Monthly State Let Construction Report For Atlanta District As Of Oct 14, 2014 Page 1 Of 3

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTITUS
Highway US 67 ETC
From MORRIS C/L
To FM 1402
CSJ 0010-07-051
Proj ID STP 2015(168)
Work Type SEAL COAT
 
184.807 7431528.54 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 55
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-07-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143204
Totals 7431528.54 0.00 0.00 0.0

CountyBOWIE
Highway FM 991
From AT AIKEN CREEK
To .
CSJ 0010-19-009
Proj ID BR 2014(143)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.273 1071821.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0010-19-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143231
Totals 1071821.22 0.00 0.00 0.0

CountyCASS
Highway SH 8 ETC
From 0.1 MI. S.OF BOWIE C/L
To SH 77
CSJ 0062-02-025
Proj ID STP 2014(401)HESG
Work Type TEXTURIZE SHOULDERS & CL TEXTURING
 
30.721 1422301.96 251154.76 1345530.06 94.6
Work Order 03-25-14
Work Began 04-21-14
Work Completed  
Time Computed 04-21-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 103
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-02-025
COWBELL TRAFFIC SERVICES, INC. (1.79%)
BRYDL CONTRACTING, INC.(1.52%)
Contract # 02143006
Totals 1422301.96 251154.76 1345530.06 94.6

CountyHARRISON
Highway US 59 ETC
From MARION C/L
To US 80
CSJ 0062-07-084
Proj ID STP 2015(144)HESG
Work Type INSTALL SAFETY LIGHTING
 
117.385 670082.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-084
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143206
Totals 670082.50 0.00 0.00 0.0

CountyHARRISON
Highway US 59
From MARION C/L
To US 80
CSJ 0062-07-085
Proj ID STP 2014(448)HESG
Work Type TEXTURIZE SHOULDERS & CL TEXTURING
 
27.965 1423390.23 288659.34 1377226.30 96.7
Work Order 03-25-14
Work Began 04-24-14
Work Completed  
Time Computed 04-24-14
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 83
Percent Time Used 100
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0062-07-085
COWBELL TRAFFIC SERVICES, INC. (0.45%)
BRYDL CONTRACTING, INC.(1.16%)
Contract # 02143015
Totals 1423390.23 288659.34 1377226.30 96.7

CountyHARRISON
Highway US 59
From AT INTERSECTION OF SH 43
To .
CSJ 0063-01-085
Proj ID STP 2015(152)HESG
Work Type IMPROVE TRAFFIC SIGNAL & LF TRN LAN
 
0.044 545314.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0063-01-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143026
Totals 545314.25 0.00 0.00 0.0

CountyPANOLA
Highway US 59 ETC
From FM 2792
To LP 436
CSJ 0063-03-059
Proj ID STP 2014(489)HESG
Work Type TEXTURIZE SHOULDERS & CL TEXTURING
 
44.394 2023926.54 0.00 972990.56 48.0
Work Order 05-01-14
Work Began 06-30-14
Work Completed  
Time Computed 06-30-14
Contract Working Days 132
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 32
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0063-03-059
BRYDL CONTRACTING, INC.(0.76%)
COWBELL TRAFFIC SERVICES, INC. (0.63%)
Contract # 03143022
Totals 2023926.54 0.00 972990.56 48.0

CountyPANOLA
Highway US 59
From US 79
To 0.4 MI. N. OF CR 420
CSJ 0063-04-056
Proj ID STP 2014(450)HESG
Work Type TEXTURIZE SHOULDERS & CL TEXTURING
 
31.432 1970000.61 155701.28 1295627.53 65.7
Work Order 05-15-14
Work Began 05-22-14
Work Completed  
Time Computed 05-22-14
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 58
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-04-056
BRYDL CONTRACTING, INC.(0.75%)
COWBELL TRAFFIC SERVICES, INC. (2.86%)
Contract # 02143209
Totals 1970000.61 155701.28 1295627.53 65.7

CountyPANOLA
Highway SH 149
From 0.6 MI W OF FM 10
To 0.2 MI E OF FM 10
CSJ 0063-11-055
Proj ID C 63-11-55
Work Type GR, BASE, SURFACING & PVMT MARKERS
 
0.787 1796137.06 223980.66 1135721.78 63.2
Work Order 08-20-13
Work Began 03-11-14
Work Completed  
Time Computed 03-01-14
Contract Working Days 96
Addl Days Granted 0
Working Days Charged 56
Percent Time Used 58
Contractor(s)
L. S. EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-055
DUSTROL, INC.(0.82%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.92%)
MADDEN CONTRACTING COMPANY, INC. ( 21.93%)
ROBINSON CONSTRUCTION(5.03%)
STRIPING TECHNOLOGY, L.P.(5.87%)
Contract # 06133218
Totals 1796137.06 223980.66 1135721.78 63.2

