Monthly State Let Construction Report For Brownwood District As Of Feb 10, 2017 Page 1 Of 2

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyEASTLAND
HighwayIH 20
FromAT 0.5 MI. W OF FM 571 AND ALSO AT
To2.5 MI. W OF SH 16
CSJ0007-06-070
Proj IDSTP 2005(276)TEG
Work TypeCONSTRUCT TWO SAFETY REST AREAS
 
3.11916358386.5816466163.6299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-04-13
Work Began02-01-13
Work Completed
Time Computed01-20-13
Contract Working Days415
Addl Days Granted180
Working Days Charged628
Percent Time Used105
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES (0.83)
ABILENE SHEET METAL (1.43)
CURTIS MECHANICAL CONTRACTORS, INC. (2.10)
GRIZZLY GLASS & MIRROR, INC. (1.01)
LONE OAK LANDSCAPE LLC (0.38)
LONE STAR BARRIER SERVICES, LLC (0.66)
PEACHTREE CONSTRUCTION, LTD. (4.79)
SCR CONSTRUCTION CO., INC. (0.18)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42)
TIPPENN FABRICATION & ERECTION (5.06)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53)
CORPUS CHRISTI STAMP WORKS, INC. (0.05)
FINLEY TERMITE AND PEST CONTROL, INC. (0.01)
SOLID ROCK LAWN & LANDSCAPE (0.21)
TEX OP CONSTRUCTION, LP (0.20)
GOMEZ FLOOR COVERING, INC. (1.55)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07)
B.A.D.J., INC. DBA THE TOPSPOT (0.21)
WILKS MASONRY CORPORATION (4.34)
LIBERTY PAINTING & DRYWALL (0.65)
HUNTER KNEPSHIELD COMPANY (0.73)
CLLA GROUP, LLC (1.46)
AMERITEX FLAG & FLAGPOLE, LLC (0.03)
A & A CONSTRUCTION (0.26)
LIBERTY PAINTING & DRYWALL (0.65)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.11)
CONROE WOOD PRODUCTS INC. (0.00)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00)
SAR TRANSPORTATION, LLC (0.00)
CHAMPION FUEL SOLUTIONS (0.00)
Contract #10123203
Totals16358386.580.0016466163.6299.9

CountySTEPHENS
HighwayUS 180
From0.47 MI. E OF SHACKELFORD C/L
To0.77 MI. E OF FM 3201
CSJ0011-07-047
Proj IDSTP 1302(081)
Work TypeBASE OVERLAY,2CST,ADD PASSING LANES
 
4.4524046707.372844824.2070.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-03-16
Work Began04-04-16
Work Completed
Time Computed00-00-00
Contract Working Days175
Addl Days Granted7
Working Days Charged165
Percent Time Used90
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-047
CONTRACTORS SERVICE COMPANY (0.45)
MARCOM"S MOWING SERVICE, LLC (1.03)
STRIPING TECHNOLOGY, L.P. (2.46)
W.S. CONSTRUCTION COMPANY (5.18)
STRIPING SYSTEMS, INC. (0.03)
Contract #11153222
Totals4046707.370.002844824.2070.2

CountySTEPHENS
HighwayUS 180
FromGONZALES CREEK
ToFM 287
CSJ0011-08-026
Proj IDSTP 1602(051)
Work TypeRECONSTRUCT URBAN ROADWAY
 
5.12913412991.583063568.0722.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-11-16
Work Began09-15-16
Work Completed
Time Computed00-00-00
Contract Working Days459
Addl Days Granted6
Working Days Charged74
Percent Time Used15
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-08-026
CHEROKEE SERVICES (0.17)
D. I. J. CONSTRUCTION, INC. (1.17)
GIBSON & ASSOCIATES, INC. (0.66)
HJC FARMS, INC. (0.63)
J&M CONTRACTING COMPANY (14.52)
PENHALL COMPANY (0.08)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.49)
WILLIS ELECTRIC CO., LP (2.37)
FAMBRO CONSTRUCTION, INC. (12.03)
NELSON INDUSTRIAL SERVICES, INC. (0.05)
Contract #05163002
Totals13412991.580.003063568.0722.8

