Monthly State Let Construction Report For Brownwood District As Of Dec 10, 2014 Page 1 Of 2

Last Update: Wednesday, December 10, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEASTLAND
Highway IH 20
From CALLAHAN C/L
To 2.443 MILES EAST
CSJ 0007-03-087
Proj ID STP 2015(057)HESG
Work Type INSTALL MEDIAN BARRIER
 
2.443 321299.40 194164.00 313347.00 97.5
Work Order 10-09-14
Work Began 10-28-14
Work Completed  
Time Computed 10-22-14
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 14
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-087
ALTUS TRAFFIC MANAGEMENT LLC (1.47%)
JUNIOR CONSTRUCTION COMPANY, INC.( 26.74%)
WOLFE CONSTRUCTION GROUP, INC. (0.43%)
Contract # 09143022
Totals 321299.40 194164.00 313347.00 97.5

CountyEASTLAND
Highway IH 20 ETC
From EAST OVERPASS AT OLDEN
To COLONY CREEK BRIDGE (WESTBOUND)
CSJ 0007-04-120
Proj ID NH 2015(323)
Work Type SEAL COAT
 
104.121 2943828.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-09-14
Work Began 00-00-00
Work Completed  
Time Computed 12-25-14
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-04-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143207
Totals 2943828.19 0.00 0.00 0.0

CountyEASTLAND
Highway IH 20
From AT 0.5 MI. W OF FM 571 AND ALSO AT
To 2.5 MI. W OF SH 16
CSJ 0007-06-070
Proj ID STP 2005(276)TEG
Work Type CONSTRUCT TWO SAFETY REST AREAS
 
3.119 16358386.58 933519.81 13163331.72 80.4
Work Order 01-04-13
Work Began 02-01-13
Work Completed  
Time Computed 01-20-13
Contract Working Days 415
Addl Days Granted 84
Working Days Charged 373
Percent Time Used 74
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES(0.83%)
ABILENE SHEET METAL(1.43%)
CURTIS MECHANICAL CONTRACTORS, INC.(2.10%)
GRIZZLY GLASS & MIRROR, INC. (1.01%)
LONE OAK LANDSCAPE LLC (0.38%)
LONE STAR BARRIER SERVICES, LLC(0.66%)
PEACHTREE CONSTRUCTION, LTD. (4.79%)
SCR CONSTRUCTION CO., INC. (0.18%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42%)
TIPPENN FABRICATION & ERECTION (5.06%)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57%)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53%)
CORPUS CHRISTI STAMP WORKS, INC. (0.05%)
FINLEY TERMITE AND PEST CONTROL, INC.(0.01%)
SOLID ROCK LAWN & LANDSCAPE(0.21%)
TEX OP CONSTRUCTION, LP(0.20%)
GOMEZ FLOOR COVERING, INC. (1.55%)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07%)
B.A.D.J., INC. DBA THE TOPSPOT (0.21%)
WILKS MASONRY CORPORATION(4.34%)
LIBERTY PAINTING & DRYWALL (0.65%)
HUNTER KNEPSHIELD COMPANY(0.73%)
CLLA GROUP, LLC(1.46%)
AMERITEX FLAG & FLAGPOLE, LLC(0.03%)
A & A CONSTRUCTION (0.26%)
LIBERTY PAINTING & DRYWALL (0.65%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.11%)
CONROE WOOD PRODUCTS INC.(0.00%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
SAR TRANSPORTATION, LLC(0.00%)
CHAMPION FUEL SOLUTIONS(0.00%)
Contract # 10123203
Totals 16358386.58 933519.81 13163331.72 80.4

CountyEASTLAND
Highway IH 20
From 4.1 MI. E OF RANGER
To 0.6 MI. W OF SH 16
CSJ 0007-06-086
Proj ID STP 2014(439)SB
Work Type TRAFFIC BARRIER, LIGHTING, STRIPING
 
2.085 2844513.82 20300.00 2986926.56 100.0
Work Order 01-17-14
Work Began 04-01-14
Work Completed 11-05-14
Time Computed 04-01-14
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 74
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-086
BICK"S CONSTRUCTION, INC.( 26.27%)
D. I. J. CONSTRUCTION, INC.(2.23%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.( 15.24%)
INTERMOUNTAIN SLURRY SEAL, INC.(4.64%)
TEX OP CONSTRUCTION, LP(2.17%)
WEST TEXAS RUMBLE STRIP(0.14%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.00%)
AAA DRILLING FOUNDATION CO., INC.(0.35%)
Contract # 12133204
Totals 2844513.82 20300.00 2986926.56 100.0

CountyMCCULLOCH
Highway US 87
From 0.5 MI. WEST OF CR 138
To 0.3 MI. WEST OF US 283
CSJ 0070-06-047
Proj ID NH 2015(340)
Work Type ADD PASSING LANES
 
