Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | CAMERON |
Highway | SH 100 |
From | S. MESQUITE ST. |
To | 567 FT. EAST OF EBANO ST. |
CSJ | 0331-01-052 |
Proj ID | NH 2021(193) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 0.900 | 4728315.84 | | 5122881.63 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 03-18-21 |
Work Began | 04-19-21 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 237 |
Addl Days Granted | 210 |
Working Days Charged | 466 |
Percent Time Used | 104 |
Contractor(s) |
EARTHWORKS ENTERPRISE |
SUBCONTRACTOR(S) FOR CCSJ: 0331-01-052 GO UNDERGROUND, LIMITED LIABILITY COMPANY (2.44) GP7 CONSTRUCTION INC. (0.77) SOIL TECH ADVANCE INC. (0.34) TEXAS HIGHWAY SYSTEMS, INC. (2.18) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (2.33) PAVEMENT MARKINGS INC. (3.53)
|
Contract # | 11203202 |
| Totals | 4728315.84 | 52826.62 | 5122881.63 | 99.9 |
|
County | CAMERON |
Highway | SH 100 |
From | SH 48 |
To | QUEEN ISABELLA CAUSEWAY |
CSJ | 0331-02-059 |
Proj ID | C 331-2-59 |
Work Type | OVERLAY |
|
| 1.480 | 1416470.40 | | 0.00 | 0.0 |
County | CAMERON |
Highway | PR 100 |
From | ORCA CIRCLE |
To | QUEEN ISABELLA CAUSEWAY |
CSJ | 0331-04-073 |
Proj ID | C 331-4-73 |
Work Type | OVERLAY |
|
| 4.215 | 4482134.00 | | 0.00 | 0.0 |
County | CAMERON |
Highway | SL 499 |
From | BU 77X |
To | IH 69E |
CSJ | 1137-01-032 |
Proj ID | C 1137-1-32 |
Work Type | OVERLAY |
|
| 1.020 | 719232.10 | | 0.00 | 0.0 |
County | CAMERON |
Highway | SL 499 |
From | FM 106 |
To | BU 77X |
CSJ | 1137-02-042 |
Proj ID | C 1137-2-42 |
Work Type | OVERLAY |
|
| 1.384 | 1147728.90 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 04-11-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 135 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
FOREMOST PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0331-02-059 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01243014 |
| Totals | 7765565.40 | 0.00 | 0.00 | 0.0 |
|
County | CAMERON |
Highway | PR 100 |
From | AT QUEEN ISABELLA CAUSEWAY |
To | STR #:_0331-04-005 |
CSJ | 0331-04-069 |
Proj ID | BR 2020(709) |
Work Type | BRIDGE MAINTENANCE |
|
| 2.639 | 9814198.00 | | 13793271.85 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-09-20 |
Work Began | 10-19-20 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 576 |
Addl Days Granted | 170 |
Working Days Charged | 685 |
Percent Time Used | 91 |
Contractor(s) |
SOUTHERN ROAD & BRIDGE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0331-04-069 MOBILE ENTERPRISES, INC. (3.60) PAVEMENT MARKINGS INC. (0.74)
|
Contract # | 04203206 |
| Totals | 9814198.00 | 660887.01 | 13793271.85 | 99.9 |
|
County | HIDALGO |
Highway | SH 107 |
From | 59TH STREET |
To | SEAWALL BLVD |
CSJ | 0342-01-074 |
Proj ID | STP 2019(085) |
Work Type | CONST 6 LN DIV RURAL |
|
| 7.075 | 20492319.77 | | 17169360.38 | 83.7 |
County | HIDALGO |
Highway | SH 107 |
From | 0.7 MI W OF FM 2128 |
To | 0.4 MI W OF FM 2128 |
CSJ | 0342-01-088 |
Proj ID | STP 2019(084)HES |
Work Type | SAFETY LIGHTING |
|
| 1.101 | 321205.00 | | 0.00 | 0.0 |
County | HIDALGO |
Highway | SH 107 |
From | @ FM 1423 |
To | . |
CSJ | 0342-01-089 |