CountyPANOLA
Highway SH 149
From 0.1 MI SOUTH OF SH 315
To US 59
CSJ 0063-11-056
Proj ID STP 2014(408)
Work Type CMT TRT EXIST MTL, OCST, ACP, & PM
 
2.211 2437500.78 147039.84 716083.17 29.3
Work Order 03-13-14
Work Began 06-20-14
Work Completed  
Time Computed 06-20-14
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 60
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0063-11-056
PANOLA SIGN & BARRICADE, INC.(0.27%)
DREWERY & WHEATON, LLC (0.13%)
DUSTROL, INC.(1.15%)
DUSTIN ALLEN, INC. (1.22%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.16%)
STRIPING TECHNOLOGY, L.P.(3.08%)
ACU CONSTRUCTION LLC (1.03%)
Contract # 02143022
Totals 2437500.78 147039.84 716083.17 29.3

CountyCAMP
Highway SH 11
From AT FM 21 INTERSECTION
To .
CSJ 0083-07-040
Proj ID C 83-7-40
Work Type GR, BASE, SURFACING & PVMT MARKERS
 
0.284 299998.42 4404.83 319841.30 99.9
Work Order 07-08-13
Work Began 04-23-14
Work Completed  
Time Computed 09-06-13
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 41
Percent Time Used 77
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0083-07-040
BAHENA CONSTRUCTION CO.,INC. (6.53%)
BANNER SIGN & BARRICADE, INC. (HOOKS)(0.76%)
MARTIN MARIETTA MATERIALS (POWDERLY) ( 17.50%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.09%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.57%)
Contract # 05133007
Totals 299998.42 4404.83 319841.30 99.9

CountyCAMP
Highway SH 11
From WOOD C/L
To FM 21
CSJ 0083-07-041
Proj ID STP 2014(409)HESG
Work Type TEXTURIZE SHOULDERS & CL TEXTURING
 
15.378 667721.66 0.10 625903.18 100.0
Work Order 03-25-14
Work Began 04-25-14
Work Completed 09-18-14
Time Computed 04-25-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 100
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0083-07-041
COWBELL TRAFFIC SERVICES, INC. (1.24%)
BRYDL CONTRACTING, INC.(0.89%)
Contract # 02143204
Totals 667721.66 0.10 625903.18 100.0

CountyMORRIS
Highway US 259
From US 67
To 0.4 MI S OF IH 30
CSJ 0085-01-044
Proj ID STP 2013(522)
Work Type ADD SHLDS, BASE, ACP & PVMT MRKS
 
7.486 7975983.33 375251.84 5290218.10 66.3
Work Order 07-23-13
Work Began 08-16-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 360
Addl Days Granted 18
Working Days Charged 282
Percent Time Used 74
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0085-01-044
SOUTHWEST ENVIRONMENT SERVICES LLC (0.60%)
ODUM SERVICES, L.P.(0.27%)
NE-TEX CONSTRUCTION, LTD.( 33.45%)
DUSTROL, INC.(1.85%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.78%)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (0.11%)
HIGHWAY 19 CONSTRUCTION, LLC (0.57%)
MARCOM"S MOWING SERVICE, LLC (0.48%)
BANNER SIGN & BARRICADE, INC. (HOOKS)(0.99%)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (0.64%)
TIME STRIPING, INC.(0.35%)
RK HALL, LLC ( 10.26%)
Contract # 04133020
Totals 7975983.33 375251.84 5290218.10 66.3

CountyBOWIE
Highway US 259
From AT RED RIVER
To .
CSJ 0085-04-033
Proj ID BR 1402(085)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.416 7588340.84 0.00 0.00 0.0
CountyBOWIE
Highway US 259
From ON TEXAS SIDE OF RED RIVER BRIDGE
To .
CSJ 0085-04-037
Proj ID BR 1402(202)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.398 2462742.58 0.00 0.00 0.0
CountyBOWIE
Highway US 259
From ON OKLAHOMA SIDE OF RED RIVER BRIDG
To .
CSJ 0085-04-038
Proj ID CC 85-4-38
Work Type REPLACE BRIDGE AND APPROACHES
 
0.398 1789824.15 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 479
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0085-04-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143008
Totals 11840907.57 0.00 0.00 0.0

CountyUPSHUR
Highway US 80
From AT BIG SANDY CREEK
To .
CSJ 0096-03-064
Proj ID BR 2013(766)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.705 2810007.30 178774.89 2477311.35 88.1
Work Order 08-08-13
Work Began 08-22-13
Work Completed  
Time Computed 08-22-13
Contract Working Days 164
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 87
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0096-03-064
DUSTIN ALLEN, INC. (0.99%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.97%)
MAC TRANSPORTATION, LTD, L.L.P.( 12.30%)
PANOLA SIGN & BARRICADE, INC.(0.37%)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.58%)
STRIPING TECHNOLOGY, L.P.(1.38%)
SOTO"S STEEL (0.14%)
TEX OP CONSTRUCTION, LP(2.04%)
Contract # 05133240
Totals 2810007.30 178774.89 2477311.35 88.1