CountyCOLEMAN ETC
HighwayUS 67 ETC
FromBROWN C/L
To0.1 MI. N OF US 67
CSJ0054-04-107
Proj IDNH 2017(262)
Work TypeSEAL COAT
 
203.0676367226.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-07-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11163026
Totals6367226.540.000.000.0

CountyBROWN
HighwayUS 67
From0.5 MI. W OF FM 3254
ToCR 152
CSJ0054-06-097
Proj IDNH 2017(369)
Work TypeREHABILITATE EXISTING ROADWAY
 
3.0553342055.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days68
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0054-06-097
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173010
Totals3342055.980.000.000.0

CountyBROWN
HighwayUS 84
FromAT FT. WORTH & WESTERN RAILROAD
To.
CSJ0054-07-069
Proj IDSTP 1302(079)RGS
Work TypeRAILROAD BRIDGE REPLACEMENT
 
0.5208488149.702374453.6027.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-16
Work Began09-07-16
Work Completed
Time Computed00-00-00
Contract Working Days400
Addl Days Granted0
Working Days Charged81
Percent Time Used20
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-069
GRANBURY EXCAVATING, INC. (24.57)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.86)
TEXAS SHAFTS, INC. (4.37)
Contract #02163207
Totals8488149.700.002374453.6027.9

CountyCOLEMAN
HighwayUS 67
FromSH 206
To.584 MI W OF CR 368
CSJ0078-03-055
Proj IDSTP 2017(457)HES
Work TypeIMPRV GR, SFT TREAT OBJECTS, ADD PA
 
8.2471678694.190.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0078-03-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173215
Totals1678694.190.000.000.0

CountyEASTLAND
HighwayUS 183
From0.599 MI. N
ToBROWN C/L
CSJ0127-02-140
Proj IDSTP 2015(785)
Work TypeADD PASSING LANES
 
0.246113364.1385690.5075.5
CountyBROWN
HighwayUS 183
FromEASTLAND C/L
ToFM 1467
CSJ0127-03-031
Proj IDSTP 2015(785)
Work TypeADD PASSING LANES
 
7.8862377048.461485664.5565.3
CountyBROWN
HighwayUS 183
FromFM 1467
To3.6 MI N OF US 67(NEAR BWD AIRPORT)
CSJ0127-04-032
Proj IDSTP 1502(143)HES
Work TypeADD PASSING LANES
 
2.9851788921.691404453.7278.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-15
Work Began12-15-15
Work Completed
Time Computed00-00-00
Contract Working Days168
Addl Days Granted0
Working Days Charged237
Percent Time Used141
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-02-140
D. I. J. CONSTRUCTION, INC. (3.35)
TEXAS ALTERNATIVE GRASSER, INC. (0.29)
HJC FARMS, INC. (1.37)
NORTH EASTERN PAVERS (23.51)
RAMBO CONTRACTING, INC. (3.20)
TEXOP CONSTRUCTION (0.84)
Contract #04153259
Totals4279334.280.002975808.7771.1

CountySAN SABA
HighwayFM 580
FromUS 190
ToLAMPASAS C/L
CSJ0231-14-017
Proj IDSTP 2015(389)HES
Work TypeADD'L PAVED SURF WIDTH, WDN STRS
 
14.1445387952.964733841.8387.8
Work Order03-13-15
Work Began06-23-15
Work Completed
Time Computed06-11-15
Contract Working Days474
Addl Days Granted0
Working Days Charged341
Percent Time Used71
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0231-14-017
D. I. J. CONSTRUCTION, INC. (2.05)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.37)
PRIMATE CONSTRUCTION, INC. (0.14)
ROADWAY SPECIALTIES, INC. (4.88)
SAN-ANN-CO., INC. (0.99)
TEXAS ALTERNATIVE GRASSER, INC. (0.47)
BROCK CONSTRUCTION, LLC (0.30)
Contract #01153225
Totals5387952.96291140.974733841.8387.8