Proj ID | STP 2019(084)HES |
Work Type | IMPROVE TRAFFIC SIGNAL |
|
| 0.200 | 121038.60 | | 36989.00 | 30.5 |
County | HIDALGO |
Highway | SH 107 |
From | @ FM 907 |
To | . |
CSJ | 0342-01-090 |
Proj ID | STP 2019(084)HES |
Work Type | IMPROVE TRAFFIC SIGNAL |
|
| 0.200 | 169327.80 | | 101517.89 | 59.9 |
Work Order | 04-16-19 |
Work Began | 05-03-21 |
Work Completed | |
Time Computed | 05-25-20 |
Contract Working Days | 461 |
Addl Days Granted | 240 |
Working Days Charged | 499 |
Percent Time Used | 71 |
Contractor(s) |
FOREMOST PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0342-01-074 GP7 CONSTRUCTION INC. (13.50) HIGHWAY BARRICADES AND SERVICES, LLC (1.85) SOIL-TECH, INC. (0.54) TRAF-TEX, INC. (6.59) RIO GRANDE REBAR RODBUSTERS, LLC. (0.03) SOIL TECH ADVANCE INC. (0.54) G & E ESCOBEDO CONSTRUCTION, INC. (0.00)
|
Contract # | 03193203 |
| Totals | 21103891.17 | 772824.64 | 17307867.27 | 82.0 |
|
County | CAMERON |
Highway | SH 107 |
From | LOUISIANA ST. |
To | HOOKS E. HODGES RD. |
CSJ | 0342-03-037 |
Proj ID | C 342-3-37 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 1.000 | 5460340.75 | | 1667367.77 | 30.5 |
County | CAMERON |
Highway | SH 107 |
From | LOUISIANA ST. |
To | HOOKS E. HODGES RD. |
CSJ | 0342-03-041 |
Proj ID | ROW 342-3-41 |
Work Type | RIGHT OF WAY |
|
| 1.000 | 90736.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 11-01-23 |
Work Began | 12-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 225 |
Addl Days Granted | 0 |
Working Days Charged | 80 |
Percent Time Used | 35 |
Contractor(s) |
TEXAS CORDIA CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0342-03-037 PAVEMENT MARKINGS INC. (1.82) DUSTROL, INC. (5.41) EXTERIOR DESIGNS (1.36) AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (5.43)
|
Contract # | 08233005 |
| Totals | 5551076.75 | 292117.81 | 1667367.77 | 30.0 |
|
County | WILLACY |
Highway | SH 186 |
From | HIDALGO/ WILLACY C.L. |
To | KING ST |
CSJ | 0433-02-052 |
Proj ID | C 433-2-52 |
Work Type | REHABILITATE ROADWAY (SUPER 2) |
|
| 12.296 | 20899927.85 | | 23166413.77 | 99.9 |
Work Order | 09-18-18 |
Work Began | 01-07-19 |
Work Completed | |
Time Computed | 10-18-18 |
Contract Working Days | 560 |
Addl Days Granted | 551 |
Working Days Charged | 1,146 |
Percent Time Used | 103 |
Contractor(s) |
ASAGO, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0433-02-052 AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.52) HIGHWAY BARRICADES AND SERVICES, LLC (3.78) GULF COAST CONTRACTORS, INC. (0.73)
|
Contract # | 08183008 |
| Totals | 20899927.85 | 565392.77 | 23166413.77 | 99.9 |
|
County | JIM HOGG ETC |
Highway | SH 16 ETC |
From | 0.22 MI S OF SIESTA RD. |
To | JIM HOGG/ZAPATA COUNTY LINE |
CSJ | 0517-06-036 |
Proj ID | STP 2B20(155)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 148.414 | 4952063.28 | | 3751764.42 | 77.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 09-18-20 |
Work Began | 03-08-21 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 256 |
Addl Days Granted | 0 |
Working Days Charged | 371 |
Percent Time Used | 144 |
Contractor(s) |
