Monthly State Let Construction Report For Yoakum District As Of Mar 13, 2024 Page 1 Of 8

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyGONZALES ETC
HighwayUA 90 ETC
FromSH 80
To0.25 MI E OF CR 143
CSJ0025-05-024
Proj IDF 2023(225)
Work TypeSEAL COAT
 
309.85718739124.7917762297.6794.9
Work Order02-09-23
Work Began05-08-23
Work Completed
Time Computed06-01-23
Contract Working Days75
Addl Days Granted0
Working Days Charged90
Percent Time Used120
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-05-024
CENTERLINE TECHNOLOGIES, LLC (16.97)
RED SIXTEEN CONSTRUCTION, INC (0.72)
Contract #11223205
Totals18739124.790.0017762297.6794.9

CountyFAYETTE ETC
HighwayUS 90 ETC
FromMARKET STREET(IN FLATONIA)
To0.4 MI E OF ELM STREET
CSJ0026-02-037
Proj IDF 2021(544)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
4.8362774624.51740507.1826.6
Work Order01-20-22
Work Began02-06-23
Work Completed
Time Computed04-21-22
Contract Working Days210
Addl Days Granted0
Working Days Charged201
Percent Time Used95
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0026-02-037
LONESTAR TRAFFIC SAFETY, LLC (0.58)
STRIPE LINES, INC. (1.44)
Contract #12213211
Totals2774624.5158260.60740507.1826.6

CountyFAYETTE ETC
HighwayUS 90 ETC
FromGONZALES C/L
To0.12 MI W OF SH 95
CSJ0026-02-039
Proj IDF 2024(332)
Work TypeSEAL COAT
 
314.38519785795.69581320.022.9
Work Order12-06-23
Work Began00-00-00
Work Completed
Time Computed06-01-24
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0026-02-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11233204
Totals19785795.69581320.02581320.022.9

CountyFAYETTE
HighwayUS 90
FromAT MIDDLE CREEK
ToSTR # 0026-03-028
CSJ0026-03-042
Proj IDBR 2017(318)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.288831842.19820401.6299.9
Work Order01-10-17
Work Began03-03-17
Work Completed
Time Computed04-10-17
Contract Working Days60
Addl Days Granted0
Working Days Charged121
Percent Time Used201
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-042
DELGADO"S CONSTRUCTION (60.07)
EGGEMEYER LAND CLEARING, LLC (2.87)
ROADWAY SPECIALTIES, INC. (3.88)
FLASHER EQUIPMENT COMPANY (0.39)
PAVEMENT MARKINGS INC. (0.94)
Contract #12163022
Totals831842.190.00820401.6299.9

CountyFAYETTE
HighwayUS 90
FromAT WEST NAVIDAD RIVER
ToSTR # 0026-03-034
CSJ0026-03-046
Proj IDBR 2023(623)
Work TypeBRIDGE REPLACEMENT
 
0.2005073582.212341810.9246.1
CountyFAYETTE
HighwayUS 90
FromAT FOSTER CREEK
ToSTR # 0026-03-035
CSJ0026-03-047
Proj IDBR 2023(623)
Work TypeBRIDGE REPLACEMENT
 
0.2001981766.25274229.8513.8
Work Order05-25-23
Work Began08-18-23
Work Completed
Time Computed08-23-23
Contract Working Days240
Addl Days Granted0
Working Days Charged108
Percent Time Used45
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-046
EGGEMEYER LAND CLEARING, LLC (0.58)
TRP CONSTRUCTION GROUP, LLC (0.75)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.50)
HOUSTON SAWING & DRILLING (0.14)
TEXAS MATERIALS GROUP, INC. (17.00)
LONE STAR EROSION CONTROL (1.64)
INTERSTATE BARRICADES & MARKINGS, INC. (0.23)
CND CONTRACTING (1.20)
TORO BRAVO CONSTRUCTION, LLC (0.24)
TRAFFIC SIGNS & LINES, LLC (0.14)
AARON CONCRETE CONTRACTORS, LLC (1.13)
Contract #04233210
Totals7055348.46435463.332616040.7737.0

