Monthly State Let Construction Report For Abilene District As Of Feb 10, 2017 Page 1 Of 2

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayIH 20
FromAT US 87 (NEW LOCATION)
To.
CSJ0005-05-102
Proj IDDMO 2012(263)
Work TypeCONSTRUCT NEW INTERCHANGE
 
2.71918434933.5818457702.6299.9
Work Order08-19-13
Work Began05-13-14
Work Completed
Time Computed01-01-14
Contract Working Days470
Addl Days Granted59
Working Days Charged542
Percent Time Used102
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-102
W.S. CONSTRUCTION COMPANY (8.38)
COPPELL CONSTRUCTION CO., INC. (8.49)
DRILL TECH DRILLING & SHORING, INC. (16.58)
PRICE CONSTRUCTION, LTD. (28.11)
TEXAS SHAFTS, INC. (1.76)
FELIX CHAVEZ & SON CONSTRUCTION (0.24)
MARTIN GONZALES INCORPORATED (1.32)
WILLIS ELECTRIC CO., LP (2.27)
HJC FARMS, INC. (1.58)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36)
TEX OP CONSTRUCTION, LP (0.23)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING (0.50)
ARANDA`S TRUCKING (0.74)
NOBLES ROAD CONSTRUCTION, INC. (0.26)
AARON CONCRETE CONTRACTORS, L.P. (0.60)
Contract #05133202
Totals18434933.582256.0018457702.6299.9

CountyMITCHELL
HighwayBI 20-J
FromIH 20 W OF COLORADO CITY
ToIH 20 E OF COLORADO CITY
CSJ0005-12-013
Proj IDSTP 2017(455)
Work TypeFLX PAV STR RPR,UNDSL,&ACP OVERLAY
 
5.9262838058.330.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days56
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-12-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173207
Totals2838058.330.000.000.0

CountyNOLAN ETC
HighwayIH 20 ETC
From0.037 MI W OF CR 104
To1.1 MI E OF CR 104
CSJ0006-02-112
Proj IDSTP 2016(904)HES
Work TypeHFC, TEXT CL & SHLDR, CHEVRONS
 
8.5603498754.252575635.6474.4
Work Order05-12-16
Work Began08-08-16
Work Completed
Time Computed06-11-16
Contract Working Days48
Addl Days Granted0
Working Days Charged79
Percent Time Used164
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-112
J. H. STRAIN & SONS, INC. (12.56)
HJC FARMS, INC. (1.17)
Contract #04163029
Totals3498754.25820375.002575635.6474.4

CountyTAYLOR
HighwayIH 20
FromIH 20 EAST BOUND LANE
ToAT SH 351(AMBLER AVE IN ABILENE)
CSJ0006-06-099
Proj IDBR 1602(557)
Work TypeREPLACE BRIDGE AND APPROACHES
 
3.93212169359.950.000.0
CountyTAYLOR
HighwaySH 351
FromEAST STAMFORD STREET
ToEAST OVERLAND STREET
CSJ0011-01-035
Proj IDNH 1602(559)
Work TypeEXC,EMB, CONC PAV
 
0.1802469640.050.000.0
Work Order11-29-16
Work Began00-00-00
Work Completed
Time Computed12-29-16
Contract Working Days445
Addl Days Granted0
Working Days Charged12
Percent Time Used2
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-06-099
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163008
Totals14639000.000.000.000.0

CountyCALLAHAN ETC
HighwayIH 20 ETC
From640' E. OF FM 2047 (FRTG RDS ONLY)
To1700' E. OF MEXIA CRK BRIDGE
CSJ0007-01-056
Proj IDNH 2017(364)
Work TypeSEAL COAT
 
245.9788458527.23468124.005.5
Work Order01-25-17
Work Began00-00-00
Work Completed
Time Computed05-01-17
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0007-01-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163005
Totals8458527.23468124.00468124.005.5

CountyTAYLOR
HighwaySH 351
FromIH 20
ToABILENE EAST CITY LIMIT
CSJ0011-01-030
Proj IDSTP 1302(056)
Work TypeFL BS,STRS,PCTB,C&G,SDWLK,DRVWY,SMA
 
