Monthly State Let Construction Report For Amarillo District As Of Apr 12, 2024 Page 3 Of 4

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHUTCHINSON
HighwaySH 152
FromSS 246
ToCARSON CO LINE
CSJ0455-01-048
Proj IDF 2023(821)
Work TypeOVERLAY
 
6.7957851871.7897196.601.2
Work Order07-12-23
Work Began03-04-24
Work Completed
Time Computed08-11-23
Contract Working Days114
Addl Days Granted0
Working Days Charged3
Percent Time Used2
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0455-01-048
BAHENA CONSTRUCTION CO.,INC. (8.36)
BARRICADES UNLIMITED (0.28)
DK CONTRACTING, LLC (1.11)
DUSTIN ALLEN, INC. (5.22)
DUSTROL, INC. (0.57)
GIBSON & ASSOCIATES, INC. (3.59)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.26)
TRP CONSTRUCTION GROUP, LLC (1.64)
WITHERS CONSTRUCTION, LLC (0.52)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.86)
Contract #06233210
Totals7851871.7875053.2797196.601.2

CountyCARSON
HighwaySH 152
FromAT SPRING CREEK
To.
CSJ0455-02-027
Proj IDBR 2021(709)
Work TypeBRIDGE REPLACEMENT
 
0.8044283739.203563308.8389.5
CountyCARSON
HighwaySH 152
FromAT WHITE DEER CREEK
To.
CSJ0455-02-028
Proj IDBR 2021(709)
Work TypeBRIDGE REPLACEMENT
 
0.7833941530.602914138.4573.9
Work Order08-25-21
Work Began11-19-21
Work Completed
Time Computed09-24-21
Contract Working Days335
Addl Days Granted0
Working Days Charged526
Percent Time Used157
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0455-02-027
ALAMO BROTHERS CONCRETE INC (2.88)
BARRICADES UNLIMITED (1.20)
HJC FARMS, INC. (2.76)
PRIMATE CONSTRUCTION, LP (0.22)
WEST TEXAS ROCK RESOURCES, LLC (0.07)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.61)
G & L REBAR (0.23)
DUSTROL, INC. (0.76)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.10)
TORO BRAVO CONSTRUCTION, LLC (1.34)
GRIT LOGISTICS, L.L.C. (0.73)
TRP CONSTRUCTION GROUP, LLC (1.20)
PINNACLE GRINDING AND GROOVING LLC (0.22)
Contract #07213010
Totals8225269.80262154.276477447.2882.0

CountyCARSON
HighwaySH 152
FromHUTCHINSON CO LINE
ToGRAY CO LINE
CSJ0455-02-031
Proj IDF 2B23(295)
Work TypeSUPER-2 HIGHWAY
 
13.01314702486.14472757.273.2
CountyCARSON
HighwaySH 152
FromHUTCHINSON COUNTY LINE
ToGRAY COUNTY LINE
CSJ0455-02-032
Proj IDSTP 2B23(296)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1772018.22545099.3230.7
Work Order12-05-23
Work Began02-15-24
Work Completed
Time Computed01-04-24
Contract Working Days202
Addl Days Granted0
Working Days Charged27
Percent Time Used13
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0455-02-031
BAHENA CONSTRUCTION CO.,INC. (6.95)
DUSTIN ALLEN, INC. (0.52)
INDUSTRIAL FABRICS, INC. (8.94)
MURRAY CONSTRUCTION (0.72)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.18)
TEX OP CONSTRUCTION, LP (1.23)
TRP CONSTRUCTION GROUP, LLC (2.96)
WITHERS CONSTRUCTION, LLC (0.79)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.27)
FC TRAFFIC CONTROL, INC. (0.15)
Contract #11233203
Totals16474504.36448185.581017856.596.1

CountyHUTCHINSON
HighwaySH 152
FromMOORE COUNTY LINE
ToSH 136 IN STINNETT
CSJ0557-02-019
Proj IDF 2023(128)
Work TypeOVERLAY
 
