Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | BURNET |
Highway | US0281 |
From | VARIOUS LOCATIONS IN |
To | BURNET AND LLANO COUNTIES |
CSJ | 6386-70-001 |
Proj ID | RMC - 638670001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 397600.00 | | 385600.00 | 96.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 07-19-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 92 |
Addl Days Granted | 0 |
Working Days Charged | 36 |
Percent Time Used | 39 |
Contractor(s) |
JASCO |
SUBCONTRACTOR(S) FOR CCSJ: 6386-70-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03224204 |
| Totals | 397600.00 | 96400.00 | 385600.00 | 96.9 |
|
County | TRAVIS |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN |
To | TRAVIS COUNTY |
CSJ | 6387-69-001 |
Proj ID | RMC - 638769001 |
Work Type | TRAFFIC SIGNAL MAINTENANCE |
|
| 0.010 | 591420.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 85 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
ELECNOR BELCO ELECTRIC, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6387-69-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12234201 |
| Totals | 591420.00 | 0.00 | 0.00 | 0.0 |
|
County | TRAVIS |
Highway | US0183 |
From | VARIOUS LOCATIONS IN TRAVIS, |
To | WILLIAMSON AND HAYS COUNTY |
CSJ | 6387-86-001 |
Proj ID | RMC - 638786001 |
Work Type | SWEEPING AND DEBRIS REMOVAL |
|
| 0.010 | 597970.00 | | 356005.00 | 59.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 517 |
Percent Time Used | 70 |
Contractor(s) |
SWEEPING CORPORATION OF AMERICA, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6387-86-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06224202 |
| Totals | 597970.00 | 24630.00 | 356005.00 | 59.5 |
|
County | TRAVIS |
Highway | US0183 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6391-93-001 |
Proj ID | BPM - 639193001 |
Work Type | BRIDGE REPAIR |
|
| 0.010 | 1429650.00 | | 16448.00 | 1.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-05-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 3 |
Percent Time Used | 0 |
Contractor(s) |
RESTEK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6391-93-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03224003 |
| Totals | 1429650.00 | 3000.00 | 16448.00 | 1.1 |
|
County | TRAVIS |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6391-94-001 |
Proj ID | BPM - 639194001 |
Work Type | BRIDGE REPAIR |
|
| 0.010 | 1558775.00 | | 14461.00 | 0.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-10-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 88 |
Percent Time Used | 12 |
Contractor(s) |
RESTEK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6391-94-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03224004 |
| Totals | 1558775.00 | 0.00 | 14461.00 | 0.9 |
|
County | TRAVIS |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN |
To | TRAVIS COUNTY AND HAYS COUNTY |
CSJ | 6396-46-001 |
Proj ID | RMC - 639646001 |
Work Type | REFLECTORIZED PAVEMENT MARKINGS & MARKE |
|
| 0.010 | 425408.58 | | 74021.45 | 17.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 10-03-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 515 |
Percent Time Used | 70 |
Contractor(s) |
D. I. J. CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6396-46-001 LROD ENTERPRISES LLC (12.04)
|
Contract # | 04224209 |
| Totals | 425408.58 | 22303.45 | 74021.45 | 17.4 |
|
County | TRAVIS |
Highway | IH0035 |
From | VARIOUS LOCATIONS |
To | IN THE AUSTIN DISTRICT |
CSJ | 6399-60-001 |
Proj ID | RMC - 639960001 |
Work Type | CONCRETE SPALL REPAIR |
|
| 0.010 | 1723645.00 | | 1606895.08 | 93.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 547 |
Percent Time Used | 74 |
Contractor(s) |
ROY JORGENSEN ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6399-60-001 AARON CONCRETE CONTRACTORS, L.P. (0.00)
|
Contract # | 06224204 |
| Totals | 1723645.00 | 0.00 | 1606895.08 | 93.2 |
|
County | BURNET |
Highway | SH0029 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6404-68-001 |
Proj ID | MMC - 640468001 |
Work Type | LIMESTONE ROCK ASPHALT |
|
| 0.010 | 1812615.00 | | 836030.63 | 46.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 240 |
Working Days Charged | 335 |
Percent Time Used | 93 |
Contractor(s) |
VULCAN CONSTRUCTION MATERIALS, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6404-68-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09224207 |
| Totals | 1812615.00 | 79844.41 | 836030.63 | 46.1 |
|
County | BASTROP |
Highway | US0290 |
From | VARIOUS LOCATIONS IN BASTROP, |
To | CALDWELL, AND LEE COUNTIES |
CSJ | 6405-24-001 |
Proj ID | RMC - 640524001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 2144000.00 | | 1128592.17 | 52.6 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 12-01-22 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 456 |
Percent Time Used | 62 |
Contractor(s) |
BK FIELD OPERATIONS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-24-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 09224208 |
| Totals | 2144000.00 | 119376.00 | 1128592.17 | 52.6 |
|
County | TRAVIS |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6405-28-001 |
Proj ID | RMC - 640528001 |
Work Type | TRAFFIC SIGNAL MAINTENANCE |
|
| 0.010 | 1241630.00 | | 363375.00 | 29.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-03-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 388 |
Percent Time Used | 53 |
Contractor(s) |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11224006 |
| Totals | 1241630.00 | 35850.00 | 363375.00 | 29.2 |
|
County | WILLIAMSON |
Highway | SH0195 |
From | VARIOUS LOCATIONS IN |
To | WILLIAMSON COUNTY |
CSJ | 6405-30-001 |
