Monthly State Let Construction Report For Brownwood District As Of Jan 11, 2017 Page 1 Of 2

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEASTLAND
Highway IH 20
From AT IH 20
To .
CSJ 0007-04-113
Proj ID CC 7-4-113
Work Type CRASH WALLS
 
0.100 278879.60 0.00 239326.50 85.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-16
Work Began 10-11-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 86
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-04-113
CONTRACTORS SERVICE COMPANY(4.41%)
TOTAL HIGHWAY MAINTENANCE, LLC (5.24%)
W.O.E. CONSTRUCTION( 33.09%)
ALLIED CORING & CUTTING, LLC (2.49%)
Contract # 07163239
Totals 278879.60 0.00 239326.50 85.8

CountyEASTLAND
Highway IH 20
From AT 0.5 MI. W OF FM 571 AND ALSO AT
To 2.5 MI. W OF SH 16
CSJ 0007-06-070
Proj ID STP 2005(276)TEG
Work Type CONSTRUCT TWO SAFETY REST AREAS
 
3.119 16358386.58 0.00 16466163.62 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-04-13
Work Began 02-01-13
Work Completed  
Time Computed 01-20-13
Contract Working Days 415
Addl Days Granted 180
Working Days Charged 628
Percent Time Used 105
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES(0.83%)
ABILENE SHEET METAL(1.43%)
CURTIS MECHANICAL CONTRACTORS, INC.(2.10%)
GRIZZLY GLASS & MIRROR, INC. (1.01%)
LONE OAK LANDSCAPE LLC (0.38%)
LONE STAR BARRIER SERVICES, LLC(0.66%)
PEACHTREE CONSTRUCTION, LTD. (4.79%)
SCR CONSTRUCTION CO., INC. (0.18%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42%)
TIPPENN FABRICATION & ERECTION (5.06%)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57%)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53%)
CORPUS CHRISTI STAMP WORKS, INC. (0.05%)
FINLEY TERMITE AND PEST CONTROL, INC.(0.01%)
SOLID ROCK LAWN & LANDSCAPE(0.21%)
TEX OP CONSTRUCTION, LP(0.20%)
GOMEZ FLOOR COVERING, INC. (1.55%)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07%)
B.A.D.J., INC. DBA THE TOPSPOT (0.21%)
WILKS MASONRY CORPORATION(4.34%)
LIBERTY PAINTING & DRYWALL (0.65%)
HUNTER KNEPSHIELD COMPANY(0.73%)
CLLA GROUP, LLC(1.46%)
AMERITEX FLAG & FLAGPOLE, LLC(0.03%)
A & A CONSTRUCTION (0.26%)
LIBERTY PAINTING & DRYWALL (0.65%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.11%)
CONROE WOOD PRODUCTS INC.(0.00%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
SAR TRANSPORTATION, LLC(0.00%)
CHAMPION FUEL SOLUTIONS(0.00%)
Contract # 10123203
Totals 16358386.58 0.00 16466163.62 99.9

CountySTEPHENS
Highway US 180
From 0.47 MI. E OF SHACKELFORD C/L
To 0.77 MI. E OF FM 3201
CSJ 0011-07-047
Proj ID STP 1302(081)
Work Type BASE OVERLAY, 2CST, ADD PASSING LANES
 
4.452 4046707.37 0.00 2489084.14 61.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-03-16
Work Began 04-04-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 175
Addl Days Granted 7
Working Days Charged 147
Percent Time Used 80
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-07-047
CONTRACTORS SERVICE COMPANY(0.45%)
MARCOM"S MOWING SERVICE, LLC (1.03%)
STRIPING TECHNOLOGY, L.P.(2.46%)
W.S. CONSTRUCTION COMPANY(5.18%)
STRIPING SYSTEMS, INC. (0.03%)
Contract # 11153222
Totals 4046707.37 0.00 2489084.14 61.5

CountySTEPHENS
Highway US 180
From GONZALES CREEK
To FM 287
CSJ 0011-08-026
Proj ID STP 1602(051)
Work Type RECONSTRUCT URBAN ROADWAY
 