CountyCOLORADO
HighwayUS 90
From.02 MI WEST OF FRONT STREET
To0.10 MI W. OF LEGION DR.
CSJ0026-06-031
Proj IDF 2023(670)
Work TypeOVERLAY
 
9.6745565142.56152452.692.7
Work Order06-28-23
Work Began00-00-00
Work Completed
Time Computed07-28-23
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-031
D. I. J. CONSTRUCTION, INC. (3.01)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (1.50)
CPAVE, INC. (0.53)
RUCOBA & MAYA CONSTRUCTION, LLC (2.56)
LONESTAR TRAFFIC SAFETY, LLC (0.24)
A BROTHERS MILLING, LLC (1.43)
WEST TEXAS ROCK RESOURCES, LLC (0.21)
QUICK MATERIALS (2.89)
Contract #05233019
Totals5565142.560.00152452.692.7

CountyCOLORADO ETC
HighwayUS 90 ETC
FromAT BS 71-F IN COLUMBUS
To.
CSJ0026-06-032
Proj IDF 2022(609)
Work TypeTRAFFIC CONTROL DEVICES
 
0.2022805099.501660782.6159.2
Work Order09-28-22
Work Began02-09-23
Work Completed
Time Computed12-27-22
Contract Working Days270
Addl Days Granted0
Working Days Charged219
Percent Time Used81
Contractor(s)
VACA UNDERGROUND UTILITIES INC
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-032
FLASHER EQUIPMENT COMPANY (2.74)
Contract #06223225
Totals2805099.50201186.861660782.6159.2

CountyCOLORADO
HighwayUS 90
FromFM 806
ToFRONT STREET
CSJ0026-06-034
Proj IDF 2022(489)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
1.503779897.20915354.1599.9
CountyMATAGORDA
HighwaySH 35
FromBAYOU DRIVE
To12 TH STREET
CSJ0179-04-100
Proj IDF 2022(490)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
4.4002077545.802346517.8299.9
Work Order06-09-22
Work Began01-04-23
Work Completed
Time Computed09-07-22
Contract Working Days240
Addl Days Granted0
Working Days Charged130
Percent Time Used54
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-034
PBJ CONSTRUCTION (5.82)
HIGHWAY 1 LLC (1.73)
LONESTAR TRAFFIC SAFETY, LLC (0.60)
Contract #05223008
Totals2857443.001000.003261871.9799.9

CountyCOLORADO ETC
HighwayUS 90 ETC
FromFM 806
To0.056 MI W OF FRONT ST.
CSJ0026-06-035
Proj IDF 2022(093)
Work TypeSEAL COAT
 
314.60116624783.2015310613.6692.0
Work Order12-16-21
Work Began05-03-22
Work Completed
Time Computed06-01-22
Contract Working Days75
Addl Days Granted2
Working Days Charged73
Percent Time Used94
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0026-06-035
INTERSTATE BARRICADES & MARKINGS, INC. (1.23)
CENTERLINE TECHNOLOGIES, LLC (14.48)
LINEAR TRAFFIC MARKINGS LLC (1.13)
Contract #11213201
Totals16624783.200.0015310613.6692.0

CountyCOLORADO
HighwayUS 90
FromAT COLORADO RIVER BRIDGE
ToSTR # 0027-01-001
CSJ0027-01-044
Proj IDBR 2019(850)
Work TypeBRIDGE REPLACEMENT
 
