Monthly State Let Construction Report For Atlanta District As Of Apr 12, 2024 Page 2 Of 2

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRISON
HighwayIH 20
FromGREGG COUNTY LINE
To0.5 MI. W. OF SH 43
CSJ0495-08-130
Proj IDF 2021(584)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
39.1292346996.002212643.6999.9
Work Order07-22-21
Work Began08-24-21
Work Completed
Time Computed08-21-21
Contract Working Days95
Addl Days Granted38
Working Days Charged433
Percent Time Used325
Contractor(s)
WESTERN SURETY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-130
TALBRAN ENTERPRISES LLC (19.09)
GARRET SHIELDS INFRASTRUCTURE (44.55)
ROACH WELDING & FABRICATION LLC (0.85)
Contract #06213009
Totals2346996.007423.802212643.6999.9

CountyHARRISON
HighwayIH 20
FromGREGG C/L
To0.5 MI W OF SH 43
CSJ0495-08-138
Proj IDF 2023(843)
Work TypeREHABILITATION OF EXISTING ROAD
 
16.8914714765.002475233.5652.4
Work Order07-20-23
Work Began09-07-23
Work Completed
Time Computed09-07-23
Contract Working Days148
Addl Days Granted0
Working Days Charged107
Percent Time Used72
Contractor(s)
GHB EQUIPMENT COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0495-08-138
WINDING ROAD CONSTRUCTION, INC. (41.18)
J. H. ODEN CONTRACTING COMPANY (1.60)
STRIPING TECHNOLOGY, L.P. (0.56)
Contract #06233225
Totals4714765.00379816.612475233.5652.4

CountyHARRISON
HighwayIH 20
FromAT US 59
To.
CSJ0495-09-056
Proj IDC 495-9-56
Work TypeBRIDGE REPLACEMENT
 
0.01011887790.539716809.2482.1
Work Order09-21-21
Work Began10-21-21
Work Completed
Time Computed10-21-21
Contract Working Days440
Addl Days Granted0
Working Days Charged476
Percent Time Used108
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0495-09-056
HODGES AND SON CONSTRUCTION COMPANY, INC. (1.55)
J. H. ODEN CONTRACTING COMPANY (1.38)
PANOLA SIGN & BARRICADE, INC. (0.31)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.16)
STRIPING TECHNOLOGY, L.P. (8.98)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.32)
TORO BRAVO CONSTRUCTION, LLC (0.38)
SOUTHEAST GRINDING AND GROOVING LLC (0.06)
Contract #08213017
Totals11887790.53309318.519716809.2482.1

CountyMARION
HighwaySH 155
FromSOUTH END OF BIG CYPRESS CREEK BRIDGE
To1.5 MI W OF FM 729
CSJ0520-04-026
Proj IDBR 2023(154)
Work TypeBRIDGE REPLACEMENT
 
1.06544688042.6310359963.0923.1
CountyUPSHUR
HighwaySH 155
FromGLENDIA DRIVE
ToSOUTH END OF BIG CYPRESS CREEK BRIDGE
CSJ0520-05-043
Proj IDBR 2023(155)
Work TypeBRIDGE REPLACEMENT
 
0.3949111876.791086812.9311.9
Work Order06-14-23
Work Began06-28-23
Work Completed
Time Computed06-26-23
Contract Working Days880
Addl Days Granted0
Working Days Charged145
Percent Time Used16
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0520-04-026
CAP RIVER LLC (0.15)
HODGES AND SON CONSTRUCTION COMPANY, INC. (3.90)
ISAACS CONSTRUCTION SERVICES LLC (0.55)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.40)
PANOLA SIGN & BARRICADE, INC. (0.09)
WITHERS CONSTRUCTION, LLC (0.12)
WEST TEXAS ROCK RESOURCES, LLC (0.00)
SNOWHILL CONTRACTING LLC (1.63)
STRIPING TECHNOLOGY, L.P. (0.33)
TORO BRAVO CONSTRUCTION, LLC (4.05)
Contract #05233005
Totals53799919.42551718.9511446776.0221.2

