Monthly State Let Construction Report For Atlanta District As Of Jan 11, 2017 Page 1 Of 2

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTITUS ETC
HighwayUS 67 ETC
From0.1 MI W OF US 271
To0.1 MI E OF FM 1734 W
CSJ0010-06-040
Proj IDSTP 2016(135)
Work TypeSEAL COAT
 
160.1456550235.522809737.3242.8
Work Order01-22-16
Work Began05-22-16
Work Completed
Time Computed05-22-16
Contract Working Days50
Addl Days Granted0
Working Days Charged29
Percent Time Used58
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-06-040
STRIPE-A-ZONE, INC. (7.47)
BRYDL CONTRACTING, INC. (0.87)
Contract #09153234
Totals6550235.520.002809737.3242.8

CountyTITUS ETC
HighwayUS 67 ETC
FromUS 271
ToFRANKLIN C/L
CSJ0010-06-041
Proj IDSTP 2017(053)HESG
Work TypePROFILE EDGELINE MARKINGS
 
120.8311861333.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-14-16
Work Began01-09-17
Work Completed
Time Computed00-00-00
Contract Working Days129
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-06-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163225
Totals1861333.540.000.000.0

CountyBOWIE
HighwayUS 67
FromFM 2149
ToSH 8 (NORTH)
CSJ0010-12-067
Proj IDSTP 2016(076)HES
Work TypeTEXTURIZE SHOULDERS & CL TEXTURING
 
34.6151829345.43744153.5340.6
Work Order10-21-15
Work Began03-07-16
Work Completed
Time Computed11-23-15
Contract Working Days195
Addl Days Granted7
Working Days Charged157
Percent Time Used77
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0010-12-067
STRIPING SYSTEMS, INC. (0.00)
BRYDL CONTRACTING, INC. (1.22)
Contract #09153009
Totals1829345.438278.53744153.5340.6

CountyBOWIE
HighwayUS 67
FromAT IH 369 INTERSECTION
To.
CSJ0010-13-087
Proj IDSTP 2017(333)HES
Work TypeIMPROVE TRAFFIC SIGNAL
 
0.009566437.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days203
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0010-13-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163015
Totals566437.350.000.000.0

CountyBOWIE ETC
HighwayFM 991 ETC
FromUS 67 W
ToUS 67 E
CSJ0010-19-011
Proj IDSTP 2017(175)
Work TypeSEAL COAT
 
104.0613968760.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-19-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10163024
Totals3968760.100.000.000.0

CountyBOWIE
HighwaySL 14
FromUS 71
To24TH STREET
CSJ0046-08-016
Proj IDSTP 2017(233)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
4.801381220.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-07-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0046-08-016
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163019
Totals381220.000.000.000.0

CountyMARION
HighwayUS 59
FromHARRISON C/L
To0.1 MI. S. OF SH 49
CSJ0062-06-053
Proj IDNH 1602(100)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
3.0482050585.722231225.9499.9
Work Order06-20-16
Work Began08-24-16
Work Completed
Time Computed07-20-16
Contract Working Days50
Addl Days Granted0
Working Days Charged52
Percent Time Used104
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-06-053
PANOLA SIGN & BARRICADE, INC. (0.34)
TEX OP CONSTRUCTION, LP (6.43)
MORRIS COUNTY CONTRACTORS, L.L.C. (4.05)
CHEROKEE SERVICES (1.38)
COWBELL TRAFFIC SERVICES, INC. (0.24)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.04)
STRIPING TECHNOLOGY, L.P. (2.34)
Contract #05163217
Totals2050585.7210160.002231225.9499.9

CountyHARRISON
HighwayUS 59
FromAT INTERSECTION OF SL 390
To.
CSJ0062-07-086
Proj IDNH 2013(617)
Work TypePLANING,ACP,CPCD & PAV MRKS
 
0.5315747430.104799838.1283.5
Work Order10-06-15
Work Began11-11-15
Work Completed
Time Computed11-05-15
Contract Working Days195
Addl Days Granted0
Working Days Charged188
Percent Time Used96
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-086
PANOLA SIGN & BARRICADE, INC. (1.10)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.89)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.42)
STRIPING TECHNOLOGY, L.P. (7.64)
ACU CONSTRUCTION LLC (0.57)
CARTHAGE DRILLING, INC. (0.21)
JEFF WILSON BORING (0.17)
Contract #07153228
Totals5747430.10322910.934799838.1283.5

CountyHARRISON
HighwayUS 59
From3.3 MI. S. OF FM 1997
To0.1 MI. N. OF SH 43 (N)
CSJ0062-07-087
Proj IDNH 2016(967)
Work TypePLANING, ACP & PAV MARKINGS
 
