Monthly State Let Construction Report For Amarillo District As Of Mar 13, 2024 Page 2 Of 4

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDEAF SMITH
HighwayUS 60
FromCAVINESS BEEF PLANT
To.
CSJ0168-05-043
Proj IDC 168-5-43
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1956451.450.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed05-01-24
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0168-05-043
BARRICADES UNLIMITED (0.70)
C & C ENVIRONMENTAL SERVICES (0.14)
MARCOM"S MOWING SERVICE, LLC (1.10)
Contract #01243031
Totals1956451.450.000.000.0

CountyDEAF SMITH
HighwayUS 60
FromEAST OF HEREFORD
ToRANDALL COUNTY LINE
CSJ0168-07-050
Proj IDC 168-7-50
Work TypeREHABILITATION OF EXISTING ROAD
 
26.39023784485.6011077775.5246.5
Work Order02-16-23
Work Began04-10-23
Work Completed
Time Computed03-18-23
Contract Working Days194
Addl Days Granted0
Working Days Charged154
Percent Time Used79
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0168-07-050
FC TRAFFIC CONTROL, INC. (0.16)
INDUSTRIAL FABRICS, INC. (4.52)
PROFESSIONAL TRAFFIC CONTROL LLC (0.18)
TEX OP CONSTRUCTION, LP (1.14)
TRP CONSTRUCTION GROUP, LLC (1.66)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.34)
W. S. CONSTRUCTION COMPANY (0.58)
Contract #01233202
Totals23784485.6095761.2911077775.5246.5

CountyRANDALL
HighwayUS 60
FromDEAF SMITH CO LINE
ToUS 87 IN CANYON
CSJ0168-08-075
Proj IDF 2024(033)
Work TypeREHABILITATION OF EXISTING ROAD
 
15.07734924133.61170100.000.4
Work Order12-06-23
Work Began00-00-00
Work Completed
Time Computed03-04-24
Contract Working Days290
Addl Days Granted0
Working Days Charged1
Percent Time Used0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-08-075
ALAMO BROTHERS CONCRETE INC (0.90)
FC TRAFFIC CONTROL, INC. (0.19)
H & F TRUCKING (0.02)
HJC FARMS, INC. (0.24)
MOBILE ENTERPRISES, INC. (0.20)
PERFORMANCE EQUIPMENT SERVICE (1.76)
SAENZ TRANSPORT, LLC (0.14)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.06)
TEX OP CONSTRUCTION, LP (1.13)
TRP CONSTRUCTION GROUP, LLC (1.99)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.10)
W. S. CONSTRUCTION COMPANY (1.07)
TEXAS ROAD RECYCLERS, L.L.C. (0.53)
Contract #09233203
Totals34924133.61170100.00170100.000.4

CountyRANDALL
HighwayIH 27
FromSL 335
ToNORTH OF US 60/US 87 INTERCHANGE
CSJ0168-09-083
Proj IDF 2024(864)
Work TypeWIDEN FREEWAY
 
0.794312507980.860.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days1,155
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243044
Totals312507980.860.000.000.0

CountyRANDALL
HighwayIH 27
From0.058 MILES SOUTH OF 45TH AVE
ToPOTTER COUNTY LINE
CSJ0168-09-180
Proj IDSTP 2021(517)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.5215291174.655204526.8498.3
CountyRANDALL
HighwayIH 27
From45TH AVE
ToPOTTER COUNTY LINE
CSJ0168-09-181
Proj IDF 2021(518)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
3.15625024977.7610457351.2641.7
CountyPOTTER
HighwayIH 27
FromRANDALL COUNTY LINE
To0.2 MILES SOUTH OF IH 40
CSJ0168-10-077
Proj IDSTP 2021(517)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.499682460.65891776.0999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-22-21
Work Began09-07-21
Work Completed
Time Computed00-00-00
Contract Working Days847
Addl Days Granted24
Working Days Charged612
Percent Time Used70
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-09-180
BARRICADES UNLIMITED (1.18)
SLATON BROTHERS, INC. (2.58)
H & F TRUCKING (2.17)
J. H. ODEN CONTRACTING COMPANY (0.18)
WILLIAMS DITCHING, LLC (1.21)
HJC FARMS, INC. (1.70)
GHC TRANSPORT, L.L.C. (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.45)
PRIMATE CONSTRUCTION, LP (0.31)
JB PINNACLE GROUP, LLC (11.06)
ARTEX ELECTRIC, INC. (2.19)
OSCAR ORDUNO, INC. (5.42)
DUSTROL, INC. (0.44)
URBAN INFRACONSTRUCTION LLC (0.20)
IBCTX, LLC (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.17)
ALAMO BROTHERS CONCRETE INC (4.11)
LMSE TRUCKING, LLC (0.00)
Contract #05213202
Totals30998613.06134096.3916553654.1953.4

