Monthly State Let Maintenance Report For San Antonio District As Of Apr 12, 2024 Page 1 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
Highway0000000
From4615 NW LOOP 410
ToSAN ANTONIO TX 78229
CSJ4704-01-595
Proj IDCBC - 470401595
Work TypeRENOVATION OR REPAIR
 
0.0012038650.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
QA CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-595
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164224
Totals2038650.000.000.000.0

CountyUVALDE
Highway0000000
From2231 US 90 WEST
ToUVALDE TX 78801
CSJ4704-01-724
Proj IDCBC - 470401724
Work TypeRENOVATION OR REPAIR
 
0.001337200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRIGGS BROTHERS ENTERPRISES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-724
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164221
Totals337200.000.000.000.0

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS IN ATASCOSA
ToCOUNTY
CSJ6354-23-001
Proj IDRMC - 635423001
Work TypeMOWING HWY ROW AND LITTER REMOVAL
 
0.001519032.24828875.95100.0
Work Order05-13-20
Work Began05-13-20
Work Completed02-20-24
Time Computed05-20-20
Contract Working Days222
Addl Days Granted229
Working Days Charged134
Percent Time Used29
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6354-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204216
Totals519032.240.00828875.95100.0

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN FRIO, ATASCOSA AND
ToLASALLE COUNTIES
CSJ6354-38-001
Proj IDRMC - 635438001
Work TypeMOWING AND LITTER REMOVAL
 
0.001649631.60901240.3199.9
Work Order00-00-00
Work Began05-15-20
Work Completed
Time Computed05-11-20
Contract Working Days252
Addl Days Granted252
Working Days Charged167
Percent Time Used33
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6354-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204219
Totals649631.600.00901240.3199.9

CountyCOMAL
HighwaySH0046
FromVARIOUS LOCATIONS IN
ToTHE SAN ANTONIO DISTRICT
CSJ6354-47-001
Proj IDRMC - 635447001
Work TypeGUARDRAIL REPAIR
 
0.0012522000.0011562634.4299.9
Work Order03-05-20
Work Began04-06-20
Work Completed
Time Computed04-06-20
Contract Working Days730
Addl Days Granted730
Working Days Charged1,456
Percent Time Used99
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6354-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01204218
Totals2522000.00296270.6411562634.4299.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6372-50-001
Proj IDRMC - 637250001
Work TypeROUTINE MAINTENANCE PROJECT - SEALED
 
0.01014977836.1625002349.5499.9
Work Order03-25-21
Work Began03-25-21
Work Completed
Time Computed04-01-21
Contract Working Days730
Addl Days Granted731
Working Days Charged1,096
Percent Time Used75
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6372-50-001
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (11.33)
BK FIELD OPERATIONS LLC (23.83)
AIMS COMPANIES (0.97)
JCW CONSTRUCTION, LLC (0.33)
YES AMERICA NOW, INC. (11.10)
BOEN LANDSCAPING & IRRIGATION, LLC (0.00)
AUSTIN BARRICADE COMPANY, L.L.C. (0.00)
Contract #01214020
Totals14977836.16612394.8825002349.5499.9

CountyKERR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToKERR, KENDALL AND BANDERA COUNTIES
CSJ6383-15-001
Proj IDRMC - 638315001
Work TypePICNIC AREA MAINTENANCE
 
0.010599880.00841312.2399.9
Work Order00-00-00
Work Began09-02-21
Work Completed
Time Computed09-02-21
Contract Working Days730
Addl Days Granted730
Working Days Charged941
Percent Time Used64
Contractor(s)
JCW CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6383-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07214214
Totals599880.0027417.96841312.2399.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6388-36-001
Proj IDRMC - 638836001
Work TypePAVEMENT MARKINGS
 
0.0103077767.504406865.2299.9
Work Order09-26-22
Work Began09-30-22
Work Completed
Time Computed10-03-22
Contract Working Days365
Addl Days Granted365
Working Days Charged539
Percent Time Used73
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6388-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10214022
Totals3077767.50543281.134406865.2299.9

CountyUVALDE
HighwayUS0083
FromAT CR 348 (RIVER ROAD)
To.
CSJ6393-14-001
Proj IDRMC - 639314001
Work TypeROADWAY WIDENING
 
0.0101633971.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CK NEWBERRY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6393-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04244001
Totals1633971.000.000.000.0

CountyMCMULLEN
HighwaySH0016
FromVARIOUS LOCATIONS IN MCMULLEN,
ToATASCOSA, AND FRIO COUNTIES
CSJ6395-05-001
Proj IDRMC - 639505001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010503637.68330482.4465.6
Work Order00-00-00
Work Began02-28-22
Work Completed
Time Computed03-01-22
Contract Working Days730
Addl Days Granted730
Working Days Charged731
Percent Time Used50
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6395-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01224018
Totals503637.680.00330482.4465.6