4.2343413079.111501186.6643.9
Work Order05-16-16
Work Began07-24-16
Work Completed
Time Computed06-15-16
Contract Working Days55
Addl Days Granted0
Working Days Charged40
Percent Time Used72
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-087
PANOLA SIGN & BARRICADE, INC. (0.21)
STRIPE-A-ZONE, INC. (2.72)
DUSTIN ALLEN, INC. (1.13)
COWBELL TRAFFIC SERVICES, INC. (0.36)
B & E CONSTRUCTION INC. (0.96)
Contract #04163017
Totals3413079.110.001501186.6643.9

CountyHARRISON
HighwayUS 59
FromAT JOHNSON ST INTERSECTION
To.
CSJ0063-01-091
Proj IDSTP 2017(235)HESG
Work TypeINSTALL TRAFFIC SIGNAL
 
0.406256403.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-12-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days140
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TRAFFIC CONTROL SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-01-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163023
Totals256403.000.000.000.0

CountyHARRISON ETC
HighwayFM 1186 ETC
FromUS 59
ToPANOLA C/L
CSJ0063-01-092
Proj IDSTP 2017(336)HESG
Work TypePROFILE EDGELINE MARKINGS
 
84.957814705.350.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-01-092
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163008
Totals814705.350.000.000.0

CountyPANOLA
HighwayUS 59
FromAT US 79 INTERSECTION
To.
CSJ0063-03-060
Proj IDSTP 2017(505)HES
Work TypeIMPROVE TRAFFIC SIGNAL & SAFE LIGHT
 
0.009524435.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days190
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0063-03-060
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173245
Totals524435.700.000.000.0

CountyHARRISON
HighwayUS 59
FromFM 1186
ToPANOLA C/L
CSJ0063-09-015
Proj IDNH 1602(147)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
4.1934850066.36884200.9018.2
Work Order07-29-16
Work Began10-03-16
Work Completed
Time Computed08-29-16
Contract Working Days160
Addl Days Granted0
Working Days Charged56
Percent Time Used35
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-09-015
PANOLA SIGN & BARRICADE, INC. (0.32)
EAST TEXAS BRIDGE, INC. (18.21)
CHEROKEE SERVICES (0.95)
DUSTIN ALLEN, INC. (2.19)
ISAACS CONSTRUCTION SERVICES, LLC. (0.11)
STRIPING TECHNOLOGY, L.P. (1.96)
COWBELL TRAFFIC SERVICES, INC. (0.29)
Contract #06163216
Totals4850066.36192510.00884200.9018.2

CountyPANOLA
HighwaySH 149
FromUS 79
To0.8 MI S. OF SH 315
CSJ0063-11-042
Proj IDSTP 2016(625)
Work TypeGR, STR, BS, SURF
 
1.98020892969.23949402.224.5
Work Order08-05-16
Work Began09-08-16
Work Completed
Time Computed09-05-16
Contract Working Days540
Addl Days Granted0
Working Days Charged56
Percent Time Used10
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-042
PANOLA SIGN & BARRICADE, INC. (0.22)
WEST TEXAS RUMBLE STRIP (0.02)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (0.51)
SCOTT DERR PAINTING CO, LLC (0.00)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.43)
OSCAR ORDUNO, INC. (0.57)
STRIPING TECHNOLOGY, L.P. (3.67)
CARTHAGE DRILLING, INC. (0.05)
DIRECTIONAL DRILLING (0.03)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.74)
ISAACS CONSTRUCTION SERVICES, LLC. (0.22)
TJT CONSTRUCTION (0.52)
RAYFORD"S TRUCK & TRACTOR (0.28)
Contract #04163202
Totals20892969.2399644.48949402.224.5

CountyBOWIE
HighwayUS 259
FromAT RED RIVER
To.
CSJ0085-04-033
Proj IDBR 1402(085)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.4167588340.842923094.6038.5
CountyBOWIE
HighwayUS 259
FromON TEXAS SIDE OF RED RIVER BRIDGE
To.
CSJ0085-04-037
Proj IDBR 1402(202)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3982462742.583081911.3599.9
CountyBOWIE
HighwayUS 259
FromON OKLAHOMA SIDE OF RED RIVER BRIDG
To.
CSJ0085-04-038
Proj IDCC 85-4-38
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.3981789824.15964282.1253.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-09-14
Work Began12-08-14
Work Completed
Time Computed12-08-14
Contract Working Days479
Addl Days Granted0
Working Days Charged164
Percent Time Used34
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0085-04-033
TOTAL HIGHWAY MAINTENANCE, LLC (0.83)
MOORE CONSTRUCTION, INC. (0.26)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (5.86)
DUSTROL, INC. (1.40)
WEST TEXAS RUMBLE STRIP (0.03)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.11)
MCL CONTRACTING, LLC (4.57)
PRIMATE CONSTRUCTION, INC. (0.12)
FARR FOUNDATION, INC. (0.59)
DUSTIN ALLEN, INC. (0.29)
ATS DRILLING, INC. (9.03)
H. V. CAVER, INC. (0.22)
Contract #08143008
Totals11840907.570.006969288.0758.8

