Monthly State Let Construction Report For Abilene District As Of Jan 11, 2017 Page 1 Of 2

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayIH 20
FromAT US 87 (NEW LOCATION)
To.
CSJ0005-05-102
Proj IDDMO 2012(263)
Work TypeCONSTRUCT NEW INTERCHANGE
 
2.71918434933.5818455446.6299.9
Work Order08-19-13
Work Began05-13-14
Work Completed
Time Computed01-01-14
Contract Working Days470
Addl Days Granted59
Working Days Charged542
Percent Time Used102
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-102
W.S. CONSTRUCTION COMPANY (8.38)
COPPELL CONSTRUCTION CO., INC. (8.49)
DRILL TECH DRILLING & SHORING, INC. (16.58)
PRICE CONSTRUCTION, LTD. (28.11)
TEXAS SHAFTS, INC. (1.76)
FELIX CHAVEZ & SON CONSTRUCTION (0.24)
MARTIN GONZALES INCORPORATED (1.32)
WILLIS ELECTRIC CO., LP (2.27)
HJC FARMS, INC. (1.58)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36)
TEX OP CONSTRUCTION, LP (0.23)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING (0.50)
ARANDA`S TRUCKING (0.74)
NOBLES ROAD CONSTRUCTION, INC. (0.26)
AARON CONCRETE CONTRACTORS, L.P. (0.60)
Contract #05133202
Totals18434933.584700.0018455446.6299.9

CountyMITCHELL
HighwayBI 20-J
FromIH 20 W OF COLORADO CITY
ToIH 20 E OF COLORADO CITY
CSJ0005-12-013
Proj IDSTP 2017(455)
Work TypeFLX PAV STR RPR,UNDSL,&ACP OVERLAY
 
5.9262838058.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-12-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173207
Totals2838058.330.000.000.0

CountyNOLAN ETC
HighwayIH 20 ETC
From0.037 MI W OF CR 104
To1.1 MI E OF CR 104
CSJ0006-02-112
Proj IDSTP 2016(904)HES
Work TypeHFC, TEXT CL & SHLDR, CHEVRONS
 
8.5603498754.251755260.6450.6
Work Order05-12-16
Work Began08-08-16
Work Completed
Time Computed06-11-16
Contract Working Days48
Addl Days Granted0
Working Days Charged64
Percent Time Used133
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-112
J. H. STRAIN & SONS, INC. (12.56)
HJC FARMS, INC. (1.17)
Contract #04163029
Totals3498754.25101685.701755260.6450.6

CountyTAYLOR ETC
HighwayIH 20 ETC
FromBI 20-Q (SFR ONLY)
ToIH 20 EXIT RAMP 277
CSJ0006-05-114
Proj IDSTP 1602(551)HES
Work TypeINSTALL ADV WARN SIGNS AND CHEVRONS
 
31.986258628.42216828.3283.8
Work Order00-00-00
Work Began11-29-16
Work Completed
Time Computed10-20-16
Contract Working Days32
Addl Days Granted0
Working Days Charged16
Percent Time Used50
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-05-114
SAMMY G. SMALLWOOD (16.16)
Contract #08163009
Totals258628.42136970.74216828.3283.8

CountyTAYLOR
HighwayIH 20
FromIH 20 EAST BOUND LANE
ToAT SH 351(AMBLER AVE IN ABILENE)
CSJ0006-06-099
Proj IDBR 1602(557)
Work TypeREPLACE BRIDGE AND APPROACHES
 
3.93212169359.950.000.0
CountyTAYLOR
HighwaySH 351
FromEAST STAMFORD STREET
ToEAST OVERLAND STREET
CSJ0011-01-035
Proj IDNH 1602(559)
Work TypeEXC,EMB, CONC PAV
 
0.1802469640.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-29-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days445
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-06-099
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163008
Totals14639000.000.000.000.0

CountyCALLAHAN ETC
HighwayIH 20 ETC
From640' E. OF FM 2047 (FRTG RDS ONLY)
To1700' E. OF MEXIA CRK BRIDGE
CSJ0007-01-056
Proj IDNH 2017(364)
Work TypeSEAL COAT
 
