Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HARRISON |
Highway | IH 20 |
From | GREGG COUNTY LINE |
To | 0.5 MI. W. OF SH 43 |
CSJ | 0495-08-130 |
Proj ID | F 2021(584) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 39.129 | 2346996.00 | | 2212643.69 | 99.9 |
Work Order | 07-22-21 |
Work Began | 08-24-21 |
Work Completed | |
Time Computed | 08-21-21 |
Contract Working Days | 95 |
Addl Days Granted | 38 |
Working Days Charged | 433 |
Percent Time Used | 325 |
Contractor(s) |
WESTERN SURETY COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-130 TALBRAN ENTERPRISES LLC (19.09) GARRET SHIELDS INFRASTRUCTURE (44.55) ROACH WELDING & FABRICATION LLC (0.85)
|
Contract # | 06213009 |
| Totals | 2346996.00 | 7423.80 | 2212643.69 | 99.9 |
|
County | HARRISON |
Highway | IH 20 |
From | GREGG C/L |
To | 0.5 MI W OF SH 43 |
CSJ | 0495-08-138 |
Proj ID | F 2023(843) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 16.891 | 4714765.00 | | 2475233.56 | 52.4 |
Work Order | 07-20-23 |
Work Began | 09-07-23 |
Work Completed | |
Time Computed | 09-07-23 |
Contract Working Days | 148 |
Addl Days Granted | 0 |
Working Days Charged | 107 |
Percent Time Used | 72 |
Contractor(s) |
GHB EQUIPMENT COMPANY, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-138 WINDING ROAD CONSTRUCTION, INC. (41.18) J. H. ODEN CONTRACTING COMPANY (1.60) STRIPING TECHNOLOGY, L.P. (0.56)
|
Contract # | 06233225 |
| Totals | 4714765.00 | 379816.61 | 2475233.56 | 52.4 |
|
County | HARRISON |
Highway | IH 20 |
From | AT US 59 |
To | . |
CSJ | 0495-09-056 |
Proj ID | C 495-9-56 |
Work Type | BRIDGE REPLACEMENT |
|
| 0.010 | 11887790.53 | | 9716809.24 | 82.1 |
Work Order | 09-21-21 |
Work Began | 10-21-21 |
Work Completed | |
Time Computed | 10-21-21 |
Contract Working Days | 440 |
Addl Days Granted | 0 |
Working Days Charged | 476 |
Percent Time Used | 108 |
Contractor(s) |
EAST TEXAS BRIDGE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0495-09-056 HODGES AND SON CONSTRUCTION COMPANY, INC. (1.55) J. H. ODEN CONTRACTING COMPANY (1.38) PANOLA SIGN & BARRICADE, INC. (0.31) SOUTHWEST ENVIRONMENT SERVICES LLC (0.16) STRIPING TECHNOLOGY, L.P. (8.98) MORRIS COUNTY CONTRACTORS, L.L.C. (1.32) TORO BRAVO CONSTRUCTION, LLC (0.38) SOUTHEAST GRINDING AND GROOVING LLC (0.06)
|
Contract # | 08213017 |
| Totals | 11887790.53 | 309318.51 | 9716809.24 | 82.1 |
|
County | MARION |
Highway | SH 155 |
From | SOUTH END OF BIG CYPRESS CREEK BRIDGE |
To | 1.5 MI W OF FM 729 |
CSJ | 0520-04-026 |
Proj ID | BR 2023(154) |
Work Type | BRIDGE REPLACEMENT |
|
| 1.065 | 44688042.63 | | 10359963.09 | 23.1 |
County | UPSHUR |
Highway | SH 155 |
From | GLENDIA DRIVE |
To | SOUTH END OF BIG CYPRESS CREEK BRIDGE |
CSJ | 0520-05-043 |
Proj ID | BR 2023(155) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.394 | 9111876.79 | | 1086812.93 | 11.9 |
Work Order | 06-14-23 |
Work Began | 06-28-23 |
Work Completed | |
Time Computed | 06-26-23 |
Contract Working Days | 880 |
Addl Days Granted | 0 |
Working Days Charged | 145 |