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6395-40-001
Proj IDRMC - 639540001
Work TypeBUNDLED BID
 
0.01017507039.238010332.3445.7
Work Order00-00-00
Work Began04-01-23
Work Completed
Time Computed04-01-23
Contract Working Days730
Addl Days Granted0
Working Days Charged366
Percent Time Used50
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234207
Totals17507039.23879531.088010332.3445.7

CountyMEDINA
HighwayIH0035
FromVARIOUS LOCATIONS IN HONDO
ToMAINTENANCE SECTION
CSJ6406-28-001
Proj IDMMC - 640628001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010486216.00833681.2699.9
Work Order02-22-23
Work Began03-15-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged397
Percent Time Used54
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6406-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234008
Totals486216.00145969.24833681.2699.9

CountyUVALDE
HighwayUS0090
FromVARIOUS LOCATIONS IN UVALDE
ToMAINTENANCE SECTION
CSJ6406-34-001
Proj IDMMC - 640634001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010693912.001767690.5999.9
Work Order00-00-00
Work Began03-07-23
Work Completed
Time Computed02-27-23
Contract Working Days365
Addl Days Granted365
Working Days Charged399
Percent Time Used54
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6406-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234208
Totals693912.00241527.641767690.5999.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS THROUGHOUT
ToSAN ANTONIO DISTRICT
CSJ6406-59-001
Proj IDMMC - 640659001
Work TypeAGGREGATE
 
0.010447366.30308313.6168.9
Work Order02-23-23
Work Began04-20-23
Work Completed
Time Computed03-02-23
Contract Working Days365
Addl Days Granted366
Working Days Charged396
Percent Time Used54
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6406-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234009
Totals447366.3040749.64308313.6168.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN EAST BEXAR
ToMAINTENANCE SECTION
CSJ6406-61-001
Proj IDMMC - 640661001
Work TypeHOT MIX
 
0.010661764.60996049.2499.9
Work Order03-01-23
Work Began03-13-23
Work Completed
Time Computed03-08-23
Contract Working Days365
Addl Days Granted365
Working Days Charged390
Percent Time Used53
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6406-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234209
Totals661764.60159915.10996049.2499.9

CountyBEXAR
HighwayIH0010
FromVARIOUS LOCATIONS IN WEST BEXAR
ToMAINTENANCE SECTION
CSJ6406-69-001
Proj IDMMC - 640669001
Work TypeHOT MIX
 
0.010693912.50428704.7561.7
Work Order02-22-23
Work Began04-03-23
Work Completed
Time Computed03-01-23
Contract Working Days365
Addl Days Granted366
Working Days Charged366
Percent Time Used50
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234010
Totals693912.500.00428704.7561.7

CountyCOMAL
HighwayIH0035
FromVARIOUS LOCATIONS IN NEW BRAUNFELS
ToMAINTENANCE SECTION
CSJ6406-73-001
Proj IDMMC - 640673001
Work TypeHOT MIX
 
0.010854150.001235885.1399.9
Work Order00-00-00
Work Began04-03-23
Work Completed
Time Computed03-12-23
Contract Working Days365
Addl Days Granted365
Working Days Charged386
Percent Time Used52
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6406-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234210
Totals854150.00226223.861235885.1399.9

CountyKERR
HighwaySH0173
FromVARIOUS LOCATIONS IN KERR, BANDERA,
ToKENDALL AND UVALDE COUNTIES
CSJ6410-37-001
Proj IDRMC - 641037001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0101410326.001841498.0599.9
Work Order00-00-00
Work Began01-23-23
Work Completed
Time Computed01-23-23
Contract Working Days365
Addl Days Granted182
Working Days Charged434
Percent Time Used79
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6410-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224217
Totals1410326.000.001841498.0599.9

CountyMEDINA
HighwayUS0090
FromVARIOUS LOCATIONS IN MEDINA, ATASCOSA,
ToFRIO AND MCMULLEN COUNTIES
CSJ6410-63-001
Proj IDRMC - 641063001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0102351122.044152879.5799.9
Work Order11-30-22
Work Began12-07-22
Work Completed
Time Computed12-07-22
Contract Working Days365
Addl Days Granted279
Working Days Charged481
Percent Time Used74
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6410-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224028
Totals2351122.042000.004152879.5799.9

CountyCOMAL
HighwaySH0046
FromVARIOUS LOCATIONS IN COMAL, GUADALUPE,
ToAND WILSON COUNTIES
CSJ6410-67-001
Proj IDRMC - 641067001
Work TypeFLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.0102637042.502780126.5099.9
Work Order10-26-22
Work Began11-02-22
Work Completed
Time Computed11-02-22
Contract Working Days365
Addl Days Granted304
Working Days Charged516
Percent Time Used77
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6410-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09224029
Totals2637042.50820067.092780126.5099.9

page 1 | page 2 | page 3