CountyTITUS ETC
HighwayIH 30 ETC
FromFRANKLIN COUNTY LINE
ToMORRIS COUNTY LINE
CSJ0610-03-100
Proj IDF 2021(740)
Work TypeSAFETY IMPROVEMENT PROJECTS
 
63.3086534113.555479426.1883.8
Work Order08-02-21
Work Began10-11-21
Work Completed
Time Computed09-01-21
Contract Working Days528
Addl Days Granted0
Working Days Charged514
Percent Time Used97
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0610-03-100
DUSTIN ALLEN, INC. (41.10)
FLEX SUPPLY, LLC (0.91)
CF SOUTHWEST ENVIRONMENT SERVICES LLC (0.00)
STRIPING TECHNOLOGY, L.P. (1.44)
AREA WIDE PROTECTIVE, INC. (0.86)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.77)
Contract #06213038
Totals6534113.5552735.445479426.1883.8

CountyMORRIS ETC
HighwayIH 30
FromAT US 259
To.
CSJ0610-04-033
Proj IDNH 2022(220)
Work TypeREHABILITATION OF EXISTING ROAD
 
39.69233388167.5320482445.2761.3
Work Order12-16-21
Work Began02-18-22
Work Completed
Time Computed01-15-22
Contract Working Days397
Addl Days Granted17
Working Days Charged266
Percent Time Used64
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0610-04-033
ISAACS CONSTRUCTION SERVICES LLC (0.56)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.53)
PANOLA SIGN & BARRICADE, INC. (0.36)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.04)
STRIPING TECHNOLOGY, L.P. (1.93)
Contract #11213019
Totals33388167.53119615.2220482445.2761.3

CountyBOWIE
HighwayIH 30
FromFM 3419
ToFM 989
CSJ0610-07-097
Proj IDIM 0303(125)
Work TypeFREEWAY OPERATIONAL IMPROVEMENTS
 
0.51958800539.8317834963.6130.3
Work Order07-18-22
Work Began08-15-22
Work Completed
Time Computed08-15-22
Contract Working Days441
Addl Days Granted75
Working Days Charged231
Percent Time Used44
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0610-07-097
HODGES AND SON CONSTRUCTION COMPANY, INC. (1.31)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.14)
S & S BRIDGE PAINTING, INC. (0.02)
STATEWIDE SAFETY SYSTEMS (0.40)
STRIPING TECHNOLOGY, L.P. (5.88)
TORO BRAVO CONSTRUCTION, LLC (1.88)
WEST TEXAS ROCK RESOURCES, LLC (0.00)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.23)
ISAACS CONSTRUCTION SERVICES LLC (0.60)
CAP RIVER LLC (0.67)
CARTHAGE DRILLING, INC. (0.30)
Contract #06223202
Totals58800539.83505939.1617834963.6130.3

CountyBOWIE
HighwayIH 30
From0.6 MI W OF FM 989
ToARKANSAS STATE LINE
CSJ0610-07-113
Proj IDNH 2020(455)
Work TypeWIDEN FREEWAY
 
5.85488870748.5851817037.8058.3
Work Order07-20-20
Work Began08-16-20
Work Completed
Time Computed08-17-20
Contract Working Days724
Addl Days Granted28
Working Days Charged704
Percent Time Used93
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0610-07-113
TIME STRIPING, INC. (0.98)
DUSTIN ALLEN, INC. (0.72)
EXPRESS EMPLOYMENT PROFESSIONALS (0.00)
HODGES AND SON CONSTRUCTION COMPANY, INC. (0.00)
COLLIER-MANPOWER, INC. (0.00)
J. H. ODEN CONTRACTING COMPANY (0.18)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.40)
STRIPING TECHNOLOGY, L.P. (2.87)
TORO BRAVO CONSTRUCTION, LLC (6.14)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.09)
ANTIGO CONSTRUCTION, INC. (0.09)
CARTHAGE DRILLING, INC. (0.01)
ACT SAW CUTTING & REMOVAL (0.01)
TORO BRAVO CONSTRUCTION, LLC (0.01)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (0.01)
SOUTHEAST GRINDING AND GROOVING LLC (0.00)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.19)
Contract #05203201
Totals88870748.5840349.7951817037.8058.3

