Monthly Local Let Maintenance Report For Amarillo District As Of Nov 9, 2016 Page 1 Of 3

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6191-59-001
Proj ID RMC - 619159001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 276000.00 0.00 424600.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-10
Work Began 04-05-10
Work Completed  
Time Computed 04-05-10
Contract Working Days 730
Addl Days Granted 790
Working Days Charged 1,487
Percent Time Used 97
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6191-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02100401
Totals 276000.00 0.00 424600.00 99.9

CountyMOORE
Highway US0087
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6191-88-001
Proj ID RMC - 619188001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 289367.38 0.00 558483.97 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-04-10
Work Began 10-04-10
Work Completed 07-20-14
Time Computed 10-04-10
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 114
Percent Time Used 78
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6191-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05100406
Totals 289367.38 0.00 558483.97 100.0

CountyGRAY
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6191-93-001
Proj ID RMC - 619193001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 335852.72 0.00 663814.24 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-05-10
Work Began 10-11-10
Work Completed  
Time Computed 10-11-10
Contract Working Days 207
Addl Days Granted 207
Working Days Charged 235
Percent Time Used 56
Contractor(s)
3JB CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6191-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05100409
Totals 335852.72 0.00 663814.24 99.9

CountyPOTTER
Highway US0087
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6219-13-001
Proj ID RMC - 621913001
Work Type CLEANING & SWEEPING HIGHWAYS (4 COUNTIES)
 
0.001 278306.20 0.00 534046.21 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-27-12
Work Began 03-05-12
Work Completed  
Time Computed 03-05-12
Contract Working Days 730
Addl Days Granted 730
Working Days Charged 1,459
Percent Time Used 99
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6219-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12110402
Totals 278306.20 0.00 534046.21 99.9

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6224-70-001
Proj ID RMC - 622470001
Work Type ON CALL STRIPING
 
0.001 292000.68 0.00 291224.78 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-07-11
Work Began 06-14-11
Work Completed 08-31-11
Time Computed 06-15-11
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 33
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6224-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05110404
Totals 292000.68 0.00 291224.78 100.0

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6245-10-001
Proj ID RMC - 624510001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 175332.44 0.00 118771.18 67.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-03-12
Work Began 11-12-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 72
Addl Days Granted 10
Working Days Charged 76
Percent Time Used 92
Contractor(s)
GORMAN OUTDOOR, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6245-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07120401
Totals 175332.44 0.00 118771.18 67.7

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6245-11-001
Proj ID RMC - 624511001
Work Type MOWING HIGHWAY RIGHT OF WAY
 
0.001 245032.00 0.00 234833.40 96.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-16-12
Work Began 10-18-12
Work Completed  
Time Computed 10-18-12
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 33
Contractor(s)
BERT WHITAKER
SUBCONTRACTOR(S) FOR CCSJ: 6245-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07120402
Totals 245032.00 0.00 234833.40 96.4

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6252-37-001
Proj ID RMC - 625237001
Work Type TRAFFIC CONTROL
 
0.001 192016.50 0.00 75269.95 39.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-14-13
Work Began 01-21-13
Work Completed  
Time Computed 01-21-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 131
Percent Time Used 35
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6252-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12120401
Totals 192016.50 0.00 75269.95 39.1

CountyCARSON
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6256-24-001
Proj ID RMC - 625624001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 167010.00 0.00 125245.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-27-13
Work Began 08-27-13
Work Completed 10-28-15
Time Computed 08-27-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 726
Percent Time Used 99
Contractor(s)
INSURORS INDEMNITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6256-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03130403
Totals 167010.00 0.00 125245.00 100.0

CountyGRAY
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6257-98-001
Proj ID RMC - 625798001
Work Type ON CALL GUARDRAIL REPAIR
 
0.001 149550.00 0.00 133798.50 89.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-13
Work Began 10-28-13
Work Completed  
Time Computed 10-28-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 673
Percent Time Used 92
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6257-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130401
Totals 149550.00 0.00 133798.50 89.4