5.129 13412991.58 0.00 2621198.93 19.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-11-16
Work Began 09-15-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 459
Addl Days Granted 6
Working Days Charged 57
Percent Time Used 12
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-08-026
CHEROKEE SERVICES(0.17%)
D. I. J. CONSTRUCTION, INC.(1.17%)
GIBSON & ASSOCIATES, INC.(0.66%)
HJC FARMS, INC.(0.63%)
J&M CONTRACTING COMPANY( 14.52%)
PENHALL COMPANY(0.08%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.49%)
WILLIS ELECTRIC CO., LP(2.37%)
FAMBRO CONSTRUCTION, INC.( 12.03%)
NELSON INDUSTRIAL SERVICES, INC. (0.05%)
Contract # 05163002
Totals 13412991.58 0.00 2621198.93 19.5

CountyCOLEMAN
Highway US 67 ETC
From BROWN C/L
To 0.1 MI. N OF US 67
CSJ 0054-04-107
Proj ID NH 2017(262)
Work Type SEAL COAT
 
203.067 6367226.54 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163026
Totals 6367226.54 0.00 0.00 0.0

CountyBROWN
Highway US 67
From 0.5 MI. W OF FM 3254
To CR 152
CSJ 0054-06-097
Proj ID NH 2017(369)
Work Type REHABILITATE EXISTING ROADWAY
 
3.055 3342055.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0054-06-097
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01173010
Totals 3342055.98 0.00 0.00 0.0

CountyBROWN
Highway US 84
From AT FT. WORTH & WESTERN RAILROAD
To .
CSJ 0054-07-069
Proj ID STP 1302(079)RGS
Work Type RAILROAD BRIDGE REPLACEMENT
 
0.520 8488149.70 0.00 1957228.30 23.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-10-16
Work Began 09-07-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 400
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 17
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-069
GRANBURY EXCAVATING, INC.( 24.57%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.30%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.86%)
TEXAS SHAFTS, INC. (4.37%)
Contract # 02163207
Totals 8488149.70 0.00 1957228.30 23.0

CountyCOLEMAN
Highway US 67
From SH 206
To .584 MI W OF CR 368
CSJ 0078-03-055
Proj ID STP 2017(457)HES
Work Type IMPRV GR, SFT TREAT OBJECTS, ADD PA
 
8.247 1678694.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0078-03-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01173215
Totals 1678694.19 0.00 0.00 0.0

CountyEASTLAND
Highway US 183
From 0.599 MI. N
To BROWN C/L
CSJ 0127-02-140
Proj ID STP 2015(785)
Work Type ADD PASSING LANES
 
0.246 113364.13 0.00 81133.00 71.5
CountyBROWN
Highway US 183
From EASTLAND C/L
To FM 1467
CSJ 0127-03-031
Proj ID STP 2015(785)
Work Type ADD PASSING LANES
 
7.886 2377048.46 0.00 1381044.55 60.5
CountyBROWN
Highway US 183
From FM 1467
To 3.6 MI N OF US 67(NEAR BWD AIRPORT)
CSJ 0127-04-032
Proj ID STP 1502(143)HES
Work Type ADD PASSING LANES
 
2.985 1788921.69 0.00 1311382.87 73.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-11-15
Work Began 12-15-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 227
Percent Time Used 135
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-03-031
D. I. J. CONSTRUCTION, INC.(3.35%)
TEXAS ALTERNATIVE GRASSER, INC.(0.29%)
HJC FARMS, INC.(1.37%)
NORTH EASTERN PAVERS ( 23.51%)
RAMBO CONTRACTING, INC.(3.20%)
TEXOP CONSTRUCTION (0.84%)
Contract # 04153259
Totals 4279334.28 0.00 2773560.42 66.1

CountySAN SABA
Highway FM 580
From US 190
To LAMPASAS C/L
CSJ 0231-14-017
Proj ID STP 2015(389)HES
Work Type ADD'L PAVED SURF WIDTH, WDN STRS
 