CountyCASS
HighwayVA
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ0919-00-085
Proj IDC 919-00-85
Work TypeSEAL COAT
 
2925770.241005822.9234.3
Work Order02-05-24
Work Began03-04-24
Work Completed
Time Computed03-06-24
Contract Working Days102
Addl Days Granted0
Working Days Charged14
Percent Time Used13
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0919-00-085
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243032
Totals2925770.241005822.921005822.9234.3

CountyPANOLA
HighwayCR
FromAT BECK CREEK
To.
CSJ0919-13-017
Proj IDBR 1902(367)
Work TypeBRIDGE REPLACEMENT
 
0.066968856.50412314.1042.5
Work Order07-26-23
Work Began01-18-24
Work Completed
Time Computed08-25-23
Contract Working Days53
Addl Days Granted0
Working Days Charged8
Percent Time Used15
Contractor(s)
TRUE ROADS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0919-13-017
DUSTIN ALLEN, INC. (1.89)
J. H. ODEN CONTRACTING COMPANY (3.44)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.93)
PANOLA SIGN & BARRICADE, INC. (0.70)
Contract #06233452
Totals968856.502200.00412314.1042.5

CountyBOWIE
HighwayVA
FromNORTH AND SOUTH ELM STREET
ToFRONT STREET, W LION DR AND ELLIS STREET
CSJ0919-19-083
Proj IDSTP 2021(276)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
760142.25607880.1284.4
Work Order12-14-22
Work Began04-11-23
Work Completed
Time Computed01-13-23
Contract Working Days64
Addl Days Granted0
Working Days Charged119
Percent Time Used185
Contractor(s)
BLACKSTONE CONCRETE VENTURES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0919-19-083
TRAFFIC HIGHWAY MAINTENANCE, LLC (1.71)
HODGES AND SON CONSTRUCTION COMPANY, INC. (5.04)
KITECO PROPERTY SOLUTIONS INC. (1.94)
Contract #10223211
Totals760142.251250.00607880.1284.4

CountyBOWIE
Highway0000000
FromALONG US 82 FROM CR 4105
ToSH 98
CSJ0919-19-087
Proj IDSTP 2022(679)TAPS
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
3.1331656386.60194700.0011.7
CountyBOWIE
Highway0000000
FromALONG US 82 FROM CR 4105
ToSH 98
CSJ0919-19-094
Proj IDROW 919-19-94
Work TypeUTILITY ADJUSTMENTS
 
3.133302122.5033800.0011.1
Work Order10-23-23
Work Began01-30-24
Work Completed
Time Computed11-23-23
Contract Working Days185
Addl Days Granted0
Working Days Charged49
Percent Time Used26
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0919-19-087
MOORE CONSTRUCTION SERVICES, LLC (12.15)
SKC EARTHWORKS LIMITED LIABILITY COMPANY (45.08)
DIAMOND ELITE BARRICADES, LLC (0.41)
Contract #09233023
Totals1958509.10102125.00228500.0011.6

CountyTITUS
HighwayFM 1735
FromSH 49
To2.1 MI S OF SH 49
CSJ1226-02-016
Proj IDC 1226-2-16
Work TypeREHABILITATION OF EXISTING ROAD
 
2.10211920527.814750906.4439.8
Work Order02-14-23
Work Began05-03-23
Work Completed
Time Computed05-04-23
Contract Working Days276
Addl Days Granted8
Working Days Charged129
Percent Time Used45
Contractor(s)
H. H. HOWARD & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1226-02-016
J. H. ODEN CONTRACTING COMPANY (3.18)
PANOLA SIGN & BARRICADE, INC. (0.25)
PROFESSIONAL TRAFFIC CONTROL LLC (0.02)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. (16.13)
WITHERS CONSTRUCTION, LLC (0.71)
STRIPING TECHNOLOGY, L.P. (4.55)
TEXOP CONSTRUCTION (0.84)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.43)
Contract #01233005
Totals11920527.811100.004750906.4439.8