ATLANTIC SPECIALTY INSURANCE COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0517-06-036 DEPENDABLE FENCE & WELDING CO. INC. (10.09) HIGHWAY BARRICADES AND SERVICES, LLC (0.18) TEXAS ICON CONSTRUCTION, LLC (30.18) TERRA CONSTRUCTION LLC (6.87) JMG CONCRETE INC (5.91) TREBOL TRAFFIC SAFETY GROUP LLC (3.63) HJC FARMS, INC. (74.52)
|
Contract # | 08203016 |
| Totals | 4952063.28 | 0.00 | 3751764.42 | 77.4 |
|
County | HIDALGO |
Highway | FM 681 |
From | 0.1 MILES W. OF INSPIRATION RD. |
To | 0.1 MILES E. OF INSPIRATION RD. |
CSJ | 0669-01-066 |
Proj ID | STP 2B23(015)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 290587.40 | | 79125.50 | 27.2 |
County | STARR |
Highway | FM 755 |
From | 0.1 MILES NE OF FLORES ST. |
To | 0.1 MILES SW OF FLORES ST. |
CSJ | 1103-05-002 |
Proj ID | STP 2B23(015)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 254170.10 | | 246105.00 | 96.8 |
County | HIDALGO |
Highway | FM 2128 |
From | 0.1 MILES W. OF TERRY RD. |
To | 0.1 MILES E. OF TERRY RD. |
CSJ | 2450-01-026 |
Proj ID | STP 2B23(015)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 218831.60 | | 7527.50 | 3.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-12-23 |
Work Began | 02-12-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 100 |
Addl Days Granted | 0 |
Working Days Charged | 30 |
Percent Time Used | 30 |
Contractor(s) |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0669-01-066 RIO GRANDE CONSTRUCTORS AND CONSTRUCTION MANAGEMENT LLC (2.97) PAVEMENT MARKINGS INC. (8.72) G & E ESCOBEDO CONSTRUCTION, INC. (4.38) SOUTH TEXAS DRILLING, LLC (0.71)
|
Contract # | 06233057 |
| Totals | 763589.10 | 129307.00 | 332758.00 | 43.5 |
|
County | HIDALGO |
Highway | FM 2221 |
From | 0.1 MILES W. OF QUEEN PALM DR. |
To | 0.1 MILES E. OF QUEEN PALM DR. |
CSJ | 0669-03-029 |
Proj ID | STP 2B23(014)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 80576.40 | | 183815.40 | 99.9 |
County | HIDALGO |
Highway | FM 2221 |
From | 0.1 MILES W. OF ABRAM RD. |
To | 0.1 MILES E. OF ABRAM RD. |
CSJ | 0669-03-030 |
Proj ID | STP 2B23(014)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 245711.30 | | 0.00 | 0.0 |
County | HIDALGO |
Highway | FM 492 |
From | 0.1 MILES N. OF MILE 6 RD. |
To | 0.1 MILES S. OF MILE 6 RD. |
CSJ | 0862-01-066 |
Proj ID | STP 2B23(014)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 221860.90 | | 0.00 | 0.0 |
County | HIDALGO |
Highway | FM 1924 |
From | 0.1 MILES WEST OF SCHUERBACH RD. |
To | 0.1 MILES EAST OF SCHUERBACH RD. |
CSJ | 1802-01-046 |
Proj ID | STP 2B23(014)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 254565.35 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-12-23 |
Work Began | 03-08-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 29 |
Percent Time Used | 24 |
Contractor(s) |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0669-03-029 PAVEMENT MARKINGS INC. (5.24) G & E ESCOBEDO CONSTRUCTION, INC. (5.00) RIO GRANDE CONSTRUCTORS AND CONSTRUCTION MANAGEMENT LLC (4.67) MUNOZ FOUNDATION DRILLING, INC. (2.27)
|
Contract # | 06233017 |
| Totals | 802713.95 | 22422.00 | 183815.40 | 22.8 |
|
County | CAMERON ETC |
Highway | FM 511 ETC |
From | OLD PORT ISABEL RD. |
To | CHARMAINE LANE |
CSJ | 0684-01-073 |