10.019 2729953.12 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 193
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0070-06-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143226
Totals 2729953.12 0.00 0.00 0.0

CountyBROWN
Highway US 377
From AT CROCKETT DRIVE
To .
CSJ 0128-01-106
Proj ID NH 2015(453)
Work Type CONSTRUCT NEW TRAFFIC SIGNAL
 
0.096 156330.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0128-01-106
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143023
Totals 156330.88 0.00 0.00 0.0

CountyLAMPASAS
Highway US 281
From SULPHUR CREEK BRIDGE
To NEAR CR 4016
CSJ 0251-06-037
Proj ID NH 2015(449)
Work Type CONSTRUCT PEDESTRIAN SIDEWALK
 
0.700 210626.58 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-09-14
Work Began 00-00-00
Work Completed  
Time Computed 12-25-14
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0251-06-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143021
Totals 210626.58 0.00 0.00 0.0

CountyEASTLAND
Highway SH 6
From 4.4 MI. E OF CARBON
To COMANCHE C/L
CSJ 0257-04-025
Proj ID STP 2014(867)
Work Type BASE OVERLAY AND 2 COURSE SURF TRT
 
5.099 3574742.00 0.00 0.00 0.0
CountyCOMANCHE
Highway SH 6
From EASTLAND C/L
To 3.22 MI. E
CSJ 0257-05-044
Proj ID STP 2014(867)
Work Type RECONSTRUCT ROADWAY
 
3.219 1920300.43 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0257-04-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143216
Totals 5495042.43 0.00 0.00 0.0

CountyCOMANCHE
Highway SH 6
From 3.22 MI. E OF EASTLAND C/L
To NEAR SH 16
CSJ 0257-05-042
Proj ID STP 2015(058)
Work Type RECONSTRUCT ROADWAY
 
5.822 3990282.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0257-05-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143214
Totals 3990282.05 0.00 0.00 0.0

CountyEASTLAND
Highway FM 8
From 0.273 MI. E OF FM 2214
To 0.06 MI. W OF HOG CREEK
CSJ 0550-01-023
Proj ID STP 2014(544)
Work Type GRADING, STRS, FLEX BASE, AND SURF
 
0.322 458987.68 0.00 0.00 0.0
CountyEASTLAND
Highway FM 2214
From 0.5 MI E OF FM 571
To FM 8
CSJ 1697-02-019
Proj ID STP 2014(544)
Work Type GRADING, STRS, FLEX BASE AND SURFAC
 
4.701 4840589.80 73600.00 73600.00 1.5
Work Order 08-07-14
Work Began 00-00-00
Work Completed  
Time Computed 12-10-14
Contract Working Days 272
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1697-02-019
MARCOM"S MOWING SERVICE, LLC (0.49%)
NORTH EASTERN PAVERS ( 11.45%)
S & S BRIDGE PAINTING, INC.(0.55%)
TEXAS ALTERNATIVE GRASSER, INC.(0.62%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.37%)
WILLIS ELECTRIC CO., LP(2.05%)
Contract # 05143002
Totals 5299577.48 73600.00 73600.00 1.3

CountyEASTLAND
Highway FM 571
From AT LEON RIVER
To .
CSJ 0570-01-019
Proj ID BR 2015(462)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.133 821742.40 0.00 0.00 0.0
CountyCOMANCHE
Highway CR
From ON CR 435 AT SABANA RIVER
To .
CSJ 0923-17-063
Proj ID BR 2012(743)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.070 379885.40 0.00 0.00 0.0
CountyCOMANCHE
Highway CR
From ON CR 178 AT SABANA RIVER DRAW
To .
CSJ 0923-17-070
Proj ID BR 2014(382)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 134401.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0570-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143211
Totals 1336028.80 0.00 0.00 0.0

CountyBROWN
Highway CS
From MARKETPLACE ROAD IN BROWNWOOD
To US 67/84
CSJ 0923-06-062
Proj ID C 923-6-62
Work Type CONSTRUCT NEW 2 LANE ROADWAY
 
0.644 1394201.67 5600.00 1518591.90 100.0
Work Order 08-02-13
Work Began 08-26-13
Work Completed 10-30-14
Time Computed 09-16-13
Contract Working Days 150
Addl Days Granted 16
Working Days Charged 164
Percent Time Used 98
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-062
D. I. J. CONSTRUCTION, INC.(0.88%)
BEAR CREEK CONSTRUCTION, LLC ( 18.97%)
KARMY CONSTRUCTION INC (4.76%)
TEXAS ALTERNATIVE GRASSER, INC.(0.10%)
HJC FARMS, INC.(0.61%)
WILLIS ELECTRIC CO., LP( 11.78%)
Contract # 06133207
Totals 1394201.67 5600.00 1518591.90 100.0

