Monthly Local Let Maintenance Report For Atlanta District As Of Apr 11, 2014 Page 1 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHARRISON
Highway IH0020
From VARIOUS
To .
CSJ 6217-02-001
Proj ID RMC - 621702001
Work Type ROW MOWING & LITTER PICKUP - TRACT 16
 
0.001 56993.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HAMM'S CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6217-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12101907
Totals 56993.16 0.00 0.00 0.0

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6230-06-001
Proj ID RMC - 623006001
Work Type GUIDE AND CALL - OUT SIGN INSTALLATION
 
0.001 289075.00 124470.00 637050.00 99.9
Work Order 12-13-11
Work Began 01-02-12
Work Completed  
Time Computed 01-02-12
Contract Working Days 254
Addl Days Granted 254
Working Days Charged 443
Percent Time Used 87
Contractor(s)
TIME STRIPING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6230-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10111901
Totals 289075.00 124470.00 637050.00 99.9

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6236-21-001
Proj ID RMC - 623621001
Work Type ILLUMINATION MAINTENANCE
 
0.001 164755.00 14250.00 231905.00 99.9
Work Order 04-19-12
Work Began 05-02-12
Work Completed  
Time Computed 05-01-12
Contract Working Days 306
Addl Days Granted 306
Working Days Charged 483
Percent Time Used 78
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6236-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03121901
Totals 164755.00 14250.00 231905.00 99.9

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6240-42-001
Proj ID RMC - 624042001
Work Type CALLOUT MBGF REPAIR
 
0.001 178415.00 4802.00 208613.25 99.9
Work Order 07-12-12
Work Began 07-19-12
Work Completed  
Time Computed 07-19-12
Contract Working Days 306
Addl Days Granted 306
Working Days Charged 519
Percent Time Used 84
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6240-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05121902
Totals 178415.00 4802.00 208613.25 99.9

CountyBOWIE
Highway IH0030
From VARIOUS
To .
CSJ 6240-43-001
Proj ID RMC - 624043001
Work Type DEBRIS REMOVAL (NORTH)
 
124.000 41600.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 306
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BENNIE JOHNSON CO.
SUBCONTRACTOR(S) FOR CCSJ: 6240-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05121901
Totals 41600.00 0.00 0.00 0.0

CountyHARRISON
Highway SH0043
From VARIOUS
To .
CSJ 6243-44-001
Proj ID SUP - 624344001
Work Type PICNIC AREA MAINTENANCE
 
0.001 63148.36 0.00 33280.93 52.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-23-12
Work Began 08-01-12
Work Completed  
Time Computed 08-01-12
Contract Working Days 365
Addl Days Granted 31
Working Days Charged 396
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6243-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06121931
Totals 63148.36 0.00 33280.93 52.7

CountyCASS
Highway US0059
From VARIOUS
To .
CSJ 6245-03-001
Proj ID SUP - 624503001
Work Type PICNIC AREA MAINTENANCE - BOWIE / CASS
 
0.001 50325.02 0.00 36225.85 71.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6245-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08121932
Totals 50325.02 0.00 36225.85 71.9

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6245-82-001
Proj ID SUP - 624582001
Work Type LITTER PICKUP & DISPOSAL
 
0.001 45630.32 0.00 42255.32 92.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6245-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08121936
Totals 45630.32 0.00 42255.32 92.6

CountyHARRISON
Highway US0059
From VARIOUS
To .
CSJ 6245-84-001
Proj ID SUP - 624584001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 39215.25 0.00 35840.25 91.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-12
Work Began 09-01-12
Work Completed  
Time Computed 09-01-12
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6245-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08121934
Totals 39215.25 0.00 35840.25 91.3

CountyHARRISON
Highway LP0390
From VARIOUS
To .
CSJ 6257-12-001
Proj ID SUP - 625712001
Work Type GROUNDS MAINTENANCE
 
0.001 13895.76 578.99 9263.84 66.6
Work Order 05-01-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 91
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6257-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03131934
Totals 13895.76 578.99 9263.84 66.6