Proj ID | F 2024(006) |
Work Type | SEAL COAT |
|
| 30.193 | 4012543.76 | | 920022.06 | 22.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-23-23 |
Work Began | 03-20-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 100 |
Addl Days Granted | 0 |
Working Days Charged | 6 |
Percent Time Used | 6 |
Contractor(s) |
CLARK CONSTRUCTION OF TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0684-01-073 CENTERLINE TECHNOLOGIES, LLC (20.64) FLASHER EQUIPMENT COMPANY (2.30)
|
Contract # | 09233222 |
| Totals | 4012543.76 | 920022.06 | 920022.06 | 22.9 |
|
County | HIDALGO |
Highway | FM 491 |
From | CR 1390 |
To | FM 1425 |
CSJ | 0861-01-068 |
Proj ID | STP 2022(723)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 3701235.71 | | 3617588.88 | 99.0 |
Work Order | 07-27-22 |
Work Began | 09-19-22 |
Work Completed | |
Time Computed | 09-29-22 |
Contract Working Days | 180 |
Addl Days Granted | 5 |
Working Days Charged | 235 |
Percent Time Used | 127 |
Contractor(s) |
ASAGO, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0861-01-068 HIGHWAY BARRICADES AND SERVICES, LLC (2.21) TEXAS ICON CONSTRUCTION, LLC (0.98)
|
Contract # | 06223415 |
| Totals | 3701235.71 | 2275.00 | 3617588.88 | 99.0 |
|
County | HIDALGO |
Highway | FM 492 |
From | .25 MI N OF BUS 83 |
To | @ EDINBURG MAIN CANAL |
CSJ | 0862-01-057 |
Proj ID | BR 2023(199) |
Work Type | BRIDGE REPLACEMENT |
|
| | 1208880.90 | | 1215159.13 | 99.9 |
County | CAMERON |
Highway | FM 732 |
From | 2.0 MI NE OF US 281 |
To | @ DRAINAGE DTICH |
CSJ | 1057-02-031 |
Proj ID | BR 2023(199) |
Work Type | BRIDGE REPLACEMENT |
|
| | 708782.60 | | 636843.54 | 89.8 |
Work Order | 12-07-22 |
Work Began | 01-06-23 |
Work Completed | |
Time Computed | 12-07-22 |
Contract Working Days | 159 |
Addl Days Granted | 0 |
Working Days Charged | 192 |
Percent Time Used | 120 |
Contractor(s) |
TEXAS CORDIA CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0862-01-057 HIGHWAY BARRICADES AND SERVICES, LLC (0.43) SOIL TECH ADVANCE INC. (1.40) HOUSTON SAWING & DRILLING (0.23) GREGORY PILE DRIVING, INC. (12.40) DEPENDABLE FENCE (5.66) RIO GRANDE REBAR RODBUSTERS, LLC. (0.20) TNT CRANE & RIGGING, INC. (0.45)
|
Contract # | 11223218 |
| Totals | 1917663.50 | 15823.83 | 1852002.67 | 98.0 |
|
County | CAMERON |
Highway | FM 506 |
From | BUS 83 |
To | FM 3067 |
CSJ | 0872-04-030 |
Proj ID | C 872-4-30 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 3.030 | 7719200.93 | | 2274027.16 | 29.4 |
County | CAMERON |
Highway | FM 800 |
From | FM 1479 |
To | FM 509 |
CSJ | 1136-02-053 |
Proj ID | C 1136-2-53 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 1.700 | 4776267.76 | | 4261837.88 | 89.2 |
County | CAMERON |
Highway | FM 1479 |
From | FM 800 |
To | FM 675 |
CSJ | 1425-04-023 |
Proj ID | C 1425-4-23 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 1.600 | 3290303.75 | | 3138072.40 | 95.3 |
Work Order | 10-11-22 |
Work Began | 01-10-23 |
Work Completed | |
Time Computed | 11-10-22 |
Contract Working Days | 554 |
Addl Days Granted | 0 |
Working Days Charged | 270 |
Percent Time Used | 48 |
Contractor(s) |