10.7467081620.087388862.4899.9
Work Order11-16-22
Work Began03-07-23
Work Completed
Time Computed12-16-22
Contract Working Days91
Addl Days Granted45
Working Days Charged135
Percent Time Used99
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0557-02-019
TRP CONSTRUCTION GROUP, LLC (1.31)
W. S. CONSTRUCTION COMPANY (15.16)
FC TRAFFIC CONTROL, INC. (0.20)
H & F TRUCKING (0.14)
WITHERS CONSTRUCTION, LLC (0.51)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.13)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.31)
TEXOP CONSTRUCTION (0.55)
WEST INFRASTRUCTURE CONSTRUCTION, LLC (1.49)
BARRICADES UNLIMITED (1.31)
DUSTIN ALLEN, INC. (5.32)
Contract #10223009
Totals7081620.0855664.197388862.4899.9

CountyDONLEY
HighwayFM 291
From@ WHITEFISH CREEK
To.
CSJ0795-05-010
Proj IDBR 2023(281)
Work TypeBRIDGE REPLACEMENT
 
3892082.001963985.8550.4
Work Order01-12-23
Work Began05-30-23
Work Completed
Time Computed02-11-23
Contract Working Days210
Addl Days Granted0
Working Days Charged177
Percent Time Used84
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0795-05-010
FC TRAFFIC CONTROL, INC. (0.47)
A-CORE CONCRETE CUTTING, INC. (0.18)
LANCO TURF & SEEDING, INC. (0.37)
TRP CONSTRUCTION GROUP, LLC (1.04)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.00)
G & L REBAR (0.30)
Contract #12223015
Totals3892082.00190697.501963985.8550.4

CountyDEAF SMITH
HighwayFM 809
FromAT FM 1062
To.
CSJ0801-02-022
Proj IDSTP 2023(691)HES
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.200404030.05419169.2499.9
CountyPOTTER
HighwayVA
FromIH 40 WEST
To.
CSJ0904-00-218
Proj IDSTP 2023(965)VRU
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1957418.44492524.4225.1
Work Order06-14-23
Work Began02-01-24
Work Completed
Time Computed10-12-23
Contract Working Days100
Addl Days Granted0
Working Days Charged35
Percent Time Used35
Contractor(s)
WG ENGINEERING & CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0801-02-022
GOMEZ PROPERTY SOLUTIONS LLC (6.92)
FC TRAFFIC CONTROL, INC. (0.74)
Contract #05233032
Totals2361448.49561148.66911693.6638.6

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-181
Proj IDF 2023(516)
Work TypeTRAFFIC CONTROL DEVICES
 
1.0001771464.251771284.5599.9
Work Order04-19-23
Work Began08-28-23
Work Completed
Time Computed08-17-23
Contract Working Days194
Addl Days Granted0
Working Days Charged122
Percent Time Used62
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-181
HJC FARMS, INC. (13.73)
BARRICADES UNLIMITED (1.25)
Contract #03233018
Totals1771464.2518112.001771284.5599.9

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-188
Proj IDSTP 2020(551)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.0001274691.701375724.5899.9
Work Order07-07-20
Work Began11-16-20
Work Completed
Time Computed11-04-20
Contract Working Days214
Addl Days Granted0
Working Days Charged214
Percent Time Used100
Contractor(s)
SIEMENS MOBILITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-188
FC TRAFFIC CONTROL, INC. (0.00)
TX DOWN UNDER CONSTRUCTION, LLC (0.00)
TALON/LPE, LTD. (0.00)
CANNON ASPHALT GROUP LLC (1.12)
D. E. RICE CONSTRUCTION COMPANY, INC. (0.00)
LINEAR TRAFFIC MARKINGS LLC (0.00)
Contract #02203224
Totals1274691.700.001375724.5899.9

CountyPOTTER
HighwayVA
FromDISTRICT WIDE
To.
CSJ0904-00-199
Proj IDF 2022(426)
Work TypeBRIDGE MAINTENANCE
 
843650.00952614.4599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-22
Work Began08-15-22
Work Completed
Time Computed00-00-00
Contract Working Days129
Addl Days Granted0
Working Days Charged185
Percent Time Used143
Contractor(s)
BLACKSTONE CONCRETE VENTURES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-199
FC TRAFFIC CONTROL, INC. (9.76)
ONE WAY CONCRETE (34.15)
Contract #04223221
Totals843650.000.00952614.4599.9

CountyPOTTER
HighwayVA
FromDISTRICT WIDE
To.
CSJ0904-00-207
Proj IDF 2024(137)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
3292241.7778088.502.3
Work Order11-30-23
Work Began00-00-00
Work Completed
Time Computed03-19-24
Contract Working Days93
Addl Days Granted0
Working Days Charged9
Percent Time Used9
Contractor(s)
CENTERLINE TECHNOLOGIES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-207
RED SIXTEEN CONSTRUCTION, INC (9.20)
SURFACE PREPARATION TECHNOLOGIES, LLC (41.09)
Contract #10233213
Totals3292241.7778088.5078088.502.3