CountyEASTLAND
Highway CR
From ON CR 107 AT COTTONWOOD CREEK
To .
CSJ 0923-09-052
Proj ID BR 2013(282)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 178335.00 0.00 185831.37 99.9
CountySTEPHENS
Highway CR
From ON CR 187 AT HOG BRANCH
To .
CSJ 0923-22-019
Proj ID BR 2013(763)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 249255.00 0.00 238958.32 95.8
CountySTEPHENS
Highway CR
From ON ELM STREET AT GONZALES DRAW
To .
CSJ 0923-22-020
Proj ID BR 1302(087)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.041 286320.80 25520.00 72962.00 25.4
Work Order 02-19-14
Work Began 03-10-14
Work Completed  
Time Computed 03-07-14
Contract Working Days 150
Addl Days Granted 5
Working Days Charged 115
Percent Time Used 74
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-09-052
CONTRACTORS SERVICE COMPANY(1.18%)
DUSTIN ALLEN, INC. (3.76%)
TEXAS ALTERNATIVE GRASSER, INC.(0.84%)
Contract # 01143007
Totals 713910.80 25520.00 497751.69 69.7

CountyEASTLAND
Highway CS
From ON HUNT ST AT N FORK PALO PINTO CR.
To IN RANGER
CSJ 0923-09-057
Proj ID BR 2014(572)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 310001.00 0.00 24000.00 7.7
CountyEASTLAND
Highway CS
From ON AVENUE A AT N FORK LEON RIVER
To .
CSJ 0923-09-061
Proj ID BR 2013(965)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 217300.00 30115.75 224567.34 99.9
CountyCOMANCHE
Highway CR
From ON CR 103 AT SWEETWATER DRAW
To .
CSJ 0923-17-069
Proj ID BR 2013(980)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 207941.00 20196.00 50396.00 24.2
Work Order 05-29-14
Work Began 08-04-14
Work Completed  
Time Computed 07-28-14
Contract Working Days 145
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 49
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-09-061
CONTRACTORS SERVICE COMPANY(1.55%)
ODUM SERVICES, L.P.(3.64%)
TEXAS ALTERNATIVE GRASSER, INC.(0.85%)
LONE STAR HIGHWAY PRODUCTS, INC. (4.39%)
Contract # 04143212
Totals 735242.00 50311.75 298963.34 40.6

CountyCOMANCHE
Highway CR
From ON CR 396 AT ROCKY CREEK
To .
CSJ 0923-17-060
Proj ID BR 2012(740)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 199765.10 0.00 198581.35 100.0
CountyCOMANCHE
Highway CR
From ON CR 396 AT ROCKY CREEK
To .
CSJ 0923-17-072
Proj ID BR 2012(741)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 216177.60 0.00 218297.60 100.0
CountyCOMANCHE
Highway CR
From ON CR 392 AT LEON RIVER
To .
CSJ 0923-17-073
Proj ID BR 2013(764)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.151 660018.00 6860.00 657382.25 100.0
Work Order 11-14-13
Work Began 01-06-14
Work Completed 10-31-14
Time Computed 02-12-14
Contract Working Days 180
Addl Days Granted 10
Working Days Charged 177
Percent Time Used 93
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-17-073
CONTRACTORS SERVICE COMPANY(1.06%)
ODUM SERVICES, L.P.(3.71%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
Contract # 08133017
Totals 1075960.70 6860.00 1074261.20 100.0

CountyCOMANCHE
Highway CR
From CR 250 AT LIVE OAK CREEK
To .
CSJ 0923-17-065
Proj ID BR 2014(438)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.068 275692.59 122110.59 226220.59 82.0
CountyCOMANCHE
Highway CR
From ON CR 175 AT PARTRIDGE CREEK
To .
CSJ 0923-17-067
Proj ID BR 2014(437)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.049 234140.72 89940.22 181705.22 77.6
CountyCOMANCHE
Highway CR
From ON CR 4980 AT LEON RIVER DRAW
To .
CSJ 0923-17-071
Proj ID BR 2014(385)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.052 174227.88 0.00 9315.00 5.3
Work Order 07-25-14
Work Began 09-30-14
Work Completed  
Time Computed 09-30-14
Contract Working Days 147
Addl Days Granted 0
Working Days Charged 38
Percent Time Used 25
Contractor(s)
PIERCE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-17-065
ALTUS TRAFFIC MANAGEMENT LLC (1.47%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.52%)
ODUM SERVICES, L.P.(5.50%)
Contract # 06143013
Totals 684061.19 212050.81 417240.81 60.9

CountyMILLS
Highway CR
From ON CR 433 AT COLORADO RIVER
To .
CSJ 0923-23-025
Proj ID BR 2013(776)
Work Type REHAB STRUCTURE
 