FOREMOST PAVING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0872-04-030 AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. (0.08) HIGHWAY BARRICADES AND SERVICES, LLC (1.06) SOIL TECH ADVANCE INC. (0.95) SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.67) RIO GRANDE REBAR RODBUSTERS, LLC. (0.04)
|
Contract # | 09223201 |
| Totals | 15785772.44 | 796575.51 | 9673937.44 | 61.2 |
|
County | HIDALGO |
Highway | VA |
From | US CUSTOMS PORT OF ENTRY EXIT |
To | US 281 |
CSJ | 0921-02-173 |
Proj ID | BOR 2002(632) |
Work Type | CONSTRUCT BSIF |
|
| 1.350 | 20116428.45 | | 29917534.49 | 99.9 |
Work Order | 08-25-11 |
Work Began | 10-18-11 |
Work Completed | |
Time Computed | 09-10-11 |
Contract Working Days | 380 |
Addl Days Granted | 753 |
Working Days Charged | 1,133 |
Percent Time Used | 100 |
Contractor(s) |
ANDERSON COLUMBIA CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-173 BULLARD CONSTRUCTION, INC. (19.38) HIGHWAY TECHNOLOGIES, INC. (1.61) HURRICANE FENCE COMPANY (0.96) METTLER TOTLEDO (5.03) NORTH TEXAS REBAR, LLC (0.54) ROVAN, LLC (3.33) SOIL-TECH, INC. (1.21) STAR OPERATIONS, INC. (19.28) TSI LABORATORIES SOUTH,INC. (0.04) RGV ALLIANCE CONSTRUCTION, LLC (0.54) FOREMOST PAVING, INC. (9.34) CONTINENTAL REFRIGERATION (1.12) M & A PAINTING SERVICE, INC. (0.39) L & G CONCRETE CONSTRUCTION, INC. (3.86) SOUTHERN STEEL FABRICATORS (4.27) CANTU"S PLUMBING (0.88) METRO ELECTRIC, INC. (1.81) ROUND ROCK INDUSTRIAL EQUIPMENT COMPANY, INC. (0.07) INTERTECH FLOORING (0.33) WEIGHT AND TEST SOLUTIONS, INC. (0.70) RGV ALLIANCE CONSTRUCTION, LLC (0.12) MCALLEN PEST CONTROL (0.03) THE CABINET SHOP (0.24) PRIME CONSTRUCTION (0.10) TAYLOR LIGHTNING PROTECTION (0.14) TAMU, DBA CONSTRUCTION SPECIALTIES (0.37) T & D SOLUTIONS, LTD (0.87) THE LEVY COMPANY, INC. (0.08) RIO GRANDE REBAR RODBUSTERS, LLC. (0.16)
|
Contract # | 07113207 |
| Totals | 20116428.45 | 175353.16 | 29917534.49 | 99.9 |
|
County | HIDALGO |
Highway | CR |
From | DOOLITTLE RD., 1.71 MI N OF FM 1925 |
To | STR# AA01-82-001 @ N MAIN DITCH |
CSJ | 0921-02-387 |
Proj ID | BR 2021(458) |
Work Type | BRIDGE REPLACEMENT |
|
| | 1531693.55 | | 1071622.80 | 69.9 |
County | CAMERON |
Highway | CS |
From | ON TEEGE RD, .30 MI W OF JCT IH-69E |
To | STR #:AA16-48-001 @ DRAINAGE DITCH |
CSJ | 0921-06-302 |
Proj ID | BR 2021(460) |
Work Type | BRIDGE REPLACEMENT |
|
| | 777989.70 | | 841769.64 | 99.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 03-16-23 |
Work Began | 06-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 221 |
Addl Days Granted | 0 |
Working Days Charged | 181 |
Percent Time Used | 81 |
Contractor(s) |
LUCANIA CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-387 PAVEMENT MARKINGS INC. (0.36) GREGORY PILE DRIVING, INC. (8.07) TEXAS HIGHWAY SYSTEMS, INC. (0.85)
|
Contract # | 02233243 |
| Totals | 2309683.25 | 173982.61 | 1913392.44 | 82.8 |
|
County | HIDALGO |
Highway | CR |
From | VARIOUS |
To | VARIOUS |
CSJ | 0921-02-465 |
Proj ID | C 921-2-465 |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 5092399.00 | | 5016054.97 | 98.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 10-14-21 |
Work Began | 09-19-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 160 |
