Monthly State Let Construction Report For San Antonio District As Of Apr 12, 2024 Page 4 Of 7

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
HighwaySH 218
FromAT LP 1604
To.
CSJ0465-01-059
Proj IDC 465-1-59
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
0.233611416.50336672.5355.0
Work Order08-03-23
Work Began09-11-23
Work Completed
Time Computed09-11-23
Contract Working Days120
Addl Days Granted0
Working Days Charged77
Percent Time Used64
Contractor(s)
DIAMOND R CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0465-01-059
JT UNDERGROUND AND UTILITY CONSTRUCTION INC (9.71)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (2.61)
BIG TREE LANDSCAPE & TRUCKING (5.72)
BETO SPRINKLERS (14.80)
Contract #06233248
Totals611416.502500.00336672.5355.0

CountyBEXAR
HighwayFM 1518
FromFM 78
ToIH 10 E
CSJ0465-02-027
Proj IDSTP 2023(954)MM
Work TypeWIDEN NON-FREEWAY
 
5.58063132032.13159980.100.2
CountyBEXAR
HighwayFM 1518
FromFM 78
ToIH 10 E
CSJ0465-02-028
Proj IDROW 465-2-28
Work TypeRIGHT OF WAY
 
5.5809648002.450.000.0
Work Order12-05-23
Work Began00-00-00
Work Completed
Time Computed03-04-24
Contract Working Days780
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0465-02-027
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.69)
E-Z BEL CONSTRUCTION, LLC (1.83)
DEPENDABLE FENCE (0.16)
TEX OP CONSTRUCTION, LP (1.20)
BADECO, INC. (2.66)
BEAIRD DRILLING (0.57)
Contract #10233002
Totals72780034.5838100.10159980.100.2

CountyBEXAR
HighwayIH 410
FromINGRAM RD.
ToUS 90
CSJ0521-04-204
Proj IDNH 1902(215)
Work TypeWF
 
6.34077171883.2780519308.7099.9
CountyBEXAR
HighwayIH 410
FromINGRAM RD.
ToUS 90
CSJ0521-04-282
Proj IDROW 521-4-282
Work TypeRIGHT OF WAY
 
6.340161000.000.000.0
Work Order07-30-19
Work Began08-29-19
Work Completed
Time Computed08-29-19
Contract Working Days805
Addl Days Granted177
Working Days Charged980
Percent Time Used99
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-04-204
FLASHER EQUIPMENT COMPANY (1.59)
CPAVE, INC. (0.23)
SCOTT DERR PAINTING CO, LLC (0.10)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.04)
LONE STAR EROSION CONTROL (0.19)
F & W ELECTRICAL CONTRACTORS, INC. (5.04)
ROYAL REBAR (6.28)
ROADWAY SPECIALTIES, INC. (0.78)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.46)
2 J RESOURCES COMPANY (3.74)
BUYERS BARRICADES SAN ANTONIO, LLC (0.47)
Z & L CONCRETE CONTRACTORS, INC. (0.04)
Contract #07193001
Totals77332883.2731036.4580519308.7099.9

CountyBEXAR
HighwayIH 410
FromFM 2536 -PEARSALL ROAD
ToVALLEY HI DRIVE
CSJ0521-05-148
Proj IDSTP 2021(486)MM
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
3.60019004542.7622140475.2199.9
CountyBEXAR
HighwayIH 410
FromFM 2536 -PEARSALL ROAD
ToVALLEY HI DRIVE
CSJ0521-05-152
Proj IDROW 521-5-152
Work TypeRIGHT OF WAY
 
3.60069485.6260172.8686.5
CountyBEXAR
HighwayIH 410
FromFM 2536-PEARSALL RD
ToUS 90
CSJ0521-05-156
Proj IDC 521-5-156
Work TypeOVERLAY
 