1.7686920469.817385291.8199.9
Work Order04-10-15
Work Began06-10-15
Work Completed
Time Computed06-10-15
Contract Working Days270
Addl Days Granted41
Working Days Charged324
Percent Time Used104
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-030
CONTRACTORS SERVICE COMPANY (0.59)
WILLIS ELECTRIC CO., LP (12.40)
STRIPING TECHNOLOGY, L.P. (1.68)
MARCOM"S MOWING SERVICE, LLC (0.26)
O. TREVINO CONSTRUCTION, LLC (5.52)
WOLFE CONSTRUCTION GROUP, INC. (0.91)
BILL STARKS CONSTRUCTION COMPANY (3.42)
JORDAN CONCRETE (13.77)
GONZALES CONCRETE CONTRACTORS, INC. (6.30)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (0.66)
Contract #03153036
Totals6920469.8185183.207385291.8199.9

CountySHACKELFORD ETC
HighwayUS 180 ETC
From@ US 283
To.
CSJ0011-06-045
Proj IDSTP 1602(560)HES
Work TypeFLASH BEACON
 
2.390467417.1059085.0012.6
Work Order09-15-16
Work Began01-10-17
Work Completed
Time Computed12-14-16
Contract Working Days87
Addl Days Granted0
Working Days Charged34
Percent Time Used39
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0011-06-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08163239
Totals467417.1059085.0059085.0012.6

CountyTAYLOR
HighwayBU 83-D
FromHILL STREET
ToNEAR IH 20
CSJ0033-08-038
Proj IDNH 2016(916)
Work TypePLAN,STR RPR,UNDSL,ACP,MBGF,BR RL
 
7.3949806711.439132274.1793.1
Work Order07-20-16
Work Began08-29-16
Work Completed
Time Computed08-19-16
Contract Working Days67
Addl Days Granted2
Working Days Charged69
Percent Time Used100
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-08-038
A BROTHERS MILLING, LLC (1.64)
HJC FARMS, INC. (0.23)
WILLIS ELECTRIC CO., LP (3.45)
CONTRACTORS SERVICE COMPANY (0.45)
BARRICADES UNLIMITED (2.35)
Contract #04163008
Totals9806711.43220957.209132274.1793.1

CountyTAYLOR
HighwayUS 84
FromUS 83
ToCOLEMAN COUNTY LINE
CSJ0054-01-031
Proj IDNH 2016(917)
Work TypeSPOT REPAIR, SEAL & OVERLAY
 
11.2107380051.177457311.0699.9
Work Order05-19-16
Work Began07-11-16
Work Completed
Time Computed06-17-16
Contract Working Days72
Addl Days Granted10
Working Days Charged109
Percent Time Used132
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0054-01-031
A BROTHERS MILLING, LLC (1.60)
BARRICADES UNLIMITED (2.33)
CONTRACTORS SERVICE COMPANY (0.16)
WEST TEXAS RUMBLE STRIP (0.50)
Contract #04163216
Totals7380051.1795507.047457311.0699.9

CountyCALLAHAN
HighwaySH 36
FromTAYLOR CO. LINE
ToFM 603
CSJ0181-02-029
Proj IDSTP 2016(676)
Work TypePLAN,FLEX PAV STR RPR,SUPER PAV ACP
 
6.2165388974.294050340.2875.1
Work Order04-01-16
Work Began05-02-16
Work Completed
Time Computed05-01-16
Contract Working Days129
Addl Days Granted20
Working Days Charged110
Percent Time Used73
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0181-02-029
CONTRACTORS SERVICE COMPANY (0.31)
WOLFE CONSTRUCTION GROUP, INC. (0.11)
JORDAN CONCRETE (0.00)
HJC FARMS, INC. (1.13)
WILLIS ELECTRIC CO., LP (3.82)
DOUBLE A CONTRACTING, L.P. (3.81)
MICA CORPORATION (1.63)
LUZ LERMA CONSTRUCTION, INC. (2.47)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (1.54)
Contract #02163010
Totals5388974.29313543.024050340.2875.1

CountyJONES
HighwayUS 180
FromNEAR ANSON WEST CITY LIMIT
ToUS 83
CSJ0296-04-019
Proj IDSTP 2017(125)
Work TypePLAN,BS RPR,ACP OV,CONC PAV INTSCTN
 
