Monthly Local Let Maintenance Report For Tyler District As Of Mar 13, 2024 Page 1 Of 4

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHENDERSON
HighwayUS0175
FromVARIOUS ROADWAYS IN THE
ToATHENS MAINTENANCE SECTION
CSJ6272-05-001
Proj IDRMC - 627205001
Work TypePAINT
 
0.01023318.75379608.72100.0
CountyVAN ZANDT
HighwaySH0019
FromVARIOUS ROADWAYS IN
ToTHE CANTON MAINTENANCE SECTION
CSJ6272-05-002
Proj IDRMC - 627205002
Work TypePAINT
 
0.01023318.7559964.01100.0
CountyRUSK
HighwayUS0259
FromVARIOUS ROADWAYS IN THE
ToHENDERSON MAINTENANCE SECTIONN
CSJ6272-05-003
Proj IDRMC - 627205003
Work TypePAINT
 
0.01023318.7560837.79100.0
CountyCHEROKEE
HighwayUS0079
FromVARIOUS ROADWAYS IN THE
ToJACKSONVILLE MAINTENANCE SECTION
CSJ6272-05-004
Proj IDRMC - 627205004
Work TypePAINT
 
0.01012009.3866767.05100.0
CountyGREGG
HighwaySH0031
FromVARIOUS ROADWAYS IN THE
ToLONGVIEW MAINTENANCE SECTION
CSJ6272-05-005
Proj IDRMC - 627205005
Work TypePAINT
 
0.01023318.7549248.01100.0
CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN THE
ToMINEOLA MAINTENACE SECTION
CSJ6272-05-006
Proj IDRMC - 627205006
Work TypePAINT
 
0.01023318.7535210.94100.0
CountyANDERSON
HighwayUS0287
FromVARIOUS ROADWAYS IN THE
ToPALESINE MAINTENANCE SECTION
CSJ6272-05-007
Proj IDRMC - 627205007
Work TypePAINT
 
0.01023318.758365.21100.0
CountySMITH
HighwaySH0110
FromVARIOUS ROADWAYS IN THE
ToTYLER MAINTENANCE SECTION
CSJ6272-05-008
Proj IDRMC - 627205008
Work TypePAINT
 
0.01023318.7548327.90100.0
CountyCHEROKEE
HighwayUS0069
FromVARIOUS ROADWAYS IN THE
ToRUSK MAINTENANCE SECTION
CSJ6272-05-009
Proj IDRMC - 627205009
Work TypePAINT
 
0.01012009.3834335.47100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-14
Work Began09-25-14
Work Completed09-15-16
Time Computed09-01-14
Contract Working Days255
Addl Days Granted255
Working Days Charged509
Percent Time Used99
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6272-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141001
Totals187250.010.00742665.10100.0

CountyRUSK
HighwayUS0079
FromVARIOUS ROADWAYS IN
ToRUSK AND CHEROKEE COUNTIES
CSJ6290-48-001
Proj IDEMC - 629048001
Work TypeEMERGENCY DEBRIS & TREE REMOVAL
 
0.010435655.003070764.75100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-26-15
Work Completed08-11-15
Time Computed00-00-00
Contract Working Days52
Addl Days Granted0
Working Days Charged33
Percent Time Used63
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6290-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151044
Totals435655.000.003070764.75100.0

CountySMITH
HighwaySL0323
FromSL 323 IN
ToSMITH COUNTY
CSJ6303-40-001
Proj IDRMC - 630340001
Work TypeSLOPE FAILURE
 
0.100182290.00461048.79100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-05-16
Work Completed10-02-17
Time Computed00-00-00
Contract Working Days40
Addl Days Granted3
Working Days Charged41
Percent Time Used95
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-40-001
NEWSTAR DRILLING, INC (2.22)
Contract #08161001
Totals182290.000.00461048.79100.0