4.3043223557.402543636.7678.9
Work Order05-20-21
Work Began07-19-21
Work Completed
Time Computed06-21-21
Contract Working Days540
Addl Days Granted109
Working Days Charged644
Percent Time Used99
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0521-05-148
COX COMMERCIAL CONSTRUCTION LLC (1.84)
FLASHER EQUIPMENT COMPANY (1.92)
SOUTHEAST HIGHWAY GUARDRAIL & ATTENUATORS, LLC (1.29)
EARTH REINFORCEMENTS LLC (3.42)
L&H ELECTRICAL, LLC (6.31)
SCOTT DERR PAINTING CO, LLC (0.15)
ADCOCK 4 INVESTMENTS, LLC (6.81)
FOX QUALITY CONCRETE, L.L.C. (0.00)
PRIMATE CONSTRUCTION, LP (0.28)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.48)
RAM II GENERAL CONTRACTOR, INC. (0.33)
CAPITAL EXCAVATION COMPANY (3.42)
GULF COAST FIBER SERVICES, L.L.C. (0.00)
THE LEVY COMPANY, INC. (0.06)
ELITECURB & CONCRETE, LLC (1.75)
BK FIELD OPERATIONS LLC (0.00)
FUQUAY, INC. (3.64)
GIBSON & ASSOCIATES, INC. (0.61)
BOEN LANDSCAPING & IRRIGATION, LLC (0.04)
BK FIELD OPERATIONS LLC (0.44)
SERNA"S TRUCKING (0.02)
BUYERS BARRICADES SAN ANTONIO, LLC (0.01)
DRILL TECH DRILLING & SHORING, INC. (2.12)
Contract #04213204
Totals22297585.78675133.7424744284.8399.9

CountyBEXAR
HighwayIH 410
FromAT IH 10 E
To.
CSJ0521-06-138
Proj IDF 2021(404)
Work TypeINTERCHANGE (NEW OR RECONSTRUCTED)
 
1.00095603519.1076706261.2880.2
CountyBEXAR
HighwayIH 410
FromAT IH 10 E
To.
CSJ0521-06-140
Proj IDNH 2019(214)
Work TypeRIGHT OF WAY
 
1.0004599151.494728453.0399.9
Work Order04-05-21
Work Began07-15-21
Work Completed
Time Computed07-04-21
Contract Working Days968
Addl Days Granted223
Working Days Charged829
Percent Time Used69
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0521-06-138
FLASHER EQUIPMENT COMPANY (0.45)
THE LEVY COMPANY, INC. (4.09)
DEPENDABLE FENCE (1.34)
Z & L CONCRETE CONTRACTORS, INC. (2.87)
LONE STAR EROSION CONTROL (0.17)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.82)
ROYAL REBAR (5.70)
SCOTT DERR PAINTING CO, LLC (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.10)
EGGEMEYER LAND CLEARING, LLC (0.02)
URETEK USA, INC. (0.45)
BADECO, INC (0.15)
CHEROKEE SERVICES (0.11)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.07)
LIGHT IT UP ELECTRIC (0.00)
COX PAVING COMPANY OF TEXAS, INC. (0.22)
DC CIVIL CONSTRUCTION, LLC (3.72)
ELLIS AND ELLIS (0.00)
CALAME CONTRACTING, LLC (0.00)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.00)
ROADWAY CONSTRUCTION, LLC (0.43)
SK CONCRETE SERVICES LLC (0.00)
ROADWAY SPECIALTIES, INC. (0.13)
SWEEPING CORPORATION OF AMERICA, LLC (0.23)
Contract #03213201
Totals100202670.591272022.8381434714.3181.2

CountyBEXAR
HighwayIH 410
FromAT SOUTHCROSS
To.
CSJ0521-06-153
Proj IDCM 2B23(051)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
0.5275690567.47498774.008.7
CountyBEXAR
HighwayIH 410
FromAT SOUTHCROSS
To.
CSJ0521-06-159
Proj IDF 2B23(239)
Work TypeRIGHT OF WAY
 
0.5272460210.00459825.0018.6
Work Order12-05-23
Work Began02-13-24
Work Completed
Time Computed02-05-24
Contract Working Days336
Addl Days Granted0
Working Days Charged28
Percent Time Used8
Contractor(s)
J3 COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0521-06-153
ENVIRONMENTAL SAFETY SERVICES, INC. (3.82)
SAECO ELECTRIC & UTILITY, LTD. (8.39)
RAM II GENERAL CONTRACTOR, INC. (19.70)
BADECO, INC. (2.58)
BARRICADES UNLIMITED (0.52)
LONE STAR PAVING COMPANY (13.42)
Contract #11233208
Totals8150777.47865057.00958599.0011.7

CountyGUADALUPE
HighwayIH 10
FromFM 464
ToSH 123
CSJ0535-01-074
Proj IDF 2023(947)
Work TypeWIDEN FREEWAY
 
4.569234507006.3933328080.9814.2
CountyGUADALUPE
HighwayIH 10
FromFM 464
ToSH 123
CSJ0535-01-076
Proj IDROW 535-1-76
Work TypeRIGHT OF WAY
 