Percent Time Used | 16 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0520-04-026 CAP RIVER LLC (0.15) HODGES AND SON CONSTRUCTION COMPANY, INC. (3.90) ISAACS CONSTRUCTION SERVICES LLC (0.55) MORRIS COUNTY CONTRACTORS, L.L.C. (0.40) PANOLA SIGN & BARRICADE, INC. (0.09) WITHERS CONSTRUCTION, LLC (0.12) WEST TEXAS ROCK RESOURCES, LLC (0.00) SNOWHILL CONTRACTING LLC (1.63) STRIPING TECHNOLOGY, L.P. (0.33) TORO BRAVO CONSTRUCTION, LLC (4.05)
|
Contract # | 05233005 |
| Totals | 53799919.42 | 551718.95 | 11446776.02 | 21.2 |
|
County | TITUS ETC |
Highway | IH 30 ETC |
From | FRANKLIN COUNTY LINE |
To | MORRIS COUNTY LINE |
CSJ | 0610-03-100 |
Proj ID | F 2021(740) |
Work Type | SAFETY IMPROVEMENT PROJECTS |
|
| 63.308 | 6534113.55 | | 5479426.18 | 83.8 |
Work Order | 08-02-21 |
Work Began | 10-11-21 |
Work Completed | |
Time Computed | 09-01-21 |
Contract Working Days | 528 |
Addl Days Granted | 0 |
Working Days Charged | 514 |
Percent Time Used | 97 |
Contractor(s) |
HIGHWAY 19 CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0610-03-100 DUSTIN ALLEN, INC. (41.10) FLEX SUPPLY, LLC (0.91) CF SOUTHWEST ENVIRONMENT SERVICES LLC (0.00) STRIPING TECHNOLOGY, L.P. (1.44) AREA WIDE PROTECTIVE, INC. (0.86) SOUTHWEST ENVIRONMENT SERVICES LLC (0.77)
|
Contract # | 06213038 |
| Totals | 6534113.55 | 52735.44 | 5479426.18 | 83.8 |
|
County | MORRIS ETC |
Highway | IH 30 |
From | AT US 259 |
To | . |
CSJ | 0610-04-033 |
Proj ID | NH 2022(220) |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 39.692 | 33388167.53 | | 20482445.27 | 61.3 |
Work Order | 12-16-21 |
Work Began | 02-18-22 |
Work Completed | |
Time Computed | 01-15-22 |
Contract Working Days | 397 |
Addl Days Granted | 17 |
Working Days Charged | 266 |
Percent Time Used | 64 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0610-04-033 ISAACS CONSTRUCTION SERVICES LLC (0.56) MORRIS COUNTY CONTRACTORS, L.L.C. (0.53) PANOLA SIGN & BARRICADE, INC. (0.36) SURFACE PREPARATION TECHNOLOGIES, LLC (0.04) STRIPING TECHNOLOGY, L.P. (1.93)
|
Contract # | 11213019 |
| Totals | 33388167.53 | 119615.22 | 20482445.27 | 61.3 |
|
County | BOWIE |
Highway | IH 30 |
From | FM 3419 |
To | FM 989 |
CSJ | 0610-07-097 |
Proj ID | IM 0303(125) |
Work Type | FREEWAY OPERATIONAL IMPROVEMENTS |
|
| 0.519 | 58800539.83 | | 17834963.61 | 30.3 |
Work Order | 07-18-22 |
Work Began | 08-15-22 |
Work Completed | |
Time Computed | 08-15-22 |
Contract Working Days | 441 |
Addl Days Granted | 75 |
Working Days Charged | 231 |
Percent Time Used | 44 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0610-07-097 HODGES AND SON CONSTRUCTION COMPANY, INC. (1.31) MORRIS COUNTY CONTRACTORS, L.L.C. (1.14) S & S BRIDGE PAINTING, INC. (0.02) STATEWIDE SAFETY SYSTEMS (0.40) STRIPING TECHNOLOGY, L.P. (5.88) TORO BRAVO CONSTRUCTION, LLC (1.88) WEST TEXAS ROCK RESOURCES, LLC (0.00) SOUTHWEST ENVIRONMENT SERVICES LLC (0.23) ISAACS CONSTRUCTION SERVICES LLC (0.60) CAP RIVER LLC (0.67) CARTHAGE DRILLING, INC. (0.30)
|
Contract # | 06223202 |
| Totals | 58800539.83 | 505939.16 | 17834963.61 | 30.3 |
|
County | BOWIE |
Highway | IH 30 |
From | 0.6 MI W OF FM 989 |
To | ARKANSAS STATE LINE |
CSJ | 0610-07-113 |
