Monthly Local Let Maintenance Report For Bryan District As Of Jan 11, 2017 Page 1 Of 5

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWASHINGTON
HighwayMR0688
FromAT BRENHAM STATE SCHOOL
ToAT BRENHAM STATE SCHOOL
CSJ6250-83-001
Proj IDRMC - 625083001
Work TypeSURFACE TREAT PARKING LOTS
 
0.00139379.850.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days4
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6250-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03131701
Totals39379.850.000.000.0

CountyBRAZOS
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6263-25-001
Proj IDRMC - 626325001
Work TypeTREE REMOVAL
 
0.001152345.00112133.0077.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-08-14
Work Began01-08-14
Work Completed
Time Computed01-16-14
Contract Working Days148
Addl Days Granted0
Working Days Charged79
Percent Time Used53
Contractor(s)
HAM-BAR, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6263-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10131704
Totals152345.000.00112133.0077.0

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6263-32-001
Proj IDRMC - 626332001
Work TypeINSTALL/REMOVE RAISED PAVEMENT
 
0.001123000.00109976.0089.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-04-14
Work Began02-06-14
Work Completed
Time Computed02-14-14
Contract Working Days41
Addl Days Granted0
Working Days Charged30
Percent Time Used73
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6263-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10131707
Totals123000.000.00109976.0089.4

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6265-67-001
Proj IDSUP - 626567001
Work TypeLITTER PICKUP
 
0.010285041.42261512.35100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-02-13
Work Began12-02-13
Work Completed12-01-14
Time Computed12-10-13
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6265-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12131733
Totals285041.420.00261512.35100.0

CountyBRAZOS
HighwayFM0974
FromVARIOUS
ToVARIOUS
CSJ6270-66-001
Proj IDSUP - 627066001
Work TypeBUILDING JANITORIAL
 
0.01020201.0417748.09100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-03-14
Work Began03-03-14
Work Completed03-02-15
Time Computed03-03-14
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03141733
Totals20201.040.0017748.09100.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6276-13-001
Proj IDRMC - 627613001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
0.001209000.00121040.3757.9
Work Order01-21-15
Work Began01-21-15
Work Completed
Time Computed01-29-15
Contract Working Days731
Addl Days Granted0
Working Days Charged703
Percent Time Used96
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12141712
Totals209000.000.00121040.3757.9

CountyBURLESON
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6281-50-001
Proj IDSUP - 628150001
Work TypeLITTER PICKUP
 
0.01099797.2895297.2895.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-15-14
Work Began12-15-14
Work Completed
Time Computed12-15-14
Contract Working Days365
Addl Days Granted0
Working Days Charged351
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12141773
Totals99797.280.0095297.2895.4

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6282-02-001
Proj IDRMC - 628202001
Work TypeMBGF & CABLE BARRIER REPAIR
 
0.001198527.00140340.0070.6
Work Order03-31-15
Work Began03-31-15
Work Completed
Time Computed04-08-15
Contract Working Days730
Addl Days Granted0
Working Days Charged634
Percent Time Used86
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6282-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02151701
Totals198527.001348.00140340.0070.6

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6283-71-001
Proj IDRMC - 628371001
Work TypeINSTALL SHORTLINE AND SPECIALTY
 
0.001302355.00183803.6060.7
Work Order04-07-16
Work Began04-07-16
Work Completed
Time Computed04-15-16
Contract Working Days731
Addl Days Granted0
Working Days Charged261
Percent Time Used35
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03151701
Totals302355.000.00183803.6060.7

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6283-72-001
Proj IDRMC - 628372001
Work TypeINSTALL SHORTLINE AND SPECIALTY
 
0.001302468.7548155.5015.9
Work Order10-26-15
Work Began10-26-15
Work Completed
Time Computed11-03-15
Contract Working Days731
Addl Days Granted0
Working Days Charged425
Percent Time Used58
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03151702
Totals302468.754322.0048155.5015.9

CountyWASHINGTON
HighwaySH0105
FromVARIOUS
ToVARIOUS
CSJ6283-73-001
Proj IDRMC - 628373001
Work TypeINSTALL SHORTLINE AND SPECIALTY
 
0.001281720.00158614.2456.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-26-16
Work Began09-24-15
Work Completed
Time Computed02-03-16
Contract Working Days731
Addl Days Granted0
Working Days Charged457
Percent Time Used62
Contractor(s)
ROADSAFE TRAFFIC SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03151703
Totals281720.000.00158614.2456.3

