Monthly State Let Construction Report For Atlanta District As Of Oct 10, 2023 Page 3 Of 3
Last Update: Tuesday, October 10, 2023
|
|
Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | HARRISON |
Highway | FM 3001 |
From | AT LITTLE CYPRESS BAYOU RELIEF |
To | . |
CSJ | 3041-03-012 |
Proj ID | BR 2022(504) |
Work Type | BRIDGE REPLACEMENT |
|
| 0.243 | 4618853.24 | | 2069749.10 | 44.8 |
Work Order | 06-16-22 |
Work Began | 08-30-22 |
Work Completed | |
Time Computed | 07-18-22 |
Contract Working Days | 343 |
Addl Days Granted | 0 |
Working Days Charged | 206 |
Percent Time Used | 60 |
Contractor(s) |
HIGHWAY 19 CONSTRUCTION LLC |
SUBCONTRACTOR(S) FOR CCSJ: 3041-03-012 FLEX SUPPLY, LLC (0.48) DUSTIN ALLEN, INC. (0.81) PRIMATE CONSTRUCTION, LP (0.17) TEX OP CONSTRUCTION, LP (0.36) FARR FOUNDATION, INC. (8.84) STRIPING TECHNOLOGY, L.P. (1.07) A. E. MOORE CONSTRUCTION, INC. (3.08)
|
Contract # | 05223216 |
| Totals | 4618853.24 | 64923.80 | 2069749.10 | 44.8 |
|
County | CAMP |
Highway | SL 255 |
From | FM 1520 |
To | US 271 |
CSJ | 3403-01-001 |
Proj ID | STP 2021(267) |
Work Type | NEW LOCATION NON-FREEWAY |
|
| 2.462 | 5634658.36 | | 7047084.77 | 99.9 |
Work Order | 05-20-21 |
Work Began | 06-07-21 |
Work Completed | |
Time Computed | 06-07-21 |
Contract Working Days | 334 |
Addl Days Granted | 96 |
Working Days Charged | 402 |
Percent Time Used | 93 |
Contractor(s) |
R & G CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 3403-01-001 CDM HOLDINGS, LLC (7.58) J. H. ODEN CONTRACTING COMPANY (1.84) MORRIS COUNTY CONTRACTORS, L.L.C. (0.57) PANOLA SIGN & BARRICADE, INC. (0.35) RK HALL, LLC (7.90) STRIPE-A-ZONE, INC. (1.82) STRIPING TECHNOLOGY, L.P. (1.40) CF SOUTHWEST ENVIRONMENT SERVICES LLC (2.12) RED TOP TRUCKING LLC (5.00) DUSTROL, INC. (0.35) HEMPHILL WBE PILE DRIVING CO. (8.02)
|
Contract # | 01213005 |
| Totals | 5634658.36 | 758051.89 | 7047084.77 | 99.9 |
|