4.569878306.37840958.3695.7
CountyGUADALUPE
HighwayIH 10
FromSH 123
ToSH 130
CSJ0535-01-079
Proj IDF 2B23(170)
Work TypeOVERLAY
 
4.0469808726.450.000.0
Work Order10-06-23
Work Began01-08-24
Work Completed
Time Computed01-04-24
Contract Working Days1,711
Addl Days Granted0
Working Days Charged67
Percent Time Used3
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0535-01-074
KING GEORGE TRAFFIC SOLUTIONS LLC (0.78)
LONE STAR PAVING COMPANY (12.52)
SCOTT DERR PAINTING CO, LLC (0.12)
SWEEPING CORPORATION OF AMERICA, LLC (0.14)
TEXAS HIGHWAY SYSTEMS, INC. (4.95)
AMERICAN SIGNAL EQUIPMENT CO., INC. (CONVERSE) (0.20)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.17)
BUYERS BARRICADES SAN ANTONIO, LLC (0.01)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (4.09)
GUERRA UNDERGROUND LLC (0.37)
PRIMATE CONSTRUCTION, LP (0.32)
PROFESSIONAL TRAFFIC CONTROL LLC (0.00)
ROYAL REBAR (4.23)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC (0.22)
A K FUQUAY CONSTRUCTION (0.67)
ALAMO ENVIRONMENTAL, INC. (0.03)
DELENA CONSTRUCTION SERVICES LLC (1.82)
EGGEMEYER LAND CLEARING, LLC (0.04)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.53)
DEPENDABLE FENCE (0.56)
STRUCTURAL TECHNOLOGIES, LLC (0.43)
EVT CONSTRUCTION (0.76)
Contract #06233002
Totals245194039.2111579256.6334169039.3413.9

CountyBEXAR
HighwaySH 16
FromAT LP 1604
To.
CSJ0613-01-068
Proj IDSTP 2021(361)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.001809120.44794519.0398.1
CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN BEXAR COUNTY
To.
CSJ0915-00-224
Proj IDSTP 2021(361)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.0011955754.271772378.0591.1
Work Order03-25-21
Work Began06-27-21
Work Completed
Time Computed06-23-21
Contract Working Days199
Addl Days Granted21
Working Days Charged232
Percent Time Used105
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0613-01-068
TEXAS MATERIALS GROUP, INC. (23.57)
LIGHT IT UP ELECTRIC (4.57)
ENVIRONMENTAL SAFETY SERVICES, INC. (2.65)
FLASHER EQUIPMENT COMPANY (2.34)
CATO ELECTRIC COMPANY (0.00)
Contract #02213215
Totals2764874.710.002566897.0893.1

CountyBEXAR
HighwayFM 1535
FromLP 1604
ToHUEBNER ROAD
CSJ0658-01-045
Proj IDSTP 2021(227)MM
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
2.07010878265.9210749038.6498.8
CountyBEXAR
HighwayFM 1535
FromLP 1604
ToHUEBNER ROAD
CSJ0658-01-046
Proj IDROW 658-1-46
Work TypeRIGHT OF WAY
 
2.0704645101.504393802.9194.5
Work Order03-01-21
Work Began06-14-21
Work Completed
Time Computed05-30-21
Contract Working Days540
Addl Days Granted71
Working Days Charged611
Percent Time Used100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0658-01-045
UNDERGROUND WATER SOLUTIONS, CO. (6.10)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.05)
LONE STAR PAVING COMPANY (11.27)
DEPENDABLE FENCE (0.83)
R K STEPHENS CONSTRUCTION, LLC (4.35)
TRP CONSTRUCTION GROUP, LLC (2.28)
BADECO, INC (19.81)
GEOSOURCE, INC. (0.41)
L&H ELECTRICAL, LLC (3.28)
SCOTT DERR PAINTING CO, LLC (0.01)
HARRIS HARDROCK TRENCHING, L.L.C. (0.00)
HB FARMER FOUNDATION, LLC (0.00)
DAKOTA UTILITY CONTRACTORS, INC. (0.00)
GULF COAST FIBER SERVICES, L.L.C. (0.00)
SAECO ELECTRIC & UTILITY, LTD. (3.21)
LOPEZSOL CONSTRUCTION, INC. (0.00)
Contract #01213003
Totals15523367.42151991.6515142841.5597.5