CountyEASTLAND
HighwaySH 6
From4.4 MI. E OF CARBON
ToCOMANCHE C/L
CSJ0257-04-025
Proj IDSTP 2014(867)
Work TypeBASE OVERLAY AND 2 COURSE SURF TRT
 
5.0993574742.003836622.2499.9
CountyCOMANCHE
HighwaySH 6
FromEASTLAND C/L
To3.22 MI. E
CSJ0257-05-044
Proj IDSTP 2014(867)
Work TypeRECONSTRUCT ROADWAY
 
3.2191920300.437433.800.3
Work Order02-05-15
Work Began03-16-15
Work Completed
Time Computed04-06-15
Contract Working Days203
Addl Days Granted42
Working Days Charged269
Percent Time Used109
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0257-04-025
NORTHEASTERN PAVERS, INC. (23.73)
TEXAS ALTERNATIVE GRASSER, INC. (0.26)
HJC FARMS, INC. (0.67)
STRIPING TECHNOLOGY, L.P. (2.67)
Contract #07143216
Totals5495042.43153640.663844056.0470.4

CountyMCCULLOCH
HighwayUS 190
FromUS 377
ToSAN SABA C/L
CSJ0272-01-031
Proj IDSTP 2016(924)HES
Work TypeUPGRADE GUARDRAIL & SFTY TREAT STRS
 
17.1741084525.50888094.3081.8
CountySAN SABA
HighwayFM 45
FromMILLS C/L
ToRICHLAND SPRINGS NORTH CITY LIMIT
CSJ0480-08-023
Proj IDSTP 2016(925)HRR
Work TypeUPGRADE GUARDRAIL & SFTY TREAT STRS
 
12.071714070.0080000.0011.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-16
Work Began08-08-16
Work Completed
Time Computed00-00-00
Contract Working Days230
Addl Days Granted0
Working Days Charged106
Percent Time Used46
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0272-01-031
ODUM SERVICES, L.P. (19.21)
Contract #04163025
Totals1798595.500.00968094.3053.8

CountyMILLS
HighwaySH 16
From.021 MI SW OF BARROW ST
ToSAN SABA COUNTY LINE
CSJ0289-03-026
Proj IDSTP 2017(445)HES
Work TypeIMPRV GR, SFT TREAT FIXED, ADD PASS
 
9.2411203835.850.000.0
CountyBURNET
HighwayFM 1478
FromLAMPASAS C/L
To7.096 MI. S OF LAMPASAS C/L
CSJ2206-02-006
Proj IDSTP 2017(471)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
7.096353795.020.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days187
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0289-03-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01173213
Totals1557630.870.000.000.0

CountyMILLS
HighwayFM 45
FromBROWN C/L
ToSAN SABA C/L
CSJ0480-07-009
Proj IDSTP 1602(052)
Work TypeGRADING, STRUCTURES, BASE, AND SURF
 
4.3624563803.881462958.0232.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-20-16
Work Began09-06-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged72
Percent Time Used28
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0480-07-009
D.I.J. CONSTRUCTION, INC (1.28)
TEXAS ALTERNATIVE GRASSER, INC. (0.60)
HJC FARMS, INC. (0.95)
J&M CONTRACTING COMPANY (14.23)
Contract #05163004
Totals4563803.880.001462958.0232.0

CountyEASTLAND
HighwayFM 8
From0.273 MI. E OF FM 2214
To0.06 MI. W OF HOG CREEK
CSJ0550-01-023
Proj IDSTP 2014(544)
Work TypeGRADING, STRS, FLEX BASE, AND SURF
 
0.322458987.68210072.1245.7
CountyEASTLAND
HighwayFM 2214
From0.5 MI E OF FM 571
ToFM 8
CSJ1697-02-019
Proj IDSTP 2014(544)
Work TypeGRADING, STRS, FLEX BASE AND SURFAC
 