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6285-84-001
Proj IDRMC - 628584001
Work TypeINSTALL/REMOVE RAISED PAVEMENT
 
0.001257399.00128001.9249.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-28-16
Work Began01-05-16
Work Completed
Time Computed01-02-17
Contract Working Days80
Addl Days Granted0
Working Days Charged41
Percent Time Used51
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6285-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151701
Totals257399.000.00128001.9249.7

CountyBRAZOS
HighwaySH0021
FromVARIOUS
ToVARIOUS
CSJ6286-75-001
Proj IDRMC - 628675001
Work TypeTREE REMOVAL
 
0.001340050.00320040.0094.1
Work Order10-13-15
Work Began10-13-15
Work Completed
Time Computed10-21-15
Contract Working Days176
Addl Days Granted8
Working Days Charged182
Percent Time Used98
Contractor(s)
DEVTEX INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151701
Totals340050.0015710.00320040.0094.1

CountyWALKER
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6286-78-001
Proj IDRMC - 628678001
Work TypeTREE REMOVAL
 
0.001214566.00180083.0083.9
Work Order07-30-15
Work Began07-30-15
Work Completed
Time Computed08-07-15
Contract Working Days176
Addl Days Granted0
Working Days Charged137
Percent Time Used77
Contractor(s)
ROY LEE WALKER
SUBCONTRACTOR(S) FOR CCSJ: 6286-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151707
Totals214566.000.00180083.0083.9

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6292-99-001
Proj IDRMC - 629299001
Work TypeROADSIDE MOWING
 
256.700138712.90121935.6387.9
Work Order07-18-16
Work Began07-18-16
Work Completed
Time Computed07-26-16
Contract Working Days45
Addl Days Granted0
Working Days Charged37
Percent Time Used82
Contractor(s)
WELLMANN ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6292-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151701
Totals138712.901885.63121935.6387.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6293-00-001
Proj IDRMC - 629300001
Work TypeROADSIDE MOWING
 
225.457239511.24184846.1677.1
Work Order06-02-16
Work Began06-02-16
Work Completed
Time Computed06-10-16
Contract Working Days70
Addl Days Granted0
Working Days Charged69
Percent Time Used98
Contractor(s)
ANGEL LADY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6293-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151702
Totals239511.240.00184846.1677.1

CountyLEON
HighwayUS0079
FromVARIOUS
ToVARIOUS
CSJ6293-01-001
Proj IDRMC - 629301001
Work TypeROADSIDE MOWING
 
302.900162623.11136573.48100.0
Work Order06-22-16
Work Began06-22-16
Work Completed12-27-16
Time Computed06-30-16
Contract Working Days48
Addl Days Granted0
Working Days Charged29
Percent Time Used60
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6293-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151703
Totals162623.1142342.30136573.48100.0

CountyFREESTONE
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6293-04-001
Proj IDRMC - 629304001
Work TypeROADSIDE MOWING
 
297.500157085.87133616.8485.0
Work Order06-08-16
Work Began06-08-16
Work Completed
Time Computed06-16-16
Contract Working Days46
Addl Days Granted0
Working Days Charged31
Percent Time Used67
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6293-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151706
Totals157085.870.00133616.8485.0

CountyROBERTSON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6293-05-001
Proj IDRMC - 629305001
Work TypeROADSIDE MOWING
 
288.315167840.44140540.4083.7
Work Order05-24-16
Work Began05-24-16
Work Completed
Time Computed06-01-16
Contract Working Days49
Addl Days Granted0
Working Days Charged27
Percent Time Used55
Contractor(s)
LAWRENCE W. SIMS
SUBCONTRACTOR(S) FOR CCSJ: 6293-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151707
Totals167840.440.00140540.4083.7

CountyGRIMES
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6293-08-001
Proj IDRMC - 629308001
Work TypeROADSIDE MOWING
 
278.600137793.90107573.1678.0
Work Order06-30-16
Work Began06-30-16
Work Completed
Time Computed07-08-16
Contract Working Days44
Addl Days Granted0
Working Days Charged12
Percent Time Used27
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6293-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151710
Totals137793.900.00107573.1678.0

page 1 | page 2 | page 3 | page 4 | page 5