245.9788458527.230.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-01-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163005
Totals8458527.230.000.000.0

CountyTAYLOR
HighwaySH 351
FromIH 20
ToABILENE EAST CITY LIMIT
CSJ0011-01-030
Proj IDSTP 1302(056)
Work TypeFL BS,STRS,PCTB,C&G,SDWLK,DRVWY,SMA
 
1.7686920469.817300108.6199.9
Work Order04-10-15
Work Began06-10-15
Work Completed
Time Computed06-10-15
Contract Working Days270
Addl Days Granted41
Working Days Charged319
Percent Time Used102
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-030
CONTRACTORS SERVICE COMPANY (0.59)
WILLIS ELECTRIC CO., LP (12.40)
STRIPING TECHNOLOGY, L.P. (1.68)
MARCOM"S MOWING SERVICE, LLC (0.26)
O. TREVINO CONSTRUCTION, LLC (5.52)
WOLFE CONSTRUCTION GROUP, INC. (0.91)
BILL STARKS CONSTRUCTION COMPANY (3.42)
JORDAN CONCRETE (13.77)
GONZALES CONCRETE CONTRACTORS, INC. (6.30)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (0.66)
Contract #03153036
Totals6920469.81182274.747300108.6199.9

CountySHACKELFORD ETC
HighwayUS 180 ETC
From@ US 283
To.
CSJ0011-06-045
Proj IDSTP 1602(560)HES
Work TypeFLASH BEACON
 
2.390467417.100.000.0
Work Order09-15-16
Work Began00-00-00
Work Completed
Time Computed12-14-16
Contract Working Days87
Addl Days Granted0
Working Days Charged11
Percent Time Used12
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-06-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163239
Totals467417.100.000.000.0

CountyJONES
HighwayUS 83
FromJUST SOUTH OF 13TH STREET IN ANSON
ToNEAR US 277
CSJ0033-04-065
Proj IDNH 2016(149)
Work TypePLANE, PVMNT REPR, UNDERSL, OVERLAY
 
2.4324425888.544264824.3196.3
Work Order11-24-15
Work Began02-29-16
Work Completed
Time Computed02-29-16
Contract Working Days152
Addl Days Granted10
Working Days Charged144
Percent Time Used88
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-065
CONTRACTORS SERVICE COMPANY (0.36)
DUSTROL, INC. (3.77)
BONTKE BROTHERS CONSTRUCTION COMPANY (7.76)
HJC FARMS, INC. (1.80)
BARRICADES UNLIMITED (2.84)
Contract #10153018
Totals4425888.5425768.774264824.3196.3

CountyTAYLOR
HighwayBU 83-D
FromHILL STREET
ToNEAR IH 20
CSJ0033-08-038
Proj IDNH 2016(916)
Work TypePLAN,STR RPR,UNDSL,ACP,MBGF,BR RL
 
7.3949806711.438911316.9790.8
Work Order07-20-16
Work Began08-29-16
Work Completed
Time Computed08-19-16
Contract Working Days67
Addl Days Granted2
Working Days Charged66
Percent Time Used95
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-08-038
A BROTHERS MILLING, LLC (1.64)
HJC FARMS, INC. (0.23)
WILLIS ELECTRIC CO., LP (3.45)
CONTRACTORS SERVICE COMPANY (0.45)
BARRICADES UNLIMITED (2.35)
Contract #04163008
Totals9806711.43463202.628911316.9790.8

CountyTAYLOR
HighwayUS 84
FromUS 83
ToCOLEMAN COUNTY LINE
CSJ0054-01-031
Proj IDNH 2016(917)
Work TypeSPOT REPAIR, SEAL & OVERLAY
 