4.7014840589.805272278.8599.9
Work Order08-07-14
Work Began01-06-15
Work Completed
Time Computed12-10-14
Contract Working Days272
Addl Days Granted31
Working Days Charged401
Percent Time Used132
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0550-01-023
MARCOM"S MOWING SERVICE, LLC (0.49)
NORTH EASTERN PAVERS (11.45)
S & S BRIDGE PAINTING, INC. (0.55)
TEXAS ALTERNATIVE GRASSER, INC. (0.62)
TOTAL HIGHWAY MAINTENANCE, LLC (1.37)
WILLIS ELECTRIC CO., LP (2.05)
SHINN & GREGORY, INC. (0.48)
EROSION CONTROL MANAGEMENT SERVICES (0.61)
ELLIS-MCGINNIS CONSTRUCTION CO. (3.96)
D.I.J. CONSTRUCTION, INC (0.30)
Contract #05143002
Totals5299577.48153240.315482350.9799.9

CountyEASTLAND
HighwayFM 2461
FromIH 20
ToFM 2214
CSJ0714-05-018
Proj IDSTP 2015(836)HES
Work TypeUPGRADE GUARDRAIL & SFTY TREAT STRS
 
8.435444021.50492025.3099.9
CountyEASTLAND
HighwayFM 2461
FromIH 20
ToFM 2214
CSJ0714-05-020
Proj IDSTP 2015(835)
Work TypeREHABILITATION OF EXISTING ROADWAY
 
8.4351998843.111975660.5199.9
Work Order05-21-15
Work Began06-30-15
Work Completed
Time Computed06-21-15
Contract Working Days238
Addl Days Granted5
Working Days Charged296
Percent Time Used121
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0714-05-018
D.I.J. CONSTRUCTION, INC (3.58)
MARCOM"S MOWING SERVICE, LLC (3.62)
NORTHEASTERN PAVERS, INC. (20.91)
TEXAS ALTERNATIVE GRASSER, INC. (0.26)
LUZ LERMA CONSTRUCTION, INC. (5.28)
Contract #04153011
Totals2442864.610.002467685.8199.9

CountyBROWN
HighwayCR
FromON CR 225 AT CLEAR CREEK
To.
CSJ0923-06-056
Proj IDBR 2015(387)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100603204.63377823.3962.6
CountyBROWN
HighwayCR
FromON CR 258 AT DOUDLE CREEK
To.
CSJ0923-06-070
Proj IDBR 2015(388)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100416710.32392062.5094.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-02-16
Work Began09-06-16
Work Completed
Time Computed00-00-00
Contract Working Days143
Addl Days Granted0
Working Days Charged86
Percent Time Used60
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-056
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.69)
JB FARM & RANCH (17.76)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.90)
WOLFE CONSTRUCTION GROUP, INC. (0.48)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.70)
Contract #04163217
Totals1019914.950.00769885.8975.4

CountyBROWN
HighwayCR
FromON CR 334 AT SALT CREEK
To.
CSJ0923-06-071
Proj IDBR 2016(004)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100404729.68161860.5839.9
CountyBROWN
HighwayCR
FromON CR 121 AT TURKEY CREEK
To.
CSJ0923-06-072
Proj IDBR 2016(258)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100401041.38391118.4897.5
CountyBROWN
HighwayCR
FromON CR 291 AT BLANKET CREEK
To.
CSJ0923-06-073
Proj IDBR 2016(005)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100343043.52339264.7598.8
CountyBROWN
HighwayFM 3021
From0.8 MI. E OF SH 279
To0.9 MI. E OF SH 279
CSJ3102-01-008
Proj IDSTP 2016(926)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
0.100132695.39132843.7399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-02-16
Work Began07-05-16
Work Completed
Time Computed00-00-00
Contract Working Days183
Addl Days Granted5
Working Days Charged133
Percent Time Used70
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-071
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.50)
MCL CONTRACTING, LLC (0.54)
FOUNDATION DRILLERS, INC. (3.58)
Contract #04163034
Totals1281509.970.001025087.5479.9