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6258-96-001
Proj ID SUP - 625896001
Work Type GROUNDS MAINTENANCE - TEXARKANA
 
0.001 7632.00 0.00 4452.00 58.3
Work Order 05-21-13
Work Began 06-01-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131932
Totals 7632.00 0.00 4452.00 58.3

CountyBOWIE
Highway SH0008
From VARIOUS
To .
CSJ 6258-97-001
Proj ID SUP - 625897001
Work Type GROUNDS MAINTENANCE
 
0.001 8952.00 0.00 4103.00 45.8
Work Order 05-21-13
Work Began 06-01-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131934
Totals 8952.00 0.00 4103.00 45.8

CountyCASS
Highway SH0008
From VARIOUS
To .
CSJ 6258-98-001
Proj ID SUP - 625898001
Work Type GROUNDS MAINTENANCE - LINDEN
 
0.001 7152.00 0.00 2384.00 33.3
Work Order 05-21-13
Work Began 06-01-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 304
Percent Time Used 83
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131931
Totals 7152.00 0.00 2384.00 33.3

CountyPANOLA
Highway BU0059D
From VARIOUS
To .
CSJ 6258-99-001
Proj ID SUP - 625899001
Work Type GROUNDS MAINTENANCE
 
0.001 7248.00 0.00 906.00 12.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-21-13
Work Began 06-01-13
Work Completed  
Time Computed 06-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6258-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05131933
Totals 7248.00 0.00 906.00 12.5

CountyMORRIS
Highway SH0049
From VARIOUS
To .
CSJ 6259-05-001
Proj ID RMC - 625905001
Work Type CRACK SEALING
 
396.650 201049.96 0.00 218636.81 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-08-13
Work Began 12-09-13
Work Completed  
Time Computed 12-16-13
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 10
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6259-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131901
Totals 201049.96 0.00 218636.81 99.9

CountyHARRISON
Highway SH0043
From VARIOUS
To .
CSJ 6260-48-001
Proj ID SUP - 626048001
Work Type PICNIC AREA MAINTENANCE
 
0.001 37169.27 1813.36 14032.27 37.7
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
THE ARC OF HARRISON COUNTY
SUBCONTRACTOR(S) FOR CCSJ: 6260-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131931
Totals 37169.27 1813.36 14032.27 37.7

CountyCASS
Highway US0059
From VARIOUS
To .
CSJ 6260-49-001
Proj ID SUP - 626049001
Work Type PICNIC AREA MAINTENANCE - BOWIE / CASS / TITUS
 
0.001 56435.02 5403.99 22950.03 40.6
Work Order 09-01-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6260-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131935
Totals 56435.02 5403.99 22950.03 40.6

CountyHARRISON
Highway US0059
From VARIOUS
To .
CSJ 6261-13-001
Proj ID SUP - 626113001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 61209.52 13730.10 23772.62 38.8
Work Order 08-23-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
COMMUNITY HEALTHCORE
SUBCONTRACTOR(S) FOR CCSJ: 6261-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131934
Totals 61209.52 13730.10 23772.62 38.8

CountyCAMP
Highway US0271
From VARIOUS
To .
CSJ 6261-14-001
Proj ID SUP - 626114001
Work Type LITTER PICKUP AND DISPOSAL
 
0.001 100841.64 2260.64 49863.64 49.4
Work Order 08-06-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
CAMP COUNTY SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6261-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131932
Totals 100841.64 2260.64 49863.64 49.4

CountyBOWIE
Highway US0059
From VARIOUS
To .
CSJ 6261-15-001
Proj ID SUP - 626115001
Work Type LITTER PICKUP & DISPOSAL
 
0.001 132184.73 5287.68 66959.08 50.6
Work Order 08-12-13
Work Began 09-01-13
Work Completed  
Time Computed 09-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
VOCATIONAL OPPORTUNITIES CENTER NORTHEAST TEXAS,INC
SUBCONTRACTOR(S) FOR CCSJ: 6261-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08131933
Totals 132184.73 5287.68 66959.08 50.6