14.144 5387952.96 127514.72 4442700.86 82.4
Work Order 03-13-15
Work Began 06-23-15
Work Completed  
Time Computed 06-11-15
Contract Working Days 474
Addl Days Granted 0
Working Days Charged 320
Percent Time Used 67
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0231-14-017
D. I. J. CONSTRUCTION, INC.(2.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.37%)
PRIMATE CONSTRUCTION, INC. (0.14%)
ROADWAY SPECIALTIES, INC.(4.88%)
SAN-ANN-CO., INC.(0.99%)
TEXAS ALTERNATIVE GRASSER, INC.(0.47%)
BROCK CONSTRUCTION, LLC(0.30%)
Contract # 01153225
Totals 5387952.96 127514.72 4442700.86 82.4

CountyEASTLAND
Highway SH 6
From 4.4 MI. E OF CARBON
To COMANCHE C/L
CSJ 0257-04-025
Proj ID STP 2014(867)
Work Type BASE OVERLAY AND 2 COURSE SURF TRT
 
5.099 3574742.00 28641.75 3682981.58 99.9
CountyCOMANCHE
Highway SH 6
From EASTLAND C/L
To 3.22 MI. E
CSJ 0257-05-044
Proj ID STP 2014(867)
Work Type RECONSTRUCT ROADWAY
 
3.219 1920300.43 0.00 7433.80 0.3
Work Order 02-05-15
Work Began 03-16-15
Work Completed  
Time Computed 04-06-15
Contract Working Days 203
Addl Days Granted 42
Working Days Charged 265
Percent Time Used 108
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0257-04-025
NORTHEASTERN PAVERS, INC.( 23.73%)
TEXAS ALTERNATIVE GRASSER, INC.(0.26%)
HJC FARMS, INC.(0.67%)
STRIPING TECHNOLOGY, L.P.(2.67%)
Contract # 07143216
Totals 5495042.43 28641.75 3690415.38 67.5

CountyMCCULLOCH
Highway US 190
From US 377
To SAN SABA C/L
CSJ 0272-01-031
Proj ID STP 2016(924)HES
Work Type UPGRADE GUARDRAIL & SFTY TREAT STRS
 
17.174 1084525.50 0.00 498668.13 45.9
CountySAN SABA
Highway FM 45
From MILLS C/L
To RICHLAND SPRINGS NORTH CITY LIMIT
CSJ 0480-08-023
Proj ID STP 2016(925)HRR
Work Type UPGRADE GUARDRAIL & SFTY TREAT STRS
 
12.071 714070.00 0.00 80000.00 11.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-16
Work Began 08-08-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 88
Percent Time Used 38
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0272-01-031
ODUM SERVICES, L.P.( 19.21%)
Contract # 04163025
Totals 1798595.50 0.00 578668.13 32.1

CountyMILLS
Highway SH 16
From .021 MI SW OF BARROW ST
To SAN SABA COUNTY LINE
CSJ 0289-03-026
Proj ID STP 2017(445)HES
Work Type IMPRV GR, SFT TREAT FIXED, ADD PASS
 
9.241 1203835.85 0.00 0.00 0.0
CountyBURNET
Highway FM 1478
From LAMPASAS C/L
To 7.096 MI. S OF LAMPASAS C/L
CSJ 2206-02-006
Proj ID STP 2017(471)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
7.096 353795.02 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 187
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0289-03-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01173213
Totals 1557630.87 0.00 0.00 0.0

CountyMILLS
Highway FM 45
From BROWN C/L
To SAN SABA C/L
CSJ 0480-07-009
Proj ID STP 1602(052)
Work Type GRADING, STRUCTURES, BASE, AND SURF
 