CountyPOTTER
HighwayUS 60
FromSL 335
ToCARSON COUNTY LINE
CSJ0169-02-068
Proj IDSTP 2023(181)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
6.8432207755.002092610.4995.5
Work Order12-07-22
Work Began03-29-23
Work Completed
Time Computed01-06-23
Contract Working Days106
Addl Days Granted3
Working Days Charged130
Percent Time Used119
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0169-02-068
URBAN HEIGHTS INVESTMENTS LLC (1.35)
DK CONTRACTING, LLC (1.82)
BARRICADES UNLIMITED (0.57)
C & C ENVIRONMENTAL SERVICES (0.58)
TRP CONSTRUCTION GROUP, LLC (2.78)
ALPHA CORPS CONCRETE & CONSTRUCTION, LLC (1.79)
B & G ELECTRIC (0.72)
TURKEY CREEK HDD, LLC (0.09)
ALPHA CORPS CONCRETE & CONSTRUCTION, LLC (1.62)
J. LEE MILLIGAN, INC. (33.76)
Contract #11223219
Totals2207755.002282.502092610.4995.5

CountyCARSON
HighwayUS 60
FromFROM POTTER CO LINE
To5 MILES WEST OF PANHANDLE
CSJ0169-03-039
Proj IDSTP 2022(502)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3699105.453765617.8699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-31-22
Work Began04-03-23
Work Completed
Time Computed00-00-00
Contract Working Days91
Addl Days Granted0
Working Days Charged83
Percent Time Used91
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0169-03-039
ALAMO BROTHERS CONCRETE INC (4.10)
TOTAL SITE, INC. (0.43)
WILLIS ELECTRIC CO., LP (17.82)
J. LEE MILLIGAN, INC. (45.51)
FC TRAFFIC CONTROL, INC. (0.33)
FIBERTEX, LLC (0.67)
LINEAR TRAFFIC MARKINGS LLC (1.46)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.24)
JVH4 SERVICES, LLC (0.43)
Contract #05223221
Totals3699105.450.003765617.8699.9

CountyGRAY
HighwayUS 60
FromLP 171 IN PAMPA
ToROBERTS COUNTY LINE
CSJ0169-07-053
Proj IDC 169-7-53
Work TypeSUPER-2 HIGHWAY
 
12.90014712201.1616392802.2999.9
CountyGRAY
HighwayUS 60
FromTIGNOR ST
ToCOUNTY ROAD 10
CSJ0169-07-054
Proj IDC 169-7-54
Work TypeREHABILITATION OF EXISTING ROAD
 
1.4271824177.811014268.7055.6
Work Order09-16-21
Work Began03-01-22
Work Completed
Time Computed10-18-21
Contract Working Days351
Addl Days Granted0
Working Days Charged307
Percent Time Used87
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0169-07-053
BARRICADES UNLIMITED (1.40)
DUSTIN ALLEN, INC. (1.58)
MARCOM"S MOWING SERVICE, LLC (0.66)
PINNACLE GRINDING AND GROOVING LLC (0.10)
TEX OP CONSTRUCTION, LP (0.74)
WITHERS CONSTRUCTION, LLC (0.23)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.18)
W. S. CONSTRUCTION COMPANY (2.52)
TRP CONSTRUCTION GROUP, LLC (1.11)
SCR CIVIL CONSTRUCTION, LLC (0.12)
Contract #08213006
Totals16536378.97319409.8717407070.9999.9

CountyOLDHAM
HighwayUS 385
FromHARTLEY COUNTY LINE
ToSOUTH OF CANADIAN RIVER BRIDGE
CSJ0226-02-038
Proj IDF 2022(282)
Work TypeSUPER-2 HIGHWAY
 
8.7499766079.7110570002.4699.9
Work Order01-10-22
Work Began03-21-22
Work Completed
Time Computed02-09-22
Contract Working Days150
Addl Days Granted0
Working Days Charged181
Percent Time Used120
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0226-02-038
SURFACE PREPARATION TECHNOLOGIES, LLC (0.17)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.13)
ALAMO BROTHERS CONCRETE INC (7.75)
BARRICADES UNLIMITED (1.99)
HJC FARMS, INC. (7.33)
Contract #12213024
Totals9766079.710.0010570002.4699.9

CountyPOTTER
HighwayIH 40
FromBI 40-D
ToFM 2590 (SONCY ROAD)
CSJ0275-01-199
Proj IDNH 2020(549)
Work TypeREHABILITATION OF EXISTING ROAD
 
1.86325360575.7727269620.6099.9
CountyPOTTER
HighwaySL 335
FromFM 2590 NORTH
ToSW 9TH
CSJ2635-04-037
Proj IDNH 2020(550)
Work TypeNEW LOCATION NON-FREEWAY
 
