Monthly Local Let Maintenance Report For Beaumont District As Of Feb 10, 2017 Page 1 Of 5

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIBERTY
HighwayFM0770
FromVARIOUS
ToVARIOUS
CSJ6186-01-001
Proj IDEMC - 618601001
Work TypeDEBRIS REMOVAL - LIBERTY CO EAST
 
1.000265644.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-17-08
Work Began09-20-08
Work Completed
Time Computed09-18-08
Contract Working Days21
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NEW BIRTH CLEANING
SUBCONTRACTOR(S) FOR CCSJ: 6186-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09082009
Totals265644.180.000.000.0

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6186-02-001
Proj IDEMC - 618602001
Work Typeemergency debris removal
 
1.000152111.829764.496.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-17-08
Work Began09-18-08
Work Completed
Time Computed09-18-08
Contract Working Days21
Addl Days Granted0
Working Days Charged13
Percent Time Used61
Contractor(s)
NEW BIRTH CLEANING
SUBCONTRACTOR(S) FOR CCSJ: 6186-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09082010
Totals152111.820.009764.496.4

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6192-82-001
Proj IDRMC - 619282001
Work TypeMOWING OF RIGHT OF WAY- BEAUMONT
 
161.000170270.30166250.9097.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-09
Work Began06-08-09
Work Completed
Time Computed06-12-09
Contract Working Days200
Addl Days Granted0
Working Days Charged81
Percent Time Used40
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6192-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04092005
Totals170270.300.00166250.9097.6

CountyJASPER
HighwayUS0190
FromUS190
ToUS190
CSJ6207-02-001
Proj IDSUP - 620702001
Work TypeGROUNDS MAINTENANCE - JASPER
 
1.0005127.962144.1241.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged249
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102011
Totals5127.960.002144.1241.8

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 287
CSJ6207-13-001
Proj IDSUP - 620713001
Work TypeJANITORIAL MAINTENANCE - WOODVILLE
 
1.0004032.004032.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102008
Totals4032.000.004032.0099.9

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 190
CSJ6207-14-001
Proj IDSUP - 620714001
Work TypePICNIC MAINTENANCE - WOODVILLE
 
1.00013440.619773.4372.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days364
Addl Days Granted0
Working Days Charged249
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102009
Totals13440.610.009773.4372.7

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 287
CSJ6207-15-001
Proj IDSUP - 620715001
Work TypeGROUNDS MAINTENANCE - WOODVILLE
 
1.0002911.401674.3657.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-01-10
Work Began03-01-10
Work Completed
Time Computed03-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged250
Percent Time Used68
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6207-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102010
Totals2911.400.001674.3657.5

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6209-45-001
Proj IDSUP - 620945001
Work TypeJANITORIAL MAINTENANCE - ANAHUAC
 
1.0004071.304013.2898.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged254
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6209-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102018
Totals4071.300.004013.2898.5

CountyCHAMBERS
HighwayFM0563
FromFM 563
ToFM 563
CSJ6209-46-001
Proj IDSUP - 620946001
Work TypeGROUNDS MAINTENANCE - ANAHUAC
 
1.0008123.006965.7985.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-10
Work Began04-01-10
Work Completed
Time Computed04-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged253
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6209-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03102015
Totals8123.000.006965.7985.7

CountyLIBERTY
HighwayUS0090
FromVARIOUS LOCATIONS IN LIBERTY AND
ToCHAMBERS COUNTIES
CSJ6232-67-001
Proj IDRMC - 623267001
Work TypeCLEAN AND RESHAPE DITCHES
 
1.000163024.0054792.5550.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-02-12
Work Began07-02-12
Work Completed
Time Computed04-02-12
Contract Working Days51
Addl Days Granted0
Working Days Charged352
Percent Time Used690
Contractor(s)
PARTNER MARIA SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6232-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01122002
Totals163024.000.0054792.5550.4