1.3732950708.42285327.809.6
Work Order11-29-16
Work Began01-02-17
Work Completed
Time Computed12-29-16
Contract Working Days94
Addl Days Granted0
Working Days Charged20
Percent Time Used21
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0296-04-019
TOTAL HIGHWAY MAINTENANCE, LLC (4.46)
GONZALES CONCRETE CONTRACTORS, INC. (17.51)
Contract #10163017
Totals2950708.42285327.80285327.809.6

CountyMITCHELL
HighwaySH 208
FromCR 633
ToCOKE COUNTY LINE
CSJ0454-03-041
Proj IDSTP 2016(372)
Work TypeSPOT REPAIR, UNDERSEAL, 2" OV SP-D
 
5.3192654056.802439089.7991.9
Work Order12-21-15
Work Began06-06-16
Work Completed
Time Computed06-01-16
Contract Working Days56
Addl Days Granted0
Working Days Charged43
Percent Time Used76
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0454-03-041
CONTRACTORS SERVICE COMPANY (0.26)
DOUBLE A CONTRACTING, L.P. (2.02)
HUDSON, INC. (1.13)
HJC FARMS, INC. (3.87)
Contract #10153230
Totals2654056.800.002439089.7991.9

CountyTAYLOR
HighwayFM 1235
FromMERKEL CITY LIMIT
ToCR 392
CSJ0663-03-027
Proj IDSTP 2015(789)HES
Work TypeFL BS,REWK BS MATL,2CST,CMP & SET
 
11.0204552099.473064200.3067.3
Work Order06-08-15
Work Began09-08-15
Work Completed
Time Computed09-07-15
Contract Working Days280
Addl Days Granted50
Working Days Charged160
Percent Time Used69
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0663-03-027
CONTRACTORS SERVICE COMPANY (1.01)
DOUBLE A CONTRACTING, L.P. (2.37)
HJC FARMS, INC. (2.91)
BRENDA CONSTRUCTION (11.84)
Contract #04153037
Totals4552099.47398901.493064200.3067.3

CountyHOWARD
HighwayVA
FromRM 33
ToIH 20
CSJ0908-12-019
Proj IDBOR 2004(670)
Work TypeCONSTRUCT NEW RELIEF ROUTE
 
8.45644837998.9547233655.5699.9
Work Order03-12-14
Work Began07-21-14
Work Completed
Time Computed05-05-14
Contract Working Days679
Addl Days Granted0
Working Days Charged538
Percent Time Used79
Contractor(s)
SUNDT CONSTRUCTION, INC.
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-019
MJE, LLC (2.01)
HARDY HOLE DRILLING (1.14)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.25)
CMT ENGINEERING, INC. (0.11)
MCL CONTRACTING, LLC (1.29)
DUSTROL, INC. (0.95)
OTTO TRUCKING, INC. (4.17)
PENHALL COMPANY (0.03)
DUSTIN ALLEN, INC. (0.27)
WILLIS ELECTRIC CO., LP (0.61)
DYNAMIC VISION CO., INC. (0.18)
DIVERSIFIED HIGHWAY PRODUCTS AND SERVICES (0.06)
ENERGY ELECTRIC SUPPLY, INC. (0.28)
DOUBLE A CONTRACTING, L.P. (0.37)
CRANE SERVICES, INC. (0.18)
LONE STAR HIGHWAY PRODUCTS, INC. (4.86)
SILVIO LOPEZ TRUCKING (0.49)
VULCAN MATERIAL COMPANY_(ABILENE) (1.23)
RMEN TRUCKING (0.39)
MAX TRUCKING (0.19)
P & S TRUCKING (0.09)
LAREDO PAVING, INC. (0.11)
CMT ENGINEERING, INC. (0.12)
AARON CONCRETE CONTRACTORS, L.P. (0.10)
GESCH CONTRACTING, INC. (0.00)
INSTA TURF LAWNS (0.28)
TEXOP CONSTRUCTION (0.02)
Contract #12133201
Totals44837998.954170.0047233655.5699.9

CountyHOWARD
HighwayVA
FromIH 20
ToFM 700
CSJ0908-12-022
Proj IDDMO 1102(493)
Work TypeCONSTRUCT NEW RELIEF ROUTE
 
8.1530.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-13-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days680
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-022
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163001
Totals0.000.000.000.0