CountyGREGG
HighwayUS0259
FromLONGVIEW MTCE. SECTION
ToGREGG COUNTY
CSJ6317-77-001
Proj IDSUP - 631777001
Work TypeLITTER REMOVAL
 
0.001121548.44115573.59100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-17
Work Completed09-03-19
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
WORKQUEST
ANDREWS DIVERSIFIED INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6317-77-001
ANDREWS DIVERSIFIED INDUSTRIES (100.00)
Contract #07171037
Totals121548.440.00115573.59100.0

CountyWOOD
HighwaySL0564
FromMINEOLA AREA OFFICE
ToIN WOOD COUNTY
CSJ6349-69-001
Proj IDRMC - 634969001
Work TypeLAWN MAINTENANCE
 
0.01076000.00104695.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-20
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted730
Working Days Charged1,325
Percent Time Used90
Contractor(s)
HX FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6349-69-001
KLEEN SWEEP SERVICES (46.05)
Contract #04201009
Totals76000.001155.00104695.0099.9

CountyANDERSON
HighwayUS0079
FromVARIOUS LOCATIONS IN
ToANDERSON COUNTY
CSJ6354-35-001
Proj IDMMC - 635435001
Work TypeHOT MIX MATERIALS
 
0.010322600.001551590.34100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-15-20
Work Completed05-11-21
Time Computed00-00-00
Contract Working Days120
Addl Days Granted240
Working Days Charged359
Percent Time Used99
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6354-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02201007
Totals322600.0041776.751551590.34100.0

CountyRUSK
HighwayFM1798
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6401-40-001
Proj IDRMC - 640140001
Work TypeCRACK SEAL
 
0.010132722.38133282.09100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-02-23
Work Completed03-16-23
Time Computed00-00-00
Contract Working Days42
Addl Days Granted0
Working Days Charged42
Percent Time Used100
Contractor(s)
SCOUT 5 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6401-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08221001
Totals132722.380.00133282.09100.0

CountyGREGG
HighwayUS0080
FromLONGVIEW'S LAWN MAINTENANCE
ToLONGVIEW OFFICE
CSJ6413-01-001
Proj IDSUP - 641301001
Work TypeLANDSCAPE MAINTENANCE
 
0.01031110.0019680.0063.2
Work Order09-01-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6413-01-001
ANDREWS DIVERSIFIED INDUSTRIES (0.00)
Contract #08221031
Totals31110.000.0019680.0063.2

CountyHENDERSON
HighwayUS0175
FromATHENS MAINTENANCE SECTION
ToHENDERSON COUNTY
CSJ6413-07-001
Proj IDSUP - 641307001
Work TypeSTATE USE CONTRACT
 
0.01016782.008229.0049.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6413-07-001
ANDREWS CENTER (100.00)
Contract #08221041
Totals16782.000.008229.0049.0

CountyRUSK
HighwayUS0259
FromHENDERSON MTCE OFFICE
ToRUSK COUNTY
CSJ6413-09-001
Proj IDSUP - 641309001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.0109193.323386.9436.8
Work Order08-30-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-09-001
RUCON, INC. (0.00)
Contract #08221032
Totals9193.32302.433386.9436.8

CountyRUSK
HighwayUS0259
FromHENDERSON MTCE OFFICE ROW
ToRUSK COUNTY
CSJ6413-11-001
Proj IDSUP - 641311001
Work TypeLANDSCAPE MAINTENANCE
 
0.01025660.8011404.8044.4
Work Order09-01-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-11-001
RUCON, INC. (0.00)
Contract #08221033
Totals25660.80712.8011404.8044.4

CountyRUSK
HighwayUS0259
FromHENDERSON MTCE OFFICE
ToRUSK COUNTY
CSJ6413-13-001
Proj IDSUP - 641313001
Work TypePICNIC AREA MAINTENANCE
 
0.01094800.9662598.9666.0
Work Order08-22-22
Work Began09-01-22
Work Completed
Time Computed09-01-22
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-13-001
RUCON, INC. (0.00)
Contract #08221034
Totals94800.963595.8062598.9666.0