CountyJEFFERSON
HighwayUS0069
FromUS 69 N
ToUS 69 N
CSJ6237-81-001
Proj IDSUP - 623781001
Work TypeBEAUMONT AO/MO JANITORIAL
 
1.0006779.286136.20100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-12
Work Began02-01-12
Work Completed02-10-13
Time Computed02-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
GOODWILL INDUSTRIES INDUSTRIAL CONTRACTS AND TEMPORARY
SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6237-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12112007
Totals6779.280.006136.20100.0

CountyORANGE
HighwaySH0062
FromVARIOUS
ToVARIOUS
CSJ6239-62-001
Proj IDSUP - 623962001
Work TypeSABINE RIVER AUTH. WATER SEWER
 
1.0001116.601015.3090.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-01-12
Work Began02-01-12
Work Completed
Time Computed01-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged330
Percent Time Used90
Contractor(s)
SABINE RIVER AUTHORITY OF TEXAS
SUBCONTRACTOR(S) FOR CCSJ: 6239-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01122005
Totals1116.600.001015.3090.9

CountyLIBERTY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6246-49-001
Proj IDSUP - 624649001
Work TypeLIBERTY ~ LITTER
 
1.000239756.04236236.2098.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08122006
Totals239756.040.00236236.2098.5

CountyLIBERTY
HighwayUS0090
FromCARTER STREET
ToCARTER STREET
CSJ6268-55-001
Proj IDRMC - 626855001
Work TypeREMOVE ABANDONED RAILROAD TRACKS_US
 
1.00053597.0073511.58100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-11-14
Work Began04-15-14
Work Completed11-10-14
Time Computed04-28-14
Contract Working Days15
Addl Days Granted0
Working Days Charged24
Percent Time Used160
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-55-001
A-1 CONSTRUCTION SERVICES (79.29)
STRIPES & STOPS COMPANY, INC. (6.62)
Contract #03142001
Totals53597.000.0073511.58100.0

CountyJEFFERSON
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6272-57-001
Proj IDSUP - 627257001
Work TypeBEAUMONT ~ LITTER
 
1.000165957.90128100.9177.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-14
Work Began09-01-14
Work Completed
Time Computed09-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6272-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08142003
Totals165957.900.00128100.9177.1

CountyJEFFERSON
HighwaySH0347
FromSH 347
ToSH 347
CSJ6273-23-001
Proj IDSUP - 627323001
Work TypePT ARTHUR ~ JANITORIAL
 
1.0008513.048513.04100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-14
Work Began06-01-14
Work Completed06-15-15
Time Computed06-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
UNITED SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6273-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05142003
Totals8513.040.008513.04100.0

CountyTYLER
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6278-40-001
Proj IDRMC - 627840001
Work TypeWOODVILLE ~ MOWING OF ROW
 
254.000257898.20257557.6199.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-09-15
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted30
Working Days Charged61
Percent Time Used48
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6278-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152001
Totals257898.200.00257557.6199.8

CountyCHAMBERS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6280-67-001
Proj IDRMC - 628067001
Work TypeTREE AND BRUSH REMOVAL
 
1.000232505.00399370.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-14-15
Work Completed06-09-16
Time Computed00-00-00
Contract Working Days60
Addl Days Granted60
Working Days Charged81
Percent Time Used67
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6280-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04152003
Totals232505.000.00399370.00100.0

CountyNEWTON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6282-78-001
Proj IDRMC - 628278001
Work TypeNEWTON ROW MOWING
 
271.000224767.28224717.2899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-24-15
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged31
Percent Time Used32
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6282-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152002
Totals224767.280.00224717.2899.9

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6283-34-001
Proj IDRMC - 628334001
Work TypeBEAUMONT ROW MOWING
 
184.000235834.36300987.5299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-03-15
Work Completed
Time Computed00-00-00
Contract Working Days117
Addl Days Granted0
Working Days Charged56
Percent Time Used47
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03152003
Totals235834.360.00300987.5299.9

page 1 | page 2 | page 3 | page 4 | page 5