CountyHOWARD
HighwayFM 821
FromFM 2183
ToIH 20
CSJ1156-02-021
Proj IDSTP 2015(794)
Work TypeSUBGR WIDN,FL BS,2CST,STRS,SET,MBGF
 
11.5429379399.558702840.3193.6
Work Order05-19-15
Work Began06-29-15
Work Completed
Time Computed06-19-15
Contract Working Days256
Addl Days Granted0
Working Days Charged332
Percent Time Used129
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1156-02-021
J.V. CONCRETE CONSTRUCTION (2.36)
CONTRACTORS SERVICE COMPANY (0.28)
HJC FARMS, INC. (2.54)
BARRICADES UNLIMITED (2.68)
BRENDA CONSTRUCTION (0.00)
Contract #04153002
Totals9379399.55140593.738702840.3193.6

CountySCURRY
HighwayFM 1606
FromSH 208
ToUS 84
CSJ1526-03-015
Proj IDSTP 2016(678)
Work TypeSUBGR WIDEN, FL BS, STRS, 2CST,MBGF
 
9.3306876410.353321674.5148.3
Work Order04-19-16
Work Began05-09-16
Work Completed
Time Computed05-09-16
Contract Working Days228
Addl Days Granted2
Working Days Charged145
Percent Time Used63
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-03-015
CONTRACTORS SERVICE COMPANY (0.33)
DOUBLE A CONTRACTING (0.33)
HJC FARMS, INC. (3.44)
Contract #02163233
Totals6876410.35206343.503321674.5148.3

CountySCURRY
HighwayFM 1610
FromBORDEN COUNTY LINE
ToFM 1606
CSJ1531-02-012
Proj IDSTP 2016(679)
Work TypeRESTORE AND WIDEN EXISTING ROADWAY
 
7.0445397845.791689401.7731.2
Work Order04-14-16
Work Began08-02-16
Work Completed
Time Computed05-14-16
Contract Working Days220
Addl Days Granted0
Working Days Charged127
Percent Time Used57
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1531-02-012
CONTRACTORS SERVICE COMPANY (0.49)
BRENDA CONSTRUCTION (8.07)
BARRICADES UNLIMITED (1.08)
HJC FARMS, INC. (2.28)
Contract #02163022
Totals5397845.79185565.271689401.7731.2

CountyHOWARD
HighwayFM 846
FromFM 669
ToFM 1205
CSJ1872-02-017
Proj IDSTP 1502(216)
Work TypeEMB, EXC, STRS, SET, SURF, MBGF
 
16.0929519743.527495173.8578.7
Work Order07-30-15
Work Began11-16-15
Work Completed
Time Computed09-28-15
Contract Working Days311
Addl Days Granted0
Working Days Charged245
Percent Time Used78
Contractor(s)
SBBI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1872-02-017
BARRICADES UNLIMITED (3.62)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (5.46)
WEST TEXAS ROCK RESOURCES, LLC (0.00)
BRETT CONSTRUCTION COMPANY (0.43)
BLACK JACK ENERGY SERVICES, LLC (11.17)
NOBLES ROAD CONSTRUCTION, INC. (0.93)
Contract #05153055
Totals9519743.52611689.067495173.8578.7

CountyHOWARD
HighwayFM 2230
FromUS 87
ToFM 846
CSJ2149-01-009
Proj IDSTP 2013(765)
Work TypeEXC,EMB,FL BS,STRS,2 CRSE SURF TRT
 
10.9656178220.665418871.2587.7
Work Order04-02-15
Work Began05-20-15
Work Completed
Time Computed06-01-15
Contract Working Days331
Addl Days Granted10
Working Days Charged312
Percent Time Used91
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2149-01-009
REECE CONSTRUCTION CO., INC. (26.62)
GARY A. CRAIN, INC. (0.05)
TEXAS SHAFTS, INC. (1.31)
ALTUS TRAFFIC MANAGEMENT LLC (0.50)
BARRICADES UNLIMITED (1.44)
HJC FARMS, INC. (1.06)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.05)
SAENZ TRANSPORT, LLC (6.16)
ARANDA"S TRUCKING (2.26)
GONZALES DUMP TRUCK SERVICES (0.80)
Contract #02153010
Totals6178220.6616407.455418871.2587.7

page 1 | page 2