0025562.5084.3
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed06-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6445-55-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #07230232
Totals30300.002275.0025562.5084.3

CountyTARRANT
HighwayIH0035W
FromVARIOUS
ToVARIOUS
CSJ6445-57-001
Proj IDSUP - 644557001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.01038937.5628736.9073.8
Work Order00-00-00
Work Began06-01-23
Work Completed
Time Computed07-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged284
Percent Time Used77
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6445-57-001
A LIFT FOR LIFE OUTREACH, INC. (0.00)
Contract #07230234
Totals38937.563122.0128736.9073.8

CountySOMERVELL
HighwaySH0144
FromVARIOUS
ToVARIOUS
CSJ6445-65-001
Proj IDSUP - 644565001
Work TypeJANITORIAL MAINTENANCE
 
0.01036890.0020740.0056.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged275
Percent Time Used75
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6445-65-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #07230236
Totals36890.003000.0020740.0056.2

CountyPALO PINTO
HighwayUS0180
FromVARIOUS LOCATIONS WITHIN
ToPALO PINTO COUNTY
CSJ6445-69-001
Proj IDRMC - 644569001
Work TypeCRACK SEAL
 
0.010224930.66207118.8192.0
Work Order00-00-00
Work Began02-19-24
Work Completed
Time Computed01-08-23
Contract Working Days90
Addl Days Granted0
Working Days Charged23
Percent Time Used25
Contractor(s)
CRACKSEAL OF TEXAS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6445-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09230201
Totals224930.66207118.81207118.8192.0

CountyERATH
HighwayBU0377J
From377 JUNCTION
To377 JUNCTION
CSJ6445-72-001
Proj IDSUP - 644572001
Work TypeJANITORIAL MAINTENANCE
 
0.01034830.0023140.0066.4
Work Order00-00-00
Work Began07-03-23
Work Completed
Time Computed07-03-23
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6445-72-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #07230237
Totals34830.002500.0023140.0066.4

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS WITHIN
ToWISE AND JACK COUNTIES
CSJ6446-06-001
Proj IDRMC - 644606001
Work TypeCLEANING AND SEALING CRACKS
 
0.010222198.6481711.1236.7
Work Order00-00-00
Work Began02-28-24
Work Completed
Time Computed11-10-23
Contract Working Days31
Addl Days Granted0
Working Days Charged21
Percent Time Used67
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08230201
Totals222198.6481711.1281711.1236.7

CountyJACK
HighwayUS0380
FromVARIOUS LOCATIONS WITHIN
ToJACK AND WISE COUNTIES
CSJ6446-30-001
Proj IDMMC - 644630001
Work TypeDENSE GRADED HOT MIX
 
0.010253000.0069958.8427.6
Work Order00-00-00
Work Began09-26-23
Work Completed
Time Computed09-26-23
Contract Working Days180
Addl Days Granted0
Working Days Charged182
Percent Time Used101
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 6446-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08230205
Totals253000.009573.2069958.8427.6

CountyERATH
HighwayUS0377
FromVARIOUS LOCATIONS IN
ToERATH, HOOD AND SOMERVELL COUNTIES
CSJ6447-80-001
Proj IDRMC - 644780001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010241400.00118800.0049.2
Work Order00-00-00
Work Began03-02-24
Work Completed
Time Computed01-18-24
Contract Working Days365
Addl Days Granted0
Working Days Charged68
Percent Time Used18
Contractor(s)
PREMIER CONTRACTORS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6447-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11230201
Totals241400.00118800.00118800.0049.2

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN
ToWISE & JACK COUNTIES
CSJ6448-67-001
Proj IDRMC - 644867001
Work TypeREFLECTORIZED PAVEMENT MARKINGS & MARKE
 
0.010272370.0049504.9018.1
Work Order00-00-00
Work Began01-29-24
Work Completed
Time Computed11-14-23
Contract Working Days365
Addl Days Granted0
Working Days Charged133
Percent Time Used36
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6448-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09230207
Totals272370.000.0049504.9018.1

page 1 | page 2 | page 3 | page 4