0.3648244674.8811316916.7899.9
Work Order06-13-19
Work Began08-05-19
Work Completed
Time Computed08-05-19
Contract Working Days405
Addl Days Granted0
Working Days Charged400
Percent Time Used98
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0027-01-044
SEMPER STRIPING LLC (0.02)
HB FARMER FOUNDATION, LLC (12.51)
MCL CONTRACTING, LLC (0.81)
DORAN STEEL, INC. (0.93)
A1 EROSION CONTROL (0.37)
CHOCTAW ERECTORS, INC. (8.27)
WILLOW CITY SIGN & RAIL, INC. (1.56)
GMJ PAVING CO. (2.99)
DORAN STEEL, INC. (0.54)
EAST - TEX PIPE AND FAB LLC (0.56)
PRIMATE CONSTRUCTION, LP (0.09)
JB PINNACLE GROUP, LLC (0.79)
PEREZ CONSTRUCTION CO. (0.48)
BATTERSON, LLP (0.63)
CRAIG & HEIDT, INC. (1.58)
Contract #05193010
Totals8244674.880.0011316916.7899.9

CountyCOLORADO
HighwayUS 90A
FromFM 102 IN EAGLE LAKE
ToWHARTON COUNTY LINE
CSJ0027-03-071
Proj IDSTP 1702(426)
Work TypeCONSTRUCT SUPER 2 LANES
 
5.0284487326.994879429.9999.9
Work Order08-11-17
Work Began10-25-17
Work Completed
Time Computed11-09-17
Contract Working Days160
Addl Days Granted0
Working Days Charged159
Percent Time Used99
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0027-03-071
AREA WIDE PROTECTIVE, INC. (0.26)
D. I. J. CONSTRUCTION, INC. (1.88)
D&S TEXAS ICON CONSTRUCTION (0.35)
ENVIRONMENTAL SAFETY SERVICES, INC. (0.27)
RIOS TRUCKING CO. (1.40)
STRIPE-A-ZONE, INC. (0.27)
Contract #06173243
Totals4487326.990.004879429.9999.9

CountyWHARTON
HighwayUA 90
From2.58 MI W OF FM 1164
ToSH 60
CSJ0027-04-041
Proj IDSTP 1902(164)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7.341496857.15677816.3199.9
CountyWHARTON
HighwayFM 640
FromFM 1161
ToFM 102
CSJ1260-03-013
Proj IDSTP 1902(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3.014527561.27477578.1390.5
CountyWHARTON
HighwayFM 1161
FromFM 102
ToSH 60
CSJ1303-01-018
Proj IDSTP 1902(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.3991138794.901073137.7394.2
CountyMATAGORDA
HighwayFM 2540
FromSH 35
ToFM 457
CSJ2525-01-017
Proj IDSTP 1902(168)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.301448295.64374263.1183.4
Work Order10-21-19
Work Began11-20-19
Work Completed
Time Computed01-19-20
Contract Working Days210
Addl Days Granted0
Working Days Charged243
Percent Time Used115
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0027-04-041
A K FUQUAY CONSTRUCTION (2.24)
AREA WIDE PROTECTIVE, INC. (0.98)
RUCOBA & MAYA CONSTRUCTION, LLC (62.13)
TRAFFIC SIGNS & LINES, LLC (1.76)
Contract #09193204
Totals2611508.960.002602795.2899.9

CountyWHARTON ETC
HighwayUS 90A ETC
FromCOLORADO C/L
ToSH 60
CSJ0027-04-042
Proj IDSTP 2021(545)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
30.9503775419.002599107.2070.0
Work Order09-29-21
Work Began03-31-22
Work Completed
Time Computed12-28-21
Contract Working Days300
Addl Days Granted0
Working Days Charged348
Percent Time Used116
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0027-04-042
CONCAN SERVICES LLC (4.01)
GV LANDSCAPE AND CONSTRUCTION LLC (7.38)
JB PINNACLE GROUP, LLC (3.23)
ROY LEE WALKER (1.74)
Contract #08213232
Totals3775419.00169049.002599107.2070.0

CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-085
Proj IDC 88-5-85
Work TypeCONSTRUCT FRONTAGE ROADS
 