Proj ID | NH 2020(455) |
Work Type | WIDEN FREEWAY |
|
| 5.854 | 88870748.58 | | 51817037.80 | 58.3 |
Work Order | 07-20-20 |
Work Began | 08-16-20 |
Work Completed | |
Time Computed | 08-17-20 |
Contract Working Days | 724 |
Addl Days Granted | 28 |
Working Days Charged | 704 |
Percent Time Used | 93 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0610-07-113 TIME STRIPING, INC. (0.98) DUSTIN ALLEN, INC. (0.72) EXPRESS EMPLOYMENT PROFESSIONALS (0.00) HODGES AND SON CONSTRUCTION COMPANY, INC. (0.00) COLLIER-MANPOWER, INC. (0.00) J. H. ODEN CONTRACTING COMPANY (0.18) SOUTHWEST ENVIRONMENT SERIVES, LLC (0.40) STRIPING TECHNOLOGY, L.P. (2.87) TORO BRAVO CONSTRUCTION, LLC (6.14) A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.09) ANTIGO CONSTRUCTION, INC. (0.09) CARTHAGE DRILLING, INC. (0.01) ACT SAW CUTTING & REMOVAL (0.01) TORO BRAVO CONSTRUCTION, LLC (0.01) HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (0.01) SOUTHEAST GRINDING AND GROOVING LLC (0.00) MORRIS COUNTY CONTRACTORS, L.L.C. (0.19)
|
Contract # | 05203201 |
| Totals | 88870748.58 | 40349.79 | 51817037.80 | 58.3 |
|
County | CASS |
Highway | VA |
From | VARIOUS LOCATIONS |
To | VARIOUS LOCATIONS |
CSJ | 0919-00-085 |
Proj ID | C 919-00-85 |
Work Type | SEAL COAT |
|
| | 2925770.24 | | 1005822.92 | 34.3 |
Work Order | 02-05-24 |
Work Began | 03-04-24 |
Work Completed | |
Time Computed | 03-06-24 |
Contract Working Days | 102 |
Addl Days Granted | 0 |
Working Days Charged | 14 |
Percent Time Used | 13 |
Contractor(s) |
STRIPE-A-ZONE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0919-00-085 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01243032 |
| Totals | 2925770.24 | 1005822.92 | 1005822.92 | 34.3 |
|
County | PANOLA |
Highway | CR |
From | AT BECK CREEK |
To | . |
CSJ | 0919-13-017 |
Proj ID | BR 1902(367) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.066 | 968856.50 | | 412314.10 | 42.5 |
Work Order | 07-26-23 |
Work Began | 01-18-24 |
Work Completed | |
Time Computed | 08-25-23 |
Contract Working Days | 53 |
Addl Days Granted | 0 |
Working Days Charged | 8 |
Percent Time Used | 15 |
Contractor(s) |
TRUE ROADS CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0919-13-017 DUSTIN ALLEN, INC. (1.89) J. H. ODEN CONTRACTING COMPANY (3.44) M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.93) PANOLA SIGN & BARRICADE, INC. (0.70)
|
Contract # | 06233452 |
| Totals | 968856.50 | 2200.00 | 412314.10 | 42.5 |
|
County | BOWIE |
Highway | VA |
From | NORTH AND SOUTH ELM STREET |
To | FRONT STREET, W LION DR AND ELLIS STREET |
CSJ | 0919-19-083 |
Proj ID | STP 2021(276)TAPS |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| | 760142.25 | | 607880.12 | 84.4 |
Work Order | 12-14-22 |
Work Began | 04-11-23 |
Work Completed | |
Time Computed | 01-13-23 |
Contract Working Days | 64 |
Addl Days Granted | 0 |
Working Days Charged | 119 |
Percent Time Used | 185 |
Contractor(s) |
BLACKSTONE CONCRETE VENTURES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0919-19-083 TRAFFIC HIGHWAY MAINTENANCE, LLC (1.71) HODGES AND SON CONSTRUCTION COMPANY, INC. (5.04) KITECO PROPERTY SOLUTIONS INC. (1.94)