CountyATASCOSA
HighwayFM 1099
FromUS 281A
ToFM 99
CSJ0748-06-016
Proj IDF 2023(102)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.67014508838.6010177429.9870.1
Work Order10-13-22
Work Began04-18-23
Work Completed
Time Computed01-11-23
Contract Working Days298
Addl Days Granted0
Working Days Charged203
Percent Time Used68
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0748-06-016
DIIBS SPECIALISTS, LLC (0.15)
FLASHER EQUIPMENT COMPANY (0.57)
WEST TEXAS ROCK RESOURCES, LLC (0.08)
LONE STAR EROSION CONTROL (2.35)
RUCOBA & MAYA CONSTRUCTION, LLC (2.09)
HIGHWAY BARRICADES AND SERVICES, LLC (1.97)
TRP CONSTRUCTION GROUP, LLC (0.25)
EGGEMEYER LAND CLEARING, LLC (0.31)
Contract #09223238
Totals14508838.601307137.6410177429.9870.1

CountyMEDINA
HighwayFM 462
FromAT HONDO CREEK
To6.5 MI S OF BANDERA/MEDINA COUNTY LINE
CSJ0848-04-049
Proj IDBR 2022(263)
Work TypeBRIDGE REPLACEMENT
 
0.2483176381.383026734.6395.2
Work Order02-23-22
Work Began06-01-22
Work Completed
Time Computed03-25-22
Contract Working Days404
Addl Days Granted0
Working Days Charged377
Percent Time Used93
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0848-04-049
FLASHER EQUIPMENT COMPANY (0.42)
DIIBS SPECIALISTS, LLC (2.53)
TORO BRAVO CONSTRUCTION, LLC (1.04)
TEXAS SHAFTS, INC. (11.74)
Contract #01223011
Totals3176381.382500.003026734.6395.2

CountyBEXAR ETC
HighwayFM 471
FromOLD FM 471
ToMEDINA COUNTY LINE
CSJ0849-01-055
Proj IDF 2022(006)
Work TypeWIDEN NON-FREEWAY
 
6.15549119269.9925083744.9151.0
Work Order01-20-22
Work Began04-20-22
Work Completed
Time Computed04-20-22
Contract Working Days1,142
Addl Days Granted0
Working Days Charged412
Percent Time Used36
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0849-01-055
TEXAS MATERIALS GROUP, INC. (14.94)
BADECO, INC (7.54)
ADCOCK 4 INVESTMENTS, LLC (5.80)
SAECO ELECTRIC & UTILITY, LTD. (3.31)
LONE STAR EROSION CONTROL (1.39)
ROADWAY SPECIALTIES, INC. (0.88)
INTERSTATE BARRICADES & MARKINGS, INC. (0.85)
FOX QUALITY CONCRETE, L.L.C. (0.63)
FLASHER EQUIPMENT COMPANY (0.45)
PERFORMANCE EQUIPMENT SERVICE (0.24)
AUSTIN WOOD RECYCLING (0.16)
JB PINNACLE GROUP, LLC (0.10)
PRIMATE CONSTRUCTION, LP (0.01)
KELLER NORTH AMERICA, INC. (0.49)
STELLAR CONSTRUCTORS, LLC (2.04)
C-3 LAND CLEARING, LLC (0.05)
TEXAS EROSION CONTROL SERVICES (1.24)
Contract #12213202
Totals49119269.991129947.6025083744.9151.0

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2020
To.
CSJ0915-00-198
Proj IDSTP 2020(558)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011588564.781556081.4598.3
Work Order03-12-20
Work Began04-12-21
Work Completed
Time Computed05-01-20
Contract Working Days320
Addl Days Granted0
Working Days Charged258
Percent Time Used80
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-198
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (2.96)
G 6 CONSTRUCTION, INC. (4.68)
CALAME CONTRACTING, LLC (1.40)
BUENO PRO SERVICES, LLC. (0.38)
Contract #02203020
Totals1588564.780.001556081.4598.3

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2021
To.
CSJ0915-00-228
Proj IDSTP 2021(362)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011625675.841242982.9178.1
Work Order03-12-21
Work Began03-21-22
Work Completed
Time Computed06-10-21
Contract Working Days320
Addl Days Granted0
Working Days Charged287
Percent Time Used89
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-228
FLASHER EQUIPMENT COMPANY (1.44)
RIO GRANDE REBAR RODBUSTERS, LLC. (1.42)
TRP CONSTRUCTION GROUP, LLC (1.03)
G 6 CONSTRUCTION, INC. (2.15)
CALAME CONTRACTING, LLC (2.58)
GREYCO CONSTRUCTION, LLC (1.04)
Contract #02213020
Totals1625675.840.001242982.9178.1