2.76927884764.5033881182.8199.9
CountyVICTORIA
HighwayUS 59
From0.5 MI S OF FM 1686
ToSL 463
CSJ0088-05-099
Proj IDROW 88-5-99
Work TypeUTILITY ONLY
 
3.329708858.20655277.2092.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-19-18
Work Began09-17-18
Work Completed
Time Computed00-00-00
Contract Working Days600
Addl Days Granted205
Working Days Charged783
Percent Time Used97
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-085
AREA WIDE PROTECTIVE, INC. (0.02)
THIRD COAST SERVICES LLC (5.43)
ANGEL BROTHERS HOLDINGS CORP. (28.20)
ADCOCK 4 INVESTMENTS, LLC (4.34)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.59)
TITO"S TRUCKING & SONS, LLC (0.00)
ROADWAY SPECIALTIES, INC. (1.60)
INSITUFORM TECHNOLOGIES, LLC (0.68)
MVA CONSTRUCTION LLC (0.00)
AIMS COMPANIES (0.03)
BORTUNCO (0.22)
FARR FOUNDATION, INC. (0.30)
HIGHWAY BARRICADES AND SERVICES, LLC (0.40)
MONTALVO BRIDGE SYSTEMS, LLC (0.11)
DUSTROL, INC. (1.14)
WEBER-BALKE FOUNDATION COMPANY, INC (0.40)
CURB PLANET INC. (0.05)
AARON CONCRETE CONTRACTORS, L.P. (1.52)
ROYAL REBAR (0.05)
PRIMATE CONSTRUCTION, LP (0.02)
TEXAS MATERIALS GROUP, INC. (0.87)
ROADWAY CONSTRUCTION, LLC (0.63)
WEST TEXAS ROCK RESOURCES, LLC (0.01)
Contract #05183003
Totals28593622.700.0034536460.0199.9

CountyVICTORIA
HighwayUS 59
FromBU 59-T
ToBU 77S
CSJ0088-05-096
Proj IDF 2B23(079)
Work TypeWIDEN NON-FREEWAY
 
7.59655933077.8312796641.9422.8
Work Order09-19-23
Work Began11-20-23
Work Completed
Time Computed12-18-23
Contract Working Days354
Addl Days Granted0
Working Days Charged45
Percent Time Used12
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-096
HIGHWAY BARRICADES AND SERVICES, LLC (0.82)
VACA UNDERGROUND UTILITIES INC (1.50)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.63)
J&R CONTRACTING SERVICES, INC. (1.72)
DEPENDABLE FENCE (1.14)
MURRAY CONSTRUCTION (0.17)
JB PINNACLE GROUP, LLC (1.67)
SK CONCRETE SERVICES LLC (0.01)
A. H. BECK FOUNDATION CO., INC. (1.10)
TORO BRAVO CONSTRUCTION, LLC (0.06)
CAT SKINNER, LLC (0.19)
Contract #08233003
Totals55933077.835014282.0212796641.9422.8

CountyVICTORIA
HighwayUS 59
FromUS 87
ToSH 185
CSJ0088-05-098
Proj IDC 88-5-98
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
1.13613531313.2512258225.4891.6
Work Order09-21-21
Work Began04-07-22
Work Completed
Time Computed12-20-21
Contract Working Days360
Addl Days Granted0
Working Days Charged353
Percent Time Used98
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-098
BEAVER CONTRACTORS, LLC (7.48)
HB FARMER FOUNDATION, LLC (1.49)
HIGHWAY BARRICADES AND SERVICES, LLC (1.61)
ROADWAY SPECIALTIES, INC. (0.68)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.80)
THIRD COAST SERVICES LLC (8.19)
BARRICADES UNLIMITED (0.18)
ANCORTEX, INC. (1.92)
PBX BRIDGE COMPANY (1.07)
TORO BRAVO CONSTRUCTION, LLC (0.03)
TORO BRAVO CONSTRUCTION, LLC (0.07)
PRIMATE CONSTRUCTION, LP (0.03)
TECHNICAL STRUCTURAL REPAIR GROUP, LLC (2.77)
Contract #08213214
Totals13531313.25210203.9712258225.4891.6