2.33324672131.9724795253.4799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-20
Work Began05-04-20
Work Completed
Time Computed00-00-00
Contract Working Days575
Addl Days Granted168
Working Days Charged928
Percent Time Used124
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-199
AARON CONCRETE CONTRACTORS, L.P. (1.01)
ACT SAW CUTTING & REMOVAL (0.11)
BARRICADES UNLIMITED (0.58)
CHEROKEE SERVICES (0.09)
SCOTT DERR PAINTING CO, LLC (0.07)
SOUTHEAST GRINDING & GROOVING, LLC (0.03)
TEXOP CONSTRUCTION (0.51)
TORO BRAVO CONSTRUCTION, LLC (0.20)
WILLIAMS DITCHING, LLC (4.71)
FC TRAFFIC CONTROL, INC. (0.32)
HJC FARMS, INC. (1.69)
H & F TRUCKING (4.90)
ARTEX ELECTRIC, INC. (2.34)
FARR FOUNDATION, INC. (0.77)
ALAMO BROTHERS CONCRETE INC (3.05)
DK CONTRACTING, LLC (0.01)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.02)
DIIBS SPECIALISTS, LLC (0.02)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.00)
G & L REBAR (0.00)
URBAN INFRACONSTRUCTION LLC (0.20)
G & L REBAR (0.07)
ROYAL REBAR (0.02)
WEBBER BARRIER SERVICES, LLC. (0.03)
GHC TRANSPORT, L.L.C. (0.00)
PEREZ REBAR CONSTRUCTION (0.01)
DRILL PIER CONSTRUCTION, LLC (0.01)
MASSANA CONSTRUCTION INC. (0.18)
ARANDA TRANSPORT LLC (0.00)
TRP CONSTRUCTION GROUP, LLC (0.22)
APOLLO CONSTRUCTORS, INC. (1.42)
Contract #02203001
Totals50032707.74334550.5652064874.0799.9

CountyPOTTER
HighwayIH 40
FromROSS ST
ToWHITAKER RD
CSJ0275-01-221
Proj IDF 2022(166)
Work TypeOVERLAY
 
15.24713120890.3512581804.1096.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-27-22
Work Began06-15-22
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged157
Percent Time Used108
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-221
ALAMO BROTHERS CONCRETE INC (11.46)
BARRICADES UNLIMITED (1.45)
HJC FARMS, INC. (4.27)
STRAIGHT LINE SAWING & SEALING, INC. (2.27)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.03)
Contract #12213005
Totals13120890.350.0012581804.1096.0

CountyPOTTER
HighwayIH 40 ETC
FromAT IH 27
To.
CSJ0275-01-229
Proj IDBR 2023(596)
Work TypeBRIDGE MAINTENANCE
 
0.1558159181.051846431.0022.6
Work Order06-14-23
Work Began10-09-23
Work Completed
Time Computed07-14-23
Contract Working Days175
Addl Days Granted54
Working Days Charged30
Percent Time Used13
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-01-229
FC TRAFFIC CONTROL, INC. (0.64)
TRP CONSTRUCTION GROUP, LLC (3.50)
J.H. PAINTING COMPANY (0.69)
SOUTHEAST GRINDING AND GROOVING LLC (0.52)
A-CORE CONCRETE CUTTING, INC. (2.67)
Contract #04233007
Totals8159181.057500.001846431.0022.6

CountyCARSON ETC
HighwayIH 40 ETC
FromAT BI 40 F
To.
CSJ0275-04-061
Proj IDBR 2024(461)
Work TypeBRIDGE MAINTENANCE
 
13665830.900.000.0
Work Order01-04-24
Work Began00-00-00
Work Completed
Time Computed02-03-24
Contract Working Days468
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0275-04-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12233007
Totals13665830.900.000.000.0

CountyCARSON
HighwayIH 40
FromWB MM 107
ToWB MM 107.6
CSJ0275-04-069
Proj IDSTP 2B23(012)TAPS
Work TypeRESTORATION
 
0.6006318689.75659326.3010.4
Work Order09-06-23
Work Began01-29-24
Work Completed
Time Computed12-03-23
Contract Working Days96
Addl Days Granted0
Working Days Charged20
Percent Time Used20
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-04-069
APOLLO CONSTRUCTORS, INC. (7.29)
BARRICADES UNLIMITED (0.09)
GREEN PLAINS DESIGN (3.10)
HJC FARMS, INC. (1.55)
PRIMATE CONSTRUCTION, LP (1.05)
TRP CONSTRUCTION GROUP, LLC (1.19)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.11)
Contract #08233226
Totals6318689.75571236.30659326.3010.4