Addl Days Granted | 45 |
Working Days Charged | 126 |
Percent Time Used | 61 |
Contractor(s) |
TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-465 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08213221 |
| Totals | 5092399.00 | 0.00 | 5016054.97 | 98.5 |
|
County | HIDALGO |
Highway | VA |
From | VARIOUS LOCATIONS IN HIDALGO COUNTY |
To | . |
CSJ | 0921-02-483 |
Proj ID | STP 2022(728)HES |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 1287240.20 | | 1230933.40 | 95.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-11-22 |
Work Began | 11-08-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 239 |
Addl Days Granted | 0 |
Working Days Charged | 175 |
Percent Time Used | 73 |
Contractor(s) |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-483 PAVEMENT MARKINGS INC. (6.12) TEXAS HIGHWAY SYSTEMS, INC. (13.25) G & E ESCOBEDO CONSTRUCTION, INC. (2.95)
|
Contract # | 05223240 |
| Totals | 1287240.20 | 0.00 | 1230933.40 | 95.6 |
|
County | HIDALGO |
Highway | CS ETC |
From | CESAR CHAVEZ RD. |
To | @ RIDGE RD. |
CSJ | 0921-02-484 |
Proj ID | STP 2B23(007)HESG |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 0.400 | 307597.50 | | 106041.00 | 34.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 07-26-23 |
Work Began | 02-29-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 147 |
Addl Days Granted | 0 |
Working Days Charged | 23 |
Percent Time Used | 15 |
Contractor(s) |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-484 PAVEMENT MARKINGS INC. (4.31)
|
Contract # | 06233646 |
| Totals | 307597.50 | 20710.00 | 106041.00 | 34.4 |
|
County | HIDALGO |
Highway | CS |
From | M RD. |
To | 17 1/2 N. RD. |
CSJ | 0921-02-489 |
Proj ID | STP 2B23(205)HESG |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 41633.60 | | 0.00 | 0.0 |
County | HIDALGO |
Highway | CS |
From | 0.1 MILES WEST OF MON MACK RD. |
To | 0.1 MILES EAST OF MON MACK RD. |
CSJ | 0921-02-500 |
Proj ID | STP 2B23(008)HESG |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 181799.41 | | 72047.31 | 39.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 08-17-23 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 96 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
THE LEVY COMPANY, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-489 HIGHWAY BARRICADES AND SERVICES, LLC (1.81) TEXAS HIGHWAY SYSTEMS, INC. (2.81)
|
Contract # | 06233647 |
| Totals | 223433.01 | 24140.04 | 72047.31 | 32.2 |
|
County | HIDALGO |
Highway | CS |
From | 0.1 MILES WEST OF TROSPER RD. |
To | 0.1 MILES EAST OF TROSPER RD. |
CSJ | 0921-02-507 |
Proj ID | STP 2024(931)VRU |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 587133.38 | | 0.00 | 0.0 |
County | HIDALGO |
Highway | CR |
From | 0.1 MILES WEST OF WESTERN RD. |
To | 0.1 MILES EAST OF WESTERN RD. |
CSJ | 0921-02-510 |
Proj ID | STP 2B24(137)HESG |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| | 193253.90 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TRAF-TEX, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0921-02-507 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04243233 |
| Totals | 780387.28 | 0.00 | 0.00 | 0.0 |
|