|
Contract # | 10223211 |
| Totals | 760142.25 | 1250.00 | 607880.12 | 84.4 |
|
County | BOWIE |
Highway | 0000000 |
From | ALONG US 82 FROM CR 4105 |
To | SH 98 |
CSJ | 0919-19-087 |
Proj ID | STP 2022(679)TAPS |
Work Type | PEDESTRIAN, SIDEWALKS & CURB RAMPS |
|
| 3.133 | 1656386.60 | | 194700.00 | 11.7 |
County | BOWIE |
Highway | 0000000 |
From | ALONG US 82 FROM CR 4105 |
To | SH 98 |
CSJ | 0919-19-094 |
Proj ID | ROW 919-19-94 |
Work Type | UTILITY ADJUSTMENTS |
|
| 3.133 | 302122.50 | | 33800.00 | 11.1 |
Work Order | 10-23-23 |
Work Began | 01-30-24 |
Work Completed | |
Time Computed | 11-23-23 |
Contract Working Days | 185 |
Addl Days Granted | 0 |
Working Days Charged | 49 |
Percent Time Used | 26 |
Contractor(s) |
GARRET SHIELDS INFRASTRUCTURE |
SUBCONTRACTOR(S) FOR CCSJ: 0919-19-087 MOORE CONSTRUCTION SERVICES, LLC (12.15) SKC EARTHWORKS LIMITED LIABILITY COMPANY (45.08) DIAMOND ELITE BARRICADES, LLC (0.41)
|
Contract # | 09233023 |
| Totals | 1958509.10 | 102125.00 | 228500.00 | 11.6 |
|
County | TITUS |
Highway | FM 1735 |
From | SH 49 |
To | 2.1 MI S OF SH 49 |
CSJ | 1226-02-016 |
Proj ID | C 1226-2-16 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 2.102 | 11920527.81 | | 4750906.44 | 39.8 |
Work Order | 02-14-23 |
Work Began | 05-03-23 |
Work Completed | |
Time Computed | 05-04-23 |
Contract Working Days | 276 |
Addl Days Granted | 8 |
Working Days Charged | 129 |
Percent Time Used | 45 |
Contractor(s) |
H. H. HOWARD & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1226-02-016 J. H. ODEN CONTRACTING COMPANY (3.18) PANOLA SIGN & BARRICADE, INC. (0.25) PROFESSIONAL TRAFFIC CONTROL LLC (0.02) RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (16.13) WITHERS CONSTRUCTION, LLC (0.71) STRIPING TECHNOLOGY, L.P. (4.55) TEXOP CONSTRUCTION (0.84) TRAFFIC HIGHWAY MAINTENANCE, LLC (0.43)
|
Contract # | 01233005 |
| Totals | 11920527.81 | 1100.00 | 4750906.44 | 39.8 |
|
County | BOWIE |
Highway | FM 989 |
From | US 82 |
To | US 67 |
CSJ | 1231-01-069 |
Proj ID | F 2023(683) |
Work Type | OVERLAY |
|
| 1.910 | 1902107.55 | | 2053780.89 | 99.9 |
Work Order | 08-23-23 |
Work Began | 09-26-23 |
Work Completed | |
Time Computed | 09-22-23 |
Contract Working Days | 33 |
Addl Days Granted | 0 |
Working Days Charged | 33 |
Percent Time Used | 100 |
Contractor(s) |
RK HALL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1231-01-069 J. H. ODEN CONTRACTING COMPANY (0.13) PANOLA SIGN & BARRICADE, INC. (0.69) STRIPING TECHNOLOGY, L.P. (3.74) TEXOP CONSTRUCTION (8.42) WITHERS CONSTRUCTION, LLC (0.86)
|
Contract # | 05233023 |
| Totals | 1902107.55 | 0.00 | 2053780.89 | 99.9 |
|
County | UPSHUR |
Highway | SH 300 |
From | 0.2 MI S OF US 271 |
To | 0.1 MI N OF S FM 3358 |
CSJ | 1385-01-045 |
Proj ID | C 1385-1-45 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 9.058 | 22871598.15 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 212 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
MADDEN CONTRACTING COMPANY, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 1385-01-045 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04243003 |