CountyGRAY
HighwayIH 40
FromW BI 40 H IN MCLEAN
ToSH 273
CSJ0275-11-090
Proj IDBR 2024(136)
Work TypeBRIDGE WIDENING OR REHABILITATION
 
12919745.1072240.000.5
Work Order11-16-23
Work Began00-00-00
Work Completed
Time Computed12-16-23
Contract Working Days247
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-11-090
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233010
Totals12919745.100.0072240.000.5

CountyHANSFORD
HighwaySH 207
FromFARWELL DRAW
To.
CSJ0308-01-013
Proj IDBR 2022(681)
Work TypeBRIDGE REPLACEMENT
 
0.0791667991.001880864.2599.9
CountySHERMAN
HighwayFM 119
FromCOLDWATER CREEK
To.
CSJ0727-02-023
Proj IDBR 2022(681)
Work TypeBRIDGE REPLACEMENT
 
0.0761880322.551867307.8599.3
CountyHANSFORD
HighwaySH 15
FromCOLDWATER CREEK
To.
CSJ0790-05-034
Proj IDBR 2022(681)
Work TypeBRIDGE REPLACEMENT
 
4358816.053902690.9389.5
Work Order08-02-22
Work Began02-06-23
Work Completed
Time Computed09-01-22
Contract Working Days387
Addl Days Granted0
Working Days Charged266
Percent Time Used68
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0308-01-013
HUNTER DEMOLITION & WRECKING CORPORATION (2.90)
FC TRAFFIC CONTROL, INC. (0.53)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.28)
PRIMATE CONSTRUCTION, LP (1.45)
HJC FARMS, INC. (2.63)
TRP CONSTRUCTION GROUP, LLC (0.47)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (100.00)
S & S BRIDGE PAINTING, INC. (0.38)
ALAMO BROTHERS CONCRETE INC (3.18)
Contract #06223612
Totals7907129.60346691.157650863.0396.2

CountyHUTCHINSON
HighwaySH 136
From0.1 MILES SOUTH OF SH 152
ToNORTH BORGER TRAFFIC CIRCLE
CSJ0356-01-107
Proj IDF 2023(456)
Work TypeOVERLAY
 
9.5369658644.050.000.0
Work Order03-13-23
Work Began00-00-00
Work Completed
Time Computed04-12-23
Contract Working Days100
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-107
BARRICADES UNLIMITED (0.19)
DK CONTRACTING, LLC (0.44)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.20)
DUSTIN ALLEN, INC. (6.18)
TEXOP CONSTRUCTION (0.68)
TRP CONSTRUCTION GROUP, LLC (1.48)
WITHERS CONSTRUCTION, LLC (0.93)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.36)
W. S. CONSTRUCTION COMPANY (6.56)
Contract #02233208
Totals9658644.050.000.000.0

CountyHUTCHINSON
HighwaySH 136
FromNORTH OF BORGER TRAFFIC CIRCLE
To240' NORTH OF JEFFERSON ST
CSJ0356-01-108
Proj IDF 2024(462)
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
2.7664885721.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed03-04-24
Contract Working Days263
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12233207
Totals4885721.300.000.000.0

CountyCARSON
HighwaySH 207
FromBNSF RAILROAD UNDERPASS (PANHANDLE)
To.
CSJ0356-02-048
Proj IDSTP 2020(635)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.1761042468.001210796.9499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-07-20
Work Began03-26-21
Work Completed
Time Computed00-00-00
Contract Working Days129
Addl Days Granted1
Working Days Charged131
Percent Time Used100
Contractor(s)
L A FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-048
ALAMO BROTHERS CONCRETE INC (12.33)
RAY ELECTRIC COMPANY (4.59)
Contract #03203029
Totals1042468.000.001210796.9499.9

CountyGRAY
HighwaySH 152
FromUS 60
ToWHEELER CO LINE
CSJ0397-01-045
Proj IDSTP 2021(130)
Work TypeSUPER-2 HIGHWAY
 
17.99015464360.4117496646.7299.9
Work Order12-11-20
Work Began02-15-21
Work Completed
Time Computed01-11-21
Contract Working Days266
Addl Days Granted31
Working Days Charged271
Percent Time Used91
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-045
BARRICADES UNLIMITED (1.50)
BIG CREEK SAND & GRAVEL, INC. (11.85)
DUSTIN ALLEN, INC. (4.69)
MARCOM"S MOWING SERVICE, LLC (0.70)
TEX OP CONSTRUCTION, LP (2.06)
W. S. CONSTRUCTION COMPANY (9.72)
WEST TEXAS ROCK RESOURCES, LLC (0.37)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.28)
TRP CONSTRUCTION GROUP, LLC (1.80)
Contract #11203004
Totals15464360.410.0017496646.7299.9

page 1 | page 2 | page 3 | page 4