CountyTITUS
HighwayUS 271
FromBU 271
ToIH 30
CSJ0221-05-088
Proj IDSTP 1602(101)
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
5.1662953900.853388848.8099.9
CountyTITUS
HighwayCS
FromON 2ND STREET
ToBETWEEN BU 271N & BU 271S
CSJ0919-30-060
Proj IDCC 919-30-60
Work TypePLANE ACP, ACP SURF, & PAV MARK
 
0.05041156.0234231.9183.1
Work Order06-06-16
Work Began07-14-16
Work Completed
Time Computed07-06-16
Contract Working Days55
Addl Days Granted0
Working Days Charged75
Percent Time Used136
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0221-05-088
PANOLA SIGN & BARRICADE, INC. (0.46)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.08)
STRIPING TECHNOLOGY, L.P. (4.72)
TEX OP CONSTRUCTION, LP (11.63)
STRIPING SYSTEMS, INC. (0.04)
JM YANEZ CONSTRUCTION (0.83)
Contract #05163027
Totals2995056.8729323.963423080.7199.9

CountyCASS
HighwaySH 77
From0.2 MILE WEST OF FM 251
To0.3 MILE EAST OF FM 1841
CSJ0278-01-044
Proj IDSTP 2015(702)
Work TypeGR, STR, BASE, C&G, ACP, ILL & PVT
 
1.0988162284.826974934.4485.4
Work Order05-21-15
Work Began10-05-15
Work Completed
Time Computed09-19-15
Contract Working Days370
Addl Days Granted0
Working Days Charged208
Percent Time Used56
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0278-01-044
BAHENA CONSTRUCTION CO.,INC. (9.92)
CARRUTH NURSERY IRRIGATION & LANDSCAPE, INC. (0.79)
PANOLA SIGN & BARRICADE, INC. (0.26)
RK HALL, LLC (49.37)
SAMMY SMALLWOOD COMPANY (0.90)
STRIPING TECHNOLOGY, L.P. (0.85)
TEXAS ENVIRONMENTAL MANAGEMENT SA, INC. (3.78)
TEXAS TRAFFIC CONTROL SYSTEMS, INC. (4.45)
TEXOP CONSTRUCTION (0.62)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.97)
Contract #03153207
Totals8162284.82130235.836974934.4485.4

CountyUPSHUR ETC
HighwaySH 154 ETC
From0.1 MI E OF US 271
ToFM 726
CSJ0402-01-023
Proj IDSTP 2017(072)HESG
Work TypeTEXTURIZE SHOULDERS & CL TEXTURING
 
81.5341158627.940.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-21-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days76
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0402-01-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163023
Totals1158627.940.000.000.0

CountyHARRISON
HighwayIH 20
FromAT FM 450 UNDERPASS
To.
CSJ0495-08-086
Proj IDBR 2013(619)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0104874784.264619587.0396.9
Work Order07-30-15
Work Began09-01-15
Work Completed
Time Computed08-31-15
Contract Working Days225
Addl Days Granted0
Working Days Charged334
Percent Time Used148
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-086
PANOLA SIGN & BARRICADE, INC. (0.44)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.45)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.96)
STRIPING TECHNOLOGY, L.P. (3.24)
TEXOP CONSTRUCTION (1.50)
S & S BRIDGE PAINTING, INC. (0.06)
ODUM SERVICES, L.P. (3.08)
HOUSTON SAWING & DRILLING (0.10)
MCL CONTRACTING, LLC (0.17)
Contract #04153256
Totals4874784.26124077.664619587.0396.9

CountyHARRISON
HighwayIH 20
FromGREGG C/L
To0.5 MI. W. OF SH 43, EB LANES ONLY
CSJ0495-08-095
Proj IDNH 2016(371)
Work TypePLANE,CONC PVMT REP,ACP SF,PAV MRK
 
17.0097872292.128042285.6699.9
Work Order02-17-16
Work Began04-04-16
Work Completed
Time Computed03-18-16
Contract Working Days110
Addl Days Granted0
Working Days Charged88
Percent Time Used80
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-095
PANOLA SIGN & BARRICADE, INC. (0.36)
VANCE BROTHERS, INC. (3.85)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.33)
STRIPING TECHNOLOGY, L.P. (1.66)
B & E CONSTRUCTION INC. (6.23)
COWBELL TRAFFIC SERVICES, INC. (0.34)
DUSTIN ALLEN, INC. (2.47)
O. TREVINO CONSTRUCTION, LLC (9.82)
JOHNSON BROTHER"S TRUCKING (0.19)
W.O.E. CONSTRUCTION (0.44)
SPARTAN CONSTRUCTION, INC. (8.46)
Contract #12153217
Totals7872292.12432257.438042285.6699.9