CountyPOTTER
HighwayVA
FromVARIOUS
To.
CSJ0904-00-213
Proj IDSTP 2023(946)HESG
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
576034.65565530.0398.1
Work Order09-06-23
Work Began01-22-24
Work Completed
Time Computed12-05-23
Contract Working Days43
Addl Days Granted0
Working Days Charged25
Percent Time Used58
Contractor(s)
APOLLO CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-213
BARRICADES UNLIMITED (0.00)
Contract #06233453
Totals576034.6510550.58565530.0398.1

CountyPOTTER
HighwayUS 60
FromDISTRICTWIDE
To.
CSJ0904-00-232
Proj IDBR 2024(520)
Work TypeBRIDGE MAINTENANCE
 
1635105.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-06-24
Work Began00-00-00
Work Completed
Time Computed04-15-24
Contract Working Days67
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DCC CONSTRUCTION AND SERVICES, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-232
FC TRAFFIC CONTROL, INC. (5.56)
Contract #01243233
Totals1635105.000.000.000.0

CountyDEAF SMITH
HighwayFM 1259
FromTIERRA BLANCA CREEK
To.
CSJ1243-02-031
Proj IDBR 2023(820)
Work TypeBRIDGE REPLACEMENT
 
0.0495827413.20666909.8411.4
Work Order07-19-23
Work Began02-02-24
Work Completed
Time Computed08-19-23
Contract Working Days145
Addl Days Granted0
Working Days Charged40
Percent Time Used27
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1243-02-031
ALAMO BROTHERS CONCRETE INC (4.93)
FC TRAFFIC CONTROL, INC. (0.15)
HJC FARMS, INC. (0.34)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.90)
PRIMATE CONSTRUCTION, LP (0.19)
TRP CONSTRUCTION GROUP, LLC (0.30)
TORO BRAVO CONSTRUCTION, LLC (0.37)
Contract #06233008
Totals5827413.20557209.84666909.8411.4

CountyOLDHAM
HighwayRM 1061
FromUS 385
ToPOTTER COUNTY LINE
CSJ1245-01-019
Proj IDF 2022(375)
Work TypeSUPER-2 HIGHWAY
 
12.89318084714.1718120243.9699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-11-22
Work Began07-06-22
Work Completed
Time Computed00-00-00
Contract Working Days332
Addl Days Granted0
Working Days Charged307
Percent Time Used92
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 1245-01-019
ALAMO BROTHERS CONCRETE INC (5.10)
DK CONTRACTING, LLC (1.26)
DUSTIN ALLEN, INC. (1.97)
FC TRAFFIC CONTROL, INC. (0.14)
J & M CONTRACTING, COMPANY (9.41)
J. H. ODEN CONTRACTING COMPANY (0.32)
TOTAL HIGHWAY MAINTENANCE, LLC (1.41)
AMARILLO ARBORLOGICAL, INC. (0.67)
WILLIS ELECTRIC CO., LP (0.00)
FIBERTEX, LLC (0.00)
DUSTROL, INC. (0.92)
BARRICADES UNLIMITED (0.44)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.09)
Contract #02223023
Totals18084714.17759127.6518120243.9699.9

CountyPOTTER
HighwayRM 1061
FromRM 2381
ToN COULTER STREET
CSJ1245-02-049
Proj IDF 2022(374)
Work TypeREHABILITATION OF EXISTING ROAD
 
7.16812755021.4113063381.1899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-11-22
Work Began06-06-22
Work Completed
Time Computed00-00-00
Contract Working Days288
Addl Days Granted10
Working Days Charged311
Percent Time Used104
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-049
ALAMO BROTHERS CONCRETE INC (0.68)
BARRICADES UNLIMITED (1.48)
DK CONTRACTING, LLC (1.31)
DUSTIN ALLEN, INC. (1.67)
J. H. ODEN CONTRACTING COMPANY (0.28)
W. S. CONSTRUCTION COMPANY (6.06)
AMARILLO ARBORLOGICAL, INC. (0.46)
DUSTROL, INC. (0.90)
TRP CONSTRUCTION GROUP, LLC (1.48)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.09)
Contract #02223226
Totals12755021.41150271.2713063381.1899.9