| Totals | 22871598.15 | 0.00 | 0.00 | 0.0 |
|
County | UPSHUR |
Highway | FM 993 |
From | AT WEST GREASY CREEK |
To | . |
CSJ | 1511-01-013 |
Proj ID | BR 2024(791) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.066 | 1523718.09 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 04-11-24 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 83 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
THK CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1511-01-013 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03243222 |
| Totals | 1523718.09 | 0.00 | 0.00 | 0.0 |
|
County | MORRIS |
Highway | FM 161 |
From | US 67 |
To | CASS C/L |
CSJ | 1574-01-018 |
Proj ID | C 1574-1-18 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| 4.174 | 2848202.22 | | 0.00 | 0.0 |
County | CASS |
Highway | FM 161 |
From | MORRIS C/L |
To | 0.1 MI S OF MORRIS C/L |
CSJ | 1574-02-026 |
Proj ID | C 1574-2-26 |
Work Type | REHABILITATION OF EXISTING ROAD |
|
| | 942890.05 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 193 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
A. K. GILLIS & SONS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1574-01-018 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04243213 |
| Totals | 3791092.27 | 0.00 | 0.00 | 0.0 |
|
County | HARRISON |
Highway | FM 726 |
From | AT COPELAND CREEK |
To | . |
CSJ | 1895-02-013 |
Proj ID | BR 2B23(016) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.160 | 1697965.52 | | 1963459.38 | 99.9 |
Work Order | 09-07-23 |
Work Began | 11-27-23 |
Work Completed | |
Time Computed | 11-27-23 |
Contract Working Days | 150 |
Addl Days Granted | 0 |
Working Days Charged | 74 |
Percent Time Used | 49 |
Contractor(s) |
THK CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 1895-02-013 CAP RIVER LLC (0.71) HODGES AND SON CONSTRUCTION COMPANY, INC. (5.92) MORRIS COUNTY CONTRACTORS, L.L.C. (1.93) PANOLA SIGN & BARRICADE, INC. (0.64) PENHALL COMPANY (0.26) STRIPING TECHNOLOGY, L.P. (0.81) TEXOP CONSTRUCTION (0.52) TORO BRAVO CONSTRUCTION, LLC (0.30) ISAACS CONSTRUCTION SERVICES LLC (0.00) J. H. ODEN CONTRACTING COMPANY (3.00) PEACHTREE CONSTRUCTION, LTD. (5.55)
|
Contract # | 08233248 |
| Totals | 1697965.52 | 1642.00 | 1963459.38 | 99.9 |
|
County | HARRISON |
Highway | FM 3001 |
From | AT LITTLE CYPRESS BAYOU RELIEF |
To | . |
CSJ | 3041-03-012 |
Proj ID | BR 2022(504) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.243 | 4618853.24 | | 2728860.60 | 59.0 |
Work Order | 06-16-22 |
Work Began | 08-30-22 |
Work Completed | |
Time Computed | 07-18-22 |
Contract Working Days | 343 |
Addl Days Granted | 0 |
Working Days Charged | 269 |
Percent Time Used | 78 |
Contractor(s) |
HIGHWAY 19 CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 3041-03-012 FLEX SUPPLY, LLC (0.48) DUSTIN ALLEN, INC. (0.81) PRIMATE CONSTRUCTION, LP (0.17) TEX OP CONSTRUCTION, LP (0.36) FARR FOUNDATION, INC. (8.84) STRIPING TECHNOLOGY, L.P. (1.07) A. E. MOORE CONSTRUCTION, INC. (3.08)
|
Contract # | 05223216 |
| Totals | 4618853.24 | 239080.00 | 2728860.60 | 59.0 |
|