Proj ID | RMC - 640530001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 510828.00 | | 244968.00 | 47.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-20-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 122 |
Addl Days Granted | 0 |
Working Days Charged | 23 |
Percent Time Used | 18 |
Contractor(s) |
YELLOWSTONE LANDSCAPE - CENTRAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-30-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02234203 |
| Totals | 510828.00 | 112680.00 | 244968.00 | 47.9 |
|
County | WILLIAMSON |
Highway | US0079 |
From | VARIOUS LOCATIONS IN |
To | WILLIAMSON COUNTY |
CSJ | 6405-32-001 |
Proj ID | RMC - 640532001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 413256.45 | | 202693.98 | 49.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-17-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 110 |
Addl Days Granted | 0 |
Working Days Charged | 18 |
Percent Time Used | 16 |
Contractor(s) |
P-VILLE, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6405-32-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12224205 |
| Totals | 413256.45 | 0.00 | 202693.98 | 49.0 |
|
County | TRAVIS |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6405-34-001 |
Proj ID | RMC - 640534001 |
Work Type | INSTALLATION OF TRAFFIC SIGNALS |
|
| 0.010 | 898125.00 | | 806866.07 | 89.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-03-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 298 |
Percent Time Used | 40 |
Contractor(s) |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-34-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02234204 |
| Totals | 898125.00 | 321575.07 | 806866.07 | 89.8 |
|
County | BURNET |
Highway | US0281 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6405-36-001 |
Proj ID | RMC - 640536001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 1515205.00 | | 647967.16 | 42.7 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-10-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 325 |
Percent Time Used | 44 |
Contractor(s) |
BK FIELD OPERATIONS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-36-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 12224206 |
| Totals | 1515205.00 | 43390.90 | 647967.16 | 42.7 |
|
County | BLANCO |
Highway | US0281 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6405-38-001 |
Proj ID | MMC - 640538001 |
Work Type | ASPHALT |
|
| 0.010 | 1738040.00 | | 7851.18 | 0.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-10-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 240 |
Working Days Charged | 326 |
Percent Time Used | 90 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-38-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01234003 |
| Totals | 1738040.00 | 0.00 | 7851.18 | 0.4 |
|
County | TRAVIS |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6405-40-001 |
Proj ID | MMC - 640540001 |
Work Type | ASPHALT |
|
| 0.010 | 1153870.00 | | 58751.60 | 5.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 04-25-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 120 |
Addl Days Granted | 240 |
Working Days Charged | 305 |
Percent Time Used | 84 |
Contractor(s) |
ERGON ASPHALT & EMULSIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-40-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234007 |
| Totals | 1153870.00 | 4352.24 | 58751.60 | 5.0 |
|
County | TRAVIS |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN |
To | TRAVIS AND WILLIAMSON COUNTY |
CSJ | 6405-42-001 |
Proj ID | RMC - 640542001 |
Work Type | METAL BEAM GUARD FENCE REPAIR |
|
| 0.010 | 3044832.00 | | 1019824.00 | 33.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 05-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 305 |
Percent Time Used | 41 |
Contractor(s) |
BK FIELD OPERATIONS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6405-42-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02234006 |
| Totals | 3044832.00 | 132919.40 | 1019824.00 | 33.4 |
|
County | TRAVIS |
Highway | IH0035 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6405-44-001 |
Proj ID | RMC - 640544001 |
Work Type | DEBRIS REMOVAL |
|
| 0.010 | 937598.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 11-01-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 121 |
Percent Time Used | 16 |
Contractor(s) |
T.F.R. ENTERPRISES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-44-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234207 |
| Totals | 937598.00 | 0.00 | 0.00 | 0.0 |
|
County | TRAVIS |
Highway | FM0685 |
From | VARIOUS LOCATIONS IN |
To | THE AUSTIN DISTRICT |
CSJ | 6405-48-001 |
Proj ID | RMC - 640548001 |
Work Type | TRAFFIC SIGNAL MAINTENANCE |
|
| 0.010 | 894172.00 | | 234239.00 | 26.1 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 07-06-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 235 |
Percent Time Used | 32 |
Contractor(s) |
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6405-48-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234008 |
| Totals | 894172.00 | 17495.00 | 234239.00 | 26.1 |
|
County | GILLESPIE |
Highway | US0087 |
From | VARIOUS LOCATIONS IN GILLESPIE, |
To | BLANCO AND LLANO COUNTIES |
CSJ | 6405-50-001 |
Proj ID | RMC - 640550001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 428480.80 | | 214180.40 | 49.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 06-06-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 88 |
Addl Days Granted | 0 |
Working Days Charged | 19 |
Percent Time Used | 21 |
Contractor(s) |
P-VILLE, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6405-50-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03234009 |
| Totals | 428480.80 | 0.00 | 214180.40 | 49.9 |
|