4.362 4563803.88 0.00 1147001.80 25.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-20-16
Work Began 09-06-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 23
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0480-07-009
D.I.J. CONSTRUCTION, INC (1.28%)
TEXAS ALTERNATIVE GRASSER, INC.(0.60%)
HJC FARMS, INC.(0.95%)
J&M CONTRACTING COMPANY( 14.23%)
Contract # 05163004
Totals 4563803.88 0.00 1147001.80 25.1

CountyEASTLAND
Highway FM 8
From 0.273 MI. E OF FM 2214
To 0.06 MI. W OF HOG CREEK
CSJ 0550-01-023
Proj ID STP 2014(544)
Work Type GRADING, STRS, FLEX BASE, AND SURF
 
0.322 458987.68 0.00 99620.10 21.7
CountyEASTLAND
Highway FM 2214
From 0.5 MI E OF FM 571
To FM 8
CSJ 1697-02-019
Proj ID STP 2014(544)
Work Type GRADING, STRS, FLEX BASE AND SURFAC
 
4.701 4840589.80 354278.59 5229490.56 99.9
Work Order 08-07-14
Work Began 01-06-15
Work Completed  
Time Computed 12-10-14
Contract Working Days 272
Addl Days Granted 31
Working Days Charged 385
Percent Time Used 127
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1697-02-019
MARCOM"S MOWING SERVICE, LLC (0.49%)
NORTH EASTERN PAVERS ( 11.45%)
S & S BRIDGE PAINTING, INC.(0.55%)
TEXAS ALTERNATIVE GRASSER, INC.(0.62%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.37%)
WILLIS ELECTRIC CO., LP(2.05%)
SHINN & GREGORY, INC.(0.48%)
EROSION CONTROL MANAGEMENT SERVICES(0.61%)
ELLIS-MCGINNIS CONSTRUCTION CO.(3.96%)
D.I.J. CONSTRUCTION, INC (0.30%)
Contract # 05143002
Totals 5299577.48 354278.59 5329110.66 99.9

CountyEASTLAND
Highway FM 8
From AT HOG CREEK
To .
CSJ 0550-01-026
Proj ID BR 1502(309)
Work Type WIDEN BRIDGE, REHAB DECK & APPRS
 
0.156 1189721.30 0.00 1213970.32 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-24-15
Work Began 03-21-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 52
Working Days Charged 109
Percent Time Used 82
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 0550-01-026
HJC FARMS, INC.(2.46%)
PEACHTREE CONSTRUCTION, LTD. (5.77%)
S&S BRIDGE PAINTING(4.91%)
SHINN & GREGORY, INC.(2.30%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (3.66%)
TEXOP CONSTRUCTION (0.46%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.55%)
STRIPING TECHNOLOGY, L.P.(2.36%)
DFW SERVICES, LLC(0.97%)
PENHALL COMPANY(0.45%)
GRANBURY EXCAVATING, INC.( 14.37%)
Contract # 06153019
Totals 1189721.30 0.00 1213970.32 99.9

CountyEASTLAND
Highway FM 2461
From IH 20
To FM 2214
CSJ 0714-05-018
Proj ID STP 2015(836)HES
Work Type UPGRADE GUARDRAIL & SFTY TREAT STRS
 
8.435 444021.50 4712.05 492025.30 99.9
CountyEASTLAND
Highway FM 2461
From IH 20
To FM 2214
CSJ 0714-05-020
Proj ID STP 2015(835)
Work Type REHABILITATION OF EXISTING ROADWAY
 
8.435 1998843.11 51896.63 1975660.51 99.9
Work Order 05-21-15
Work Began 06-30-15
Work Completed  
Time Computed 06-21-15
Contract Working Days 238
Addl Days Granted 5
Working Days Charged 296
Percent Time Used 121
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0714-05-020
D.I.J. CONSTRUCTION, INC (3.58%)
MARCOM"S MOWING SERVICE, LLC (3.62%)
NORTHEASTERN PAVERS, INC.( 20.91%)
TEXAS ALTERNATIVE GRASSER, INC.(0.26%)
LUZ LERMA CONSTRUCTION, INC. (5.28%)
Contract # 04153011
Totals 2442864.61 56608.68