11.2107380051.177361804.0299.9
Work Order05-19-16
Work Began07-11-16
Work Completed
Time Computed06-17-16
Contract Working Days72
Addl Days Granted7
Working Days Charged101
Percent Time Used127
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0054-01-031
A BROTHERS MILLING, LLC (1.60)
BARRICADES UNLIMITED (2.33)
CONTRACTORS SERVICE COMPANY (0.16)
WEST TEXAS RUMBLE STRIP (0.50)
Contract #04163216
Totals7380051.17492317.407361804.0299.9

CountyCALLAHAN
HighwaySH 36
FromTAYLOR CO. LINE
ToFM 603
CSJ0181-02-029
Proj IDSTP 2016(676)
Work TypePLAN,FLEX PAV STR RPR,SUPER PAV ACP
 
6.2165388974.293736797.2669.3
Work Order04-01-16
Work Began05-02-16
Work Completed
Time Computed05-01-16
Contract Working Days129
Addl Days Granted20
Working Days Charged96
Percent Time Used64
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0181-02-029
CONTRACTORS SERVICE COMPANY (0.31)
WOLFE CONSTRUCTION GROUP, INC. (0.11)
JORDAN CONCRETE (0.00)
HJC FARMS, INC. (1.13)
WILLIS ELECTRIC CO., LP (3.82)
DOUBLE A CONTRACTING, L.P. (3.81)
MICA CORPORATION (1.63)
LUZ LERMA CONSTRUCTION, INC. (2.47)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (1.54)
Contract #02163010
Totals5388974.29332398.323736797.2669.3

CountyJONES
HighwayUS 180
FromNEAR ANSON WEST CITY LIMIT
ToUS 83
CSJ0296-04-019
Proj IDSTP 2017(125)
Work TypePLAN,BS RPR,ACP OV,CONC PAV INTSCTN
 
1.3732950708.420.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-29-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days94
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0296-04-019
TOTAL HIGHWAY MAINTENANCE, LLC (4.46)
GONZALES CONCRETE CONTRACTORS, INC. (17.51)
Contract #10163017
Totals2950708.420.000.000.0

CountyMITCHELL
HighwaySH 208
FromCR 633
ToCOKE COUNTY LINE
CSJ0454-03-041
Proj IDSTP 2016(372)
Work TypeSPOT REPAIR, UNDERSEAL, 2" OV SP-D
 
5.3192654056.802439089.7991.9
Work Order12-21-15
Work Began06-06-16
Work Completed
Time Computed06-01-16
Contract Working Days56
Addl Days Granted0
Working Days Charged43
Percent Time Used76
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0454-03-041
CONTRACTORS SERVICE COMPANY (0.26)
DOUBLE A CONTRACTING, L.P. (2.02)
HUDSON, INC. (1.13)
HJC FARMS, INC. (3.87)
Contract #10153230
Totals2654056.800.002439089.7991.9

CountyTAYLOR
HighwayFM 1235
FromMERKEL CITY LIMIT
ToCR 392
CSJ0663-03-027
Proj IDSTP 2015(789)HES
Work TypeFL BS,REWK BS MATL,2CST,CMP & SET
 
11.0204552099.472665298.8158.5
Work Order06-08-15
Work Began09-08-15
Work Completed
Time Computed09-07-15
Contract Working Days280
Addl Days Granted50
Working Days Charged140
Percent Time Used60
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0663-03-027
CONTRACTORS SERVICE COMPANY (1.01)
DOUBLE A CONTRACTING, L.P. (2.37)
HJC FARMS, INC. (2.91)
BRENDA CONSTRUCTION (11.84)
Contract #04153037
Totals4552099.47179019.382665298.8158.5

CountyTAYLOR
HighwayVA
FromVARIOUS LOCATIONS IN KENT,SCURRY,
ToSTONEWALL,AND HASKELL COUNTIES
CSJ0908-00-080
Proj IDNH 2016(677)
Work TypeINSTALL HIGH MAST ILLUMINATION
 
1.000448260.50468197.4099.9
Work Order03-14-16
Work Began08-09-16
Work Completed
Time Computed04-13-16
Contract Working Days75
Addl Days Granted0
Working Days Charged67
Percent Time Used89
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-080
MICA CORPORATION (66.36)
BARRICADES UNLIMITED (4.22)
BONTKE BROTHERS CONSTRUCTION COMPANY (2.34)
MCL CONTRACTING, LLC (0.82)
Contract #02163037
Totals448260.500.00468197.4099.9