CountyPOTTER
HighwayRM 1061
From10.5 MILES NORTH OF RM 2381
ToRM 2381
CSJ1245-02-050
Proj IDF 2023(053)
Work TypeOVERLAY
 
10.6947909237.499051921.9999.9
Work Order10-06-22
Work Began04-17-23
Work Completed
Time Computed11-05-22
Contract Working Days79
Addl Days Granted10
Working Days Charged108
Percent Time Used121
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-050
BAHENA CONSTRUCTION CO.,INC. (1.85)
BARRICADES UNLIMITED (0.00)
DK CONTRACTING, LLC (0.63)
DUSTIN ALLEN, INC. (2.94)
DUSTROL, INC. (0.29)
FC TRAFFIC CONTROL, INC. (0.20)
INDUSTRIAL FABRICS, INC. (18.14)
PINNACLE GRINDING AND GROOVING LLC (0.47)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.13)
TRP CONSTRUCTION GROUP, LLC (1.45)
PROFESSIONAL TRAFFIC CONTROL LLC (0.47)
APOLLO CONSTRUCTORS, INC. (0.75)
Contract #09223231
Totals7909237.4965215.159051921.9999.9

CountyLIPSCOMB
HighwaySH 23
From11 MI NORTH OF US 83
ToUS 83
CSJ1337-02-012
Proj IDF 2022(057)
Work TypeREHABILITATION OF EXISTING ROAD
 
11.0507414243.897612655.7499.9
Work Order11-17-21
Work Began07-28-22
Work Completed
Time Computed12-17-21
Contract Working Days257
Addl Days Granted8
Working Days Charged265
Percent Time Used100
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1337-02-012
BARRICADES UNLIMITED (3.15)
HJC FARMS, INC. (3.56)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.29)
H & F TRUCKING (1.70)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (3.03)
Contract #10213006
Totals7414243.89582624.007612655.7499.9

CountyLIPSCOMB
HighwayFM 1454
FromWOLF CREEK BRIDGE .
To.
CSJ1339-02-028
Proj IDBR 2023(457)
Work TypeBRIDGE REPLACEMENT
 
0.2288532873.454713018.0755.5
CountyLIPSCOMB
HighwayFM 1920
FromLITTLE SAND CREEK BRIDGE
To.
CSJ1819-01-016
Proj IDBR 2023(457)
Work TypeBRIDGE REPLACEMENT
 
0.0841892138.901700115.4089.8
Work Order03-16-23
Work Began07-05-23
Work Completed
Time Computed04-15-23
Contract Working Days315
Addl Days Granted0
Working Days Charged169
Percent Time Used53
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1339-02-028
FC TRAFFIC CONTROL, INC. (0.27)
LINEAR TRAFFIC MARKINGS LLC (0.39)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (7.07)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.95)
S&S BRIDGE PAINTING (0.31)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.40)
TORO BRAVO CONSTRUCTION, LLC (0.32)
L A FULLER & SONS CONSTRUCTION, LTD. (12.41)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.17)
Contract #02233012
Totals10425012.35477969.046413133.4761.7

CountyMOORE
HighwayFM 281
FromHARTLEY COUNTY LINE
ToUS 287
CSJ1727-02-024
Proj IDC 1727-2-24
Work TypeREHABILITATION OF EXISTING ROAD
 
9.38741097397.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days299
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1727-02-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243203
Totals41097397.100.000.000.0

CountyLIPSCOMB
HighwayFM 1920
FromRM 3260
ToHEMPHILL COUNTY LINE
CSJ1819-01-015
Proj IDSSW 1819-1-15
Work TypeSAFETY IMPROVEMENT PROJECTS
 
10.07616356130.4116238846.4799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-09-20
Work Began03-15-21
Work Completed
Time Computed00-00-00
Contract Working Days441
Addl Days Granted10
Working Days Charged604
Percent Time Used133
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1819-01-015
BARRICADES UNLIMITED (5.90)
GREGORY PILE DRIVING, INC. (0.31)
PRIMATE CONSTRUCTION, LP (0.10)
SCOTT DERR PAINTING CO, LLC (0.11)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.78)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (1.26)
Contract #04203203
Totals16356130.410.0016238846.4799.9

page 1 | page 2 | page 3 | page 4