CountyBOWIE
HighwayFM 989
FromUS 82
ToUS 67
CSJ1231-01-069
Proj IDF 2023(683)
Work TypeOVERLAY
 
1.9101902107.552053780.8999.9
Work Order08-23-23
Work Began09-26-23
Work Completed
Time Computed09-22-23
Contract Working Days33
Addl Days Granted0
Working Days Charged33
Percent Time Used100
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1231-01-069
J. H. ODEN CONTRACTING COMPANY (0.13)
PANOLA SIGN & BARRICADE, INC. (0.69)
STRIPING TECHNOLOGY, L.P. (3.74)
TEXOP CONSTRUCTION (8.42)
WITHERS CONSTRUCTION, LLC (0.86)
Contract #05233023
Totals1902107.550.002053780.8999.9

CountyUPSHUR
HighwaySH 300
From0.2 MI S OF US 271
To0.1 MI N OF S FM 3358
CSJ1385-01-045
Proj IDC 1385-1-45
Work TypeREHABILITATION OF EXISTING ROAD
 
9.05822871598.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days212
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 1385-01-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243003
Totals22871598.150.000.000.0

CountyUPSHUR
HighwayFM 993
FromAT WEST GREASY CREEK
To.
CSJ1511-01-013
Proj IDBR 2024(791)
Work TypeBRIDGE REPLACEMENT
 
0.0661523718.090.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-11-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days83
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1511-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243222
Totals1523718.090.000.000.0

CountyMORRIS
HighwayFM 161
FromUS 67
ToCASS C/L
CSJ1574-01-018
Proj IDC 1574-1-18
Work TypeREHABILITATION OF EXISTING ROAD
 
4.1742848202.220.000.0
CountyCASS
HighwayFM 161
FromMORRIS C/L
To0.1 MI S OF MORRIS C/L
CSJ1574-02-026
Proj IDC 1574-2-26
Work TypeREHABILITATION OF EXISTING ROAD
 
942890.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days193
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A. K. GILLIS & SONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1574-01-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243213
Totals3791092.270.000.000.0

CountyHARRISON
HighwayFM 726
FromAT COPELAND CREEK
To.
CSJ1895-02-013
Proj IDBR 2B23(016)
Work TypeBRIDGE REPLACEMENT
 
0.1601697965.521963459.3899.9
Work Order09-07-23
Work Began11-27-23
Work Completed
Time Computed11-27-23
Contract Working Days150
Addl Days Granted0
Working Days Charged74
Percent Time Used49
Contractor(s)
THK CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1895-02-013
CAP RIVER LLC (0.71)
HODGES AND SON CONSTRUCTION COMPANY, INC. (5.92)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.93)
PANOLA SIGN & BARRICADE, INC. (0.64)
PENHALL COMPANY (0.26)
STRIPING TECHNOLOGY, L.P. (0.81)
TEXOP CONSTRUCTION (0.52)
TORO BRAVO CONSTRUCTION, LLC (0.30)
ISAACS CONSTRUCTION SERVICES LLC (0.00)
J. H. ODEN CONTRACTING COMPANY (3.00)
PEACHTREE CONSTRUCTION, LTD. (5.55)
Contract #08233248
Totals1697965.521642.001963459.3899.9

CountyHARRISON
HighwayFM 3001
FromAT LITTLE CYPRESS BAYOU RELIEF
To.
CSJ3041-03-012
Proj IDBR 2022(504)
Work TypeBRIDGE REPLACEMENT
 
0.2434618853.242728860.6059.0
Work Order06-16-22
Work Began08-30-22
Work Completed
Time Computed07-18-22
Contract Working Days343
Addl Days Granted0
Working Days Charged269
Percent Time Used78
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 3041-03-012
FLEX SUPPLY, LLC (0.48)
DUSTIN ALLEN, INC. (0.81)
PRIMATE CONSTRUCTION, LP (0.17)
TEX OP CONSTRUCTION, LP (0.36)
FARR FOUNDATION, INC. (8.84)
STRIPING TECHNOLOGY, L.P. (1.07)
A. E. MOORE CONSTRUCTION, INC. (3.08)
Contract #05223216
Totals4618853.24239080.002728860.6059.0