CountyHARRISON
Highway US 80
From FM 450
To SH 154 (LP 390)
CSJ 0096-08-052
Proj ID STP 2014(494)HESG
Work Type TEXTURIZE SHOULDERS & CL TEXTURING
 
22.200 1310828.65 50613.70 1298561.88 99.0
Work Order 04-11-14
Work Began 06-10-14
Work Completed  
Time Computed 06-10-14
Contract Working Days 46
Addl Days Granted 0
Working Days Charged 42
Percent Time Used 91
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0096-08-052
BRYDL CONTRACTING, INC.(0.71%)
Contract # 03143017
Totals 1310828.65 50613.70 1298561.88 99.0

CountyHARRISON
Highway FM 2208
From SH 154
To FM 450
CSJ 0138-13-017
Proj ID STP 2013(775)
Work Type CEM TRT SUBGRD, FLEX BS, OCST, PVT MKS
 
1.179 329938.77 10990.40 321408.72 97.4
Work Order 08-21-13
Work Began 06-12-14
Work Completed  
Time Computed 12-22-14
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 35
Contractor(s)
H. V. CAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0138-13-017
SOUTHWEST ENVIRONMENT SERVICES LLC (3.57%)
BAHENA CONSTRUCTION CO.,INC. (4.47%)
TOTAL HIGHWAY MAINTENANCE, LLC (5.65%)
RICE ENVIRONMENTAL SERVICES(3.90%)
BANNER SIGN & BARRICADE, INC. (HOOKS)(0.53%)
Contract # 06133014
Totals 329938.77 10990.40 321408.72 97.4

CountyPANOLA
Highway SH 43
From 0.4 MI S. OF FM 959
To HARRISON C/L
CSJ 0207-04-035
Proj ID STP 2014(801)
Work Type ACP SURF & PAV MKS
 
3.839 1243150.66 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-27-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 0207-04-035
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143230
Totals 1243150.66 0.00 0.00 0.0

CountyCASS
Highway US 59
From AT INTERSECTION OF FM 3129
To .
CSJ 0218-03-076
Proj ID STP 1102(039)SB
Work Type GRADING, STRUCTURES, BASE & SURFACING
 
3.241 15425865.78 339834.68 13953022.53 90.4
CountyUPSHUR
Highway US 271
From AT INTERSECTION OF SH 155(S)
To .
CSJ 0248-05-055
Proj ID STP 1102(039)SB
Work Type GRADING, STRUCTURES, BASE & SURFACING
 
0.304 4690776.56 2000.00 4662920.69 99.5
CountyUPSHUR
Highway US 271
From AT INTERSECTION OF SH 155(S)
To .
CSJ 0248-05-058
Proj ID STP 1102(041)
Work Type INSTALL TREES, SHRUBS AND IRRIGATION
 
0.304 73847.00 0.00 75589.00 99.9
Work Order 08-11-11
Work Began 09-01-11
Work Completed  
Time Computed 09-01-11
Contract Working Days 770
Addl Days Granted 21
Working Days Charged 749
Percent Time Used 94
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0248-05-055
STRIPING TECHNOLOGY, L.P.(5.10%)
DUSTROL, INC.(0.07%)
HIGHWAY TECHNOLOGIES, INC. (0.68%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.63%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.34%)
ATS DRILLING, L.P. (0.48%)
CARTHAGE DRILLING, INC.(0.15%)
R & R TELCO ENTERPRISES, INC.(0.03%)
MAC TRANSPORTATION, LTD, L.L.P.(3.93%)
RICK HARGROVE TRUCKING (3.93%)
TEX OP CONSTRUCTION, LP(0.27%)
DUSTIN ALLEN, INC. (0.73%)
AQUA BORE(0.01%)
WEBBER BARRIER SERVICES, INC.(0.29%)
SCOTT DERR PAINTING CO, LLC(0.01%)
SOUTHEAST GRINDING & GROOVING, LLC (0.02%)
COKER TREE SERVICE (0.01%)
PENHALL COMPANY(0.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.03%)
Contract # 06113017
Totals 20190489.34 341834.68 18691532.22 92.6

CountyTITUS
Highway US 271
From FRANKLIN COUNTY LINE
To FM 1896
CSJ 0221-05-083
Proj ID NH 2013(620)
Work Type ACP SURFACE, OCST AND PAV MARKINGS
 
5.782 1958984.74 63.33 1993416.08 99.9
Work Order 02-12-14
Work Began 06-13-14
Work Completed  
Time Computed 04-14-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 128
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0221-05-083
TOTAL HIGHWAY MAINTENANCE, LLC (0.38%)
TEX OP CONSTRUCTION, LP(6.96%)
DUSTROL, INC.(0.43%)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.05%)
STRIPING TECHNOLOGY, L.P.(2.38%)
H. H. HOWARD & SONS, INC.(6.22%)
Contract # 01143024
Totals 1958984.74 63.33 1993416.08 99.9