CountyRANDALL
Highway IH0027
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6259-28-001
Proj ID BPM - 625928001
Work Type MISC BRIDGE REPAIRS
 
0.001 279192.00 0.00 267683.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-08-14
Work Began 07-17-14
Work Completed 08-26-14
Time Computed 07-21-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 85
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140401
Totals 279192.00 0.00 267683.00 100.0

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6260-01-001
Proj ID RMC - 626001001
Work Type TRAFFIC CONTROL
 
0.001 196575.00 0.00 396755.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-17-13
Work Began 07-17-13
Work Completed  
Time Computed 07-17-13
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 722
Percent Time Used 98
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6260-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06130403
Totals 196575.00 0.00 396755.00 99.9

CountyDEAF SMITH
Highway FM1412
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6266-54-001
Proj ID RMC - 626654001
Work Type EXTENDING CULVERTS
 
0.001 164450.00 0.00 159010.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-14
Work Began 10-27-14
Work Completed 02-19-15
Time Computed 07-07-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 78
Contractor(s)
M & S CONCRETE CO.
SUBCONTRACTOR(S) FOR CCSJ: 6266-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140402
Totals 164450.00 0.00 159010.00 100.0

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6269-86-001
Proj ID RMC - 626986001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 275999.68 14777.76 309401.48 99.9
Work Order 04-17-14
Work Began 05-05-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 730
Addl Days Granted 730
Working Days Charged 914
Percent Time Used 62
Contractor(s)
ALL HANDS & DUKE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03140401
Totals 275999.68 14777.76 309401.48 99.9

CountyPOTTER
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6271-28-001
Proj ID RMC - 627128001
Work Type CLEANING AND SWEEPING HIGHWAYS
 
0.001 263250.56 0.00 496645.12 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-15-14
Work Began 06-04-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 729
Percent Time Used 99
Contractor(s)
PANHANDLE SWEEPING & MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6271-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140404
Totals 263250.56 0.00 496645.12 99.9

CountyDALLAM
Highway US0087
From SEE PLANS
To SEE PLANS
CSJ 6271-81-001
Proj ID SUP - 627181001
Work Type STATE USE JANITORIAL SERVICE
 
0.001 8487.47 0.00 2720.85 32.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-07-14
Work Began 00-00-00
Work Completed  
Time Computed 04-15-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 108
Percent Time Used 29
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6271-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04140423
Totals 8487.47 0.00 2720.85 32.0

CountyRANDALL
Highway FM1541
From JANITORIAL AMARILLO AE/E-WAY
To JANITORIAL AMARILLO AE/E-WAY
CSJ 6273-58-001
Proj ID SUP - 627358001
Work Type STATE USE JANITORIAL MAINTENANCE
 
0.001 14904.63 0.00 12097.97 81.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 06-04-14
Work Completed  
Time Computed 06-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05140420
Totals 14904.63 0.00 12097.97 81.1

CountyCARSON
Highway IH0040
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6275-45-001
Proj ID RMC - 627545001
Work Type PICNIC AREA MAINTENANCE
 
0.001 48000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MARION POOL
SUBCONTRACTOR(S) FOR CCSJ: 6275-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140401
Totals 48000.00 0.00 0.00 0.0

CountyHUTCHINSON
Highway SH0207
From SEE PLAN SHEETS
To SEE PLAN SHEETS
CSJ 6276-78-001
Proj ID SUP - 627678001
Work Type BORGER JANITORIAL
 
0.001 6491.73 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08140421
Totals 6491.73 0.00 0.00 0.0

CountyHARTLEY
Highway FM0767
From PUNTA DE AGUA BRIDGE
To PUNTA DE AGUA BRIDGE
CSJ 6282-46-001
Proj ID EMC - 628246001
Work Type EMERGENCY BRIDGE REPAIRS
 
0.001 70300.00 0.00 70300.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 11-24-14
Contract Working Days 5
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 60
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11140430
Totals 70300.00 0.00 70300.00 99.9

page 1 | page 2 | page 3