CountyVICTORIA ETC
HighwayUS 59 ETC
FromAT SP 91
To.
CSJ0088-05-110
Proj IDF 2024(584)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1666764.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-24
Work Began00-00-00
Work Completed
Time Computed05-05-24
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-110
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243229
Totals1666764.200.000.000.0

CountyWHARTON
HighwayUS 59
FromFM 1163
To900 FT N OF CR 355
CSJ0089-06-092
Proj IDSTP 2023(977)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.4623220561.050.000.0
CountyWHARTON
HighwayUS 59
FromFM 960
ToFM 1163
CSJ0089-07-164
Proj IDSTP 2023(977)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.4642938497.090.000.0
CountyVICTORIA
HighwayUS 77
From750 FT N OF COLETO CREEK BRIDGE
ToFLEMING PRAIRIE RD
CSJ0371-01-093
Proj IDSTP 2023(977)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.808960841.860.000.0
Work Order07-26-23
Work Began00-00-00
Work Completed
Time Computed10-24-23
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-092
MTAM CORPORATION (1.16)
QUALITY TURF FARMS, L.C. (0.65)
LONESTAR TRAFFIC SAFETY, LLC (0.27)
ROADWAY SPECIALTIES, INC. (0.76)
Contract #06233610
Totals7119900.000.000.000.0

CountyWHARTON
HighwayUS 59
From0.40 MI S OF CR 357
To0.40 MI N OF CR 357
CSJ0089-06-093
Proj IDC 89-6-93
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8102182905.020.000.0
Work Order07-26-23
Work Began02-28-24
Work Completed
Time Computed10-24-23
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-093
TRAFFIC SIGNS & LINES, LLC (4.62)
CEN TEX HYDROSEED, INC. (1.20)
PROFESSIONAL TRAFFIC CONTROL LLC (0.32)
Contract #06233024
Totals2182905.020.000.000.0

CountyWHARTON
HighwayUS 59
FromBU 59 NORTH OF ELCAMPO
ToSH 71
CSJ0089-07-146
Proj IDNH 2019(437)
Work TypeCONSTRUCT FRONTAGE ROADS
 
3.16834757444.7636081243.2899.9
Work Order02-20-19
Work Began06-20-19
Work Completed
Time Computed05-21-19
Contract Working Days450
Addl Days Granted29
Working Days Charged479
Percent Time Used100
Contractor(s)
SER CONSTRUCTION PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0089-07-146
RELIABLE SIGNAL & LIGHTING SOLUTIONS, LLC (2.54)
ROADWAY CONSTRUCTION, LLC (0.74)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.34)
ANGEL BROTHERS HOLDINGS CORP. (10.74)
A BROTHERS MILLING, LLC (0.93)
SOUTHERN CRUSHED CONCRETE LLC (0.84)
BATTERSON,LLP (1.28)
JMHP, INC. (0.34)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28)
MESA ROD BUSTERS, INC. (0.05)
MONTALVO BRIDGE SYSTEMS, LLC (0.14)
ROADWAY SPECIALTIES, INC. (0.41)
TITO"S TRUCKING & SONS, LLC (0.00)
CURB PLANET INC. (0.05)
PRIMATE CONSTRUCTION, LP (0.02)
PRV SERVICES, INC. (0.00)
ALLGAYER, INC. (0.00)
SCOTT DERR PAINTING CO, LLC (0.30)
HODGES BROTHERS, INC. (0.00)
AARON CONCRETE CONTRACTORS, L.P. (0.81)
TEXAS MATERIALS GROUP, INC. (10.74)
WEST TEXAS ROCK RESOURCES, LLC (0.01)
Contract #01193002
Totals34757444.76712.0036081243.2899.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8