CountyBEXAR
HighwayVA
FromVARIOUS LOCATIONS IN MEDINA
ToAND ATASCOSA COUNTIES
CSJ0915-00-231
Proj IDSTP 2021(231)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.0013127184.733446232.0999.9
CountyMEDINA
HighwayFM 471
FromAT BIPPETT (CR 482)
To.
CSJ1547-01-051
Proj IDSTP 2021(352)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.199289277.82363405.7799.9
Work Order03-05-21
Work Began06-09-21
Work Completed
Time Computed06-03-21
Contract Working Days214
Addl Days Granted60
Working Days Charged273
Percent Time Used99
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-231
AREA WIDE PROTECTIVE, INC. (0.69)
FLASHER EQUIPMENT COMPANY (4.24)
DEPENDABLE FENCE (3.54)
LIGHT IT UP ELECTRIC (1.78)
LONE STAR EROSION CONTROL (1.87)
THE LEVY COMPANY, INC. (1.31)
Contract #01213211
Totals3416462.550.003809637.8699.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CNTRL FY 2021
To.
CSJ0915-00-235
Proj IDF 2021(487)
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011609699.251462112.6091.9
Work Order05-20-21
Work Began05-21-22
Work Completed
Time Computed08-18-21
Contract Working Days256
Addl Days Granted25
Working Days Charged290
Percent Time Used103
Contractor(s)
D&G ENERGY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-235
FIBERTEL, LLC (0.62)
FLASHER EQUIPMENT COMPANY (1.58)
Contract #04213225
Totals1609699.255495.001462112.6091.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CONTROL FY 2022
ToPROJECT 1
CSJ0915-00-236
Proj IDC 915-00-236
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011421995.00981163.7968.9
Work Order03-24-22
Work Began10-10-22
Work Completed
Time Computed04-23-22
Contract Working Days260
Addl Days Granted0
Working Days Charged140
Percent Time Used53
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-236
FLASHER EQUIPMENT COMPANY (2.80)
Contract #02223007
Totals1421995.000.00981163.7968.9

CountyBEXAR
HighwayVA
FromDISTRICTWIDE GUIDE SIGNS FY 2022
To.
CSJ0915-00-238
Proj IDC 915-00-238
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011675784.441618972.0996.6
Work Order06-16-22
Work Began02-13-23
Work Completed
Time Computed07-18-22
Contract Working Days290
Addl Days Granted35
Working Days Charged238
Percent Time Used73
Contractor(s)
THE LEVY COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-238
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (18.19)
FLASHER EQUIPMENT COMPANY (6.30)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.87)
Contract #05223223
Totals1675784.44102457.111618972.0996.6

CountyBEXAR
HighwayCS
FromALONG FM 2790, COTTAGE ST., AND PRAIRIE
ToIN LYTLE: MEDINA, ATASCOSA, BEXAR COUNTY
CSJ0915-00-252
Proj IDSTP 2023(490)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1244334.00222108.0317.8
Work Order11-16-23
Work Began02-08-24
Work Completed
Time Computed12-16-23
Contract Working Days280
Addl Days Granted0
Working Days Charged33
Percent Time Used11
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-252
BARRICADES UNLIMITED (2.30)
A K FUQUAY CONSTRUCTION (8.26)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.81)
Contract #10233218
Totals1244334.00138470.55222108.0317.8

CountyBEXAR
HighwayVA
FromDISTRICTWIDE TRAFFIC CONTROL FY 2023
ToPROJECT 1
CSJ0915-00-253
Proj IDC 915-00-253
Work TypeTRAFFIC CONTROL DEVICES
 
0.0011505725.721511460.3199.9
Work Order03-16-23
Work Began08-07-23
Work Completed
Time Computed06-14-23
Contract Working Days260
Addl Days Granted0
Working Days Charged114
Percent Time Used43
Contractor(s)
E-Z BEL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0915-00-253
ALAMO CRANE SERVICE, INC. (0.87)
FIBERTEL, LLC (4.20)
FLASHER EQUIPMENT COMPANY (3.77)
LOZANO TRUCKING COMPANY, INC. (1.03)
M & M STRIPING & POWER WASHING, LLC (1.30)
SOUTH TEXAS TRAFFIC ALLIANCE INC. (0.09)
CATO ELECTRIC COMPANY (0.14)
Contract #02233231
Totals1505725.72150660.961511460.3199.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7