CountySMITH
HighwayUS0069
FromVARIOUS LOCATION IN SMITH COUNTY
ToSMITH COUNTY
CSJ6413-17-001
Proj IDSUP - 641317001
Work TypePICNIC AREA MAINTENANCE
 
0.010133140.0093137.8569.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
ANDREWS CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6413-17-001
ANDREWS CENTER (100.00)
Contract #08221043
Totals133140.008446.0093137.8569.9

CountySMITH
HighwayUS0069
FromTYLER MAINTENANCE OFFICE
ToSMITH COUNTY
CSJ6413-19-001
Proj IDSUP - 641319001
Work TypeJANITORIAL MAINTENANCE
 
0.01050016.0836263.1872.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-19-001
WORLD TECHNICAL SERVICES, INC. (100.00)
Contract #08221039
Totals50016.082916.5936263.1872.5

CountyANDERSON
HighwayUS0079
FromPALESTINE MAINTENANCE SECTION
ToANDERSON COUNTY
CSJ6413-21-001
Proj IDSUP - 641321001
Work TypeJANITORIAL MAINTENANCE
 
0.01026490.4015384.6458.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged516
Percent Time Used70
Contractor(s)
WORKQUEST
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-21-001
WORLD TECHNICAL SERVICES, INC. (100.01)
Contract #08221038
Totals26490.40845.6415384.6458.0

CountyCHEROKEE
HighwayUS0069
FromJACKSONVILLE MTCE. SECTION
ToCHEROKEE COUNTY
CSJ6413-23-001
Proj IDSUP - 641323001
Work TypeSTATE USE CONTRACT
 
0.01012083.565360.9644.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-23-001
GATEWAY COMMUNITY PARTNERS, INC. (100.04)
Contract #08221035
Totals12083.56303.195360.9644.3

CountyCHEROKEE
HighwayUS0069
FromRUSK'S LAWN MAINTENANCE
ToRUSK OFFICE
CSJ6413-37-001
Proj IDSUP - 641337001
Work TypeSTATE USE CONTRACT
 
0.01015611.586234.6939.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-37-001
GATEWAY COMMUNITY PARTNERS, INC. (100.03)
Contract #08221036
Totals15611.58347.296234.6939.9

CountyCHEROKEE
HighwayUS0069
FromJACKSONVILLE/RUSK ROW MAINTENANCE
ToCHEROKEE COUNTY
CSJ6413-39-001
Proj IDSUP - 641339001
Work TypeSTATE USE CONTRACT
 
0.01015712.807001.1044.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-22
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged424
Percent Time Used58
Contractor(s)
WORKQUEST
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-39-001
GATEWAY COMMUNITY PARTNERS, INC. (100.03)
Contract #08221037
Totals15712.802287.267001.1044.5

CountySMITH
HighwayUS0069
FromTYLER ROW MAINTENANCE
ToSMITH COUNTY
CSJ6413-41-001
Proj IDSUP - 641341001
Work TypeSTATE USE CONTRACT
 
0.01031806.0012555.0039.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged546
Percent Time Used74
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6413-41-001
RUCON, INC. (100.00)
Contract #08221042
Totals31806.000.0012555.0039.4

CountyRUSK
HighwayUS0059
FromVARIOUS ROADWAYS IN
ToRUSK COUNTY
CSJ6415-09-001
Proj IDRMC - 641509001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.0100.00205944.200.0
Work Order01-01-23
Work Began02-01-23
Work Completed09-01-23
Time Computed02-01-23
Contract Working Days114
Addl Days Granted3
Working Days Charged120
Percent Time Used102
Contractor(s)
WESTGATE GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6415-09-001
FOWLER CONSTRUCTION (49.68)
Contract #09221006
Totals0.000.00205944.200.0

page 1 | page 2 | page 3 | page 4