Monthly State Let Maintenance Report For Abilene District As Of Sep 15, 2014 Page 1 Of 1

Last Update: Monday, September 15, 2014
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTAYLOR
Highway IH0020
From TAYLOR, CALLAHAN, SHACKELFORD,JONES
To HASKELL, STONEWALL COUNTIES
CSJ 6249-60-001
Proj ID RMC - 624960001
Work Type ON CALL MBGF
 
0.001 569199.42 47153.00 913100.66 99.9
Work Order 03-26-13
Work Began 03-27-13
Work Completed  
Time Computed 04-02-13
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 518
Percent Time Used 70
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6249-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134041
Totals 569199.42 47153.00 913100.66 99.9

CountyHOWARD
Highway IH0020
From VARIOUS LOCATIONS IN
To THE ABILENE DISTRICT
CSJ 6264-37-001
Proj ID RMC - 626437001
Work Type SEAL COAT
 
0.010 4336163.04 0.00 4474389.68 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-21-14
Work Began 03-24-14
Work Completed  
Time Computed 04-28-14
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 64
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-37-001
TOTAL HIGHWAY MAINTENANCE, LLC (0.59%)
FLAT LINE, INC.(0.00%)
Contract # 11134023
Totals 4336163.04 0.00 4474389.68 99.9

page 1