CountyCOMANCHE
HighwayCR
FromON CR 403 AT DRAW
To.
CSJ0923-17-076
Proj IDBR 2015(346)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100217652.00133056.0061.1
CountyCOMANCHE
HighwayCR
FromON CR 304 AT INDIAN CREEK
To.
CSJ0923-17-078
Proj IDBR 2016(003)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100568174.5064190.0011.2
CountyCOMANCHE
HighwayFM 1689
FromAT WALNUT CREEK
To.
CSJ1033-04-021
Proj IDBR 1602(572)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100994764.15249980.0025.1
CountyCOMANCHE
HighwayFM 1477
FromAT N COPPERAS CREEK
To.
CSJ1366-01-009
Proj IDBR 1602(573)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100684261.2048020.007.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-16
Work Began12-07-16
Work Completed
Time Computed00-00-00
Contract Working Days264
Addl Days Granted0
Working Days Charged32
Percent Time Used12
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 0923-17-076
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.69)
ODUM SERVICES, L.P. (2.90)
PEACHTREE CONSTRUCTION, LTD. (3.50)
STRIPE-A-ZONE, INC. (0.53)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
Contract #08163217
Totals2464851.850.00495246.0020.0

CountyMILLS
HighwayCR
FromON CR 333 AT BENNETT CREEK.
To.
CSJ0923-23-014
Proj IDBR 96(274)OX
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100363760.4087994.0024.1
CountySAN SABA
HighwayCR
FromON CR 236 AT RICHLAND CREEK
To.
CSJ0923-25-020
Proj IDBR 2007(630)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100604350.40368147.4060.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-30-16
Work Began09-19-16
Work Completed
Time Computed00-00-00
Contract Working Days102
Addl Days Granted0
Working Days Charged73
Percent Time Used71
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-23-014
DALLAS LITE AND BARRICADE INC. (0.52)
MORRIS COUNTY CONTRACTORS, L.L.C. (3.79)
PRIMATE CONSTRUCTION, INC. (0.75)
Contract #05163225
Totals968110.800.00456141.4047.1

CountyMCCULLOCH
HighwayCR
FromON CR 214 AT SAN SABA RIVER
To.
CSJ0923-24-014
Proj IDBR 2013(824)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.100659680.59705277.2199.9
CountyMCCULLOCH
HighwaySH 71
FromAT SAN SABA RIVER
To.
CSJ1102-01-039
Proj IDBR 2013(825)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.2263536720.833848264.4099.9
CountyMCCULLOCH
HighwaySH 71
FromAT TIGER CREEK
To.
CSJ1102-01-040
Proj IDBR 2013(825)
Work TypeWIDEN BRIDGE AND APPROACHES
 
0.094845670.30976971.0899.9
CountyMCCULLOCH
HighwaySH 71
FromNEAR FM 2309
To.2 MI. S OF CR 220
CSJ1102-01-041
Proj IDSTP 2013(265)
Work TypeWDN SUBGRADE, STR, SURFACE
 
10.6997626706.076398101.7183.8
Work Order10-24-13
Work Began01-21-14
Work Completed
Time Computed02-14-14
Contract Working Days575
Addl Days Granted7
Working Days Charged549
Percent Time Used94
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-24-014
COPPELL CONSTRUCTION CO., INC. (30.07)
D. I. J. CONSTRUCTION, INC. (1.59)
HJC FARMS, INC. (2.11)
J & M CONTRACTING, COMPANY (5.46)
RICE ENVIRONMENTAL SERVICES (0.40)
TEXAS ALTERNATIVE GRASSER, INC. (0.32)
WILLIS ELECTRIC CO., LP (0.91)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.60)
S & S BRIDGE PAINTING, INC. (0.66)
GIBSON & ASSOCIATES, INC. (0.81)
MESA ROD BUSTERS, INC. (0.06)
Contract #07133245
Totals12668777.7963638.0311928614.4094.1

page 1 | page 2