CountyHOWARD
HighwayVA
FromRM 33
ToIH 20
CSJ0908-12-019
Proj IDBOR 2004(670)
Work TypeCONSTRUCT NEW RELIEF ROUTE
 
8.45644837998.9547229485.5699.9
Work Order03-12-14
Work Began07-21-14
Work Completed
Time Computed05-05-14
Contract Working Days679
Addl Days Granted0
Working Days Charged538
Percent Time Used79
Contractor(s)
SUNDT CONSTRUCTION, INC.
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-019
MJE, LLC (2.01)
HARDY HOLE DRILLING (1.14)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.25)
CMT ENGINEERING, INC. (0.11)
MCL CONTRACTING, LLC (1.29)
DUSTROL, INC. (0.95)
OTTO TRUCKING, INC. (4.17)
PENHALL COMPANY (0.03)
DUSTIN ALLEN, INC. (0.27)
WILLIS ELECTRIC CO., LP (0.61)
DYNAMIC VISION CO., INC. (0.18)
DIVERSIFIED HIGHWAY PRODUCTS AND SERVICES (0.06)
ENERGY ELECTRIC SUPPLY, INC. (0.28)
DOUBLE A CONTRACTING, L.P. (0.37)
CRANE SERVICES, INC. (0.18)
LONE STAR HIGHWAY PRODUCTS, INC. (4.86)
SILVIO LOPEZ TRUCKING (0.49)
VULCAN MATERIAL COMPANY_(ABILENE) (1.23)
RMEN TRUCKING (0.39)
MAX TRUCKING (0.19)
P & S TRUCKING (0.09)
LAREDO PAVING, INC. (0.11)
CMT ENGINEERING, INC. (0.12)
AARON CONCRETE CONTRACTORS, L.P. (0.10)
GESCH CONTRACTING, INC. (0.00)
INSTA TURF LAWNS (0.28)
TEXOP CONSTRUCTION (0.02)
Contract #12133201
Totals44837998.954000.0047229485.5699.9

CountyHOWARD
HighwayVA
FromIH 20
ToFM 700
CSJ0908-12-022
Proj IDDMO 1102(493)
Work TypeCONSTRUCT NEW RELIEF ROUTE
 
8.1530.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days680
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163001
Totals0.000.000.000.0

CountyHOWARD
HighwayFM 821
FromFM 2183
ToIH 20
CSJ1156-02-021
Proj IDSTP 2015(794)
Work TypeSUBGR WIDN,FL BS,2CST,STRS,SET,MBGF
 
11.5429379399.558562246.5892.1
Work Order05-19-15
Work Began06-29-15
Work Completed
Time Computed06-19-15
Contract Working Days256
Addl Days Granted0
Working Days Charged331
Percent Time Used129
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1156-02-021
J.V. CONCRETE CONSTRUCTION (2.36)
CONTRACTORS SERVICE COMPANY (0.28)
HJC FARMS, INC. (2.54)
BARRICADES UNLIMITED (2.68)
BRENDA CONSTRUCTION (0.00)
Contract #04153002
Totals9379399.55285097.778562246.5892.1

CountySCURRY
HighwayFM 1606
FromSH 208
ToUS 84
CSJ1526-03-015
Proj IDSTP 2016(678)
Work TypeSUBGR WIDEN, FL BS, STRS, 2CST,MBGF
 
9.3306876410.353115331.0145.3
Work Order04-19-16
Work Began05-09-16
Work Completed
Time Computed05-09-16
Contract Working Days228
Addl Days Granted2
Working Days Charged129
Percent Time Used56
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-03-015
CONTRACTORS SERVICE COMPANY (0.33)
DOUBLE A CONTRACTING (0.33)
HJC FARMS, INC. (3.44)
Contract #02163233
Totals6876410.35607857.013115331.0145.3

page 1 | page 2