0.076 1045171.90 1530.00 354083.00 33.8
Work Order 01-30-14
Work Began 08-19-14
Work Completed  
Time Computed 08-19-14
Contract Working Days 68
Addl Days Granted 12
Working Days Charged 9
Percent Time Used 11
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-23-025
S & S BRIDGE PAINTING, INC.( 34.06%)
Contract # 11133013
Totals 1045171.90 1530.00 354083.00 33.8

CountyMILLS
Highway CS
From CITY BLOCK CONTAINED WITHIN US 183
To AND 2ND ST, PARKER ST, AND THIRD ST
CSJ 0923-23-026
Proj ID STP 2011(218)TE
Work Type TRANSPORTATION ENHANCEMENT
 
0.100 1314183.65 117699.90 958676.73 72.9
Work Order 10-08-13
Work Began 12-02-13
Work Completed  
Time Computed 12-03-13
Contract Working Days 235
Addl Days Granted 10
Working Days Charged 223
Percent Time Used 91
Contractor(s)
ZIMMERMAN CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-23-026
ABC EROSION CONTROL, INC.(0.14%)
ALLIANCE GLASS & MIRROR, LTD (6.49%)
BARR ROOFING COMPANY (4.52%)
BEST PEST CONTROL(0.03%)
CONCRETE WORX(0.48%)
GRANT GOSS CONTRACTING, INC(2.22%)
HEART OF TEXAS MECHANICAL CONTRACTING, L.L.C.(5.00%)
JORDAN CONSTRUCTION, INC., (3.51%)
KANTEX CONSTRUCTION, LLC (2.87%)
KENNETH CATTLES CONSTRUCTION ( 22.60%)
LOOKING OUT DESIGN, LLC(1.36%)
KARL OESTREICH (0.82%)
STRIPE-RITE(0.16%)
WESLEY CROW ELECTRIC, INC.,(9.34%)
GK CONSTRUCTION, LLC (2.05%)
ARRON SANDERS CONSTRUCTION (0.25%)
Contract # 07133214
Totals 1314183.65 117699.90 958676.73 72.9

CountyMILLS
Highway CR
From ON CR 272 AT WASHBOARD CREEK
To .
CSJ 0923-23-027
Proj ID BR 2013(963)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 248488.40 800.00 252474.50 99.9
CountyMILLS
Highway CR
From ON CR 549 AT POMPEY CREEK
To .
CSJ 0923-23-028
Proj ID BR 2013(964)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 352805.50 0.00 358806.87 99.9
Work Order 05-22-14
Work Began 07-21-14
Work Completed  
Time Computed 06-07-14
Contract Working Days 119
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 73
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0923-23-027
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.31%)
RICE ENVIRONMENTAL SERVICES(6.80%)
SAN-ANN-CO., INC.(0.91%)
Contract # 04143223
Totals 601293.90 800.00 611281.37 99.9

CountyMCCULLOCH
Highway CR
From ON CR 214 AT SAN SABA RIVER
To .
CSJ 0923-24-014
Proj ID BR 2013(824)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 659680.59 0.00 651979.32 98.8
CountyMCCULLOCH
Highway SH 71
From AT SAN SABA RIVER
To .
CSJ 1102-01-039
Proj ID BR 2013(825)
Work Type WIDEN BRIDGE AND APPROACHES
 
0.226 3536720.83 13863.96 1405921.71 39.7
CountyMCCULLOCH
Highway SH 71
From AT TIGER CREEK
To .
CSJ 1102-01-040
Proj ID BR 2013(825)
Work Type WIDEN BRIDGE AND APPROACHES
 
0.094 845670.30 1674.00 796200.98 94.1
CountyMCCULLOCH
Highway SH 71
From NEAR FM 2309
To .2 MI. S OF CR 220
CSJ 1102-01-041
Proj ID STP 2013(265)
Work Type WDN SUBGRADE, STR, SURFACE
 
10.699 7626706.07 322331.91 3543917.28 46.4
Work Order 10-24-13
Work Began 01-21-14
Work Completed  
Time Computed 02-14-14
Contract Working Days 575
Addl Days Granted 0
Working Days Charged 199
Percent Time Used 34
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1102-01-041
COPPELL CONSTRUCTION CO., INC. ( 30.07%)
D. I. J. CONSTRUCTION, INC.(1.59%)
HJC FARMS, INC.(2.11%)
J & M CONTRACTING, COMPANY (5.46%)
RICE ENVIRONMENTAL SERVICES(0.40%)
TEXAS ALTERNATIVE GRASSER, INC.(0.32%)
WILLIS ELECTRIC CO., LP(0.91%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.60%)
S & S BRIDGE PAINTING, INC.(0.66%)
GIBSON & ASSOCIATES, INC.(0.81%)
MESA ROD BUSTERS, INC. (0.06%)
Contract # 07133245
Totals 12668777.79 337869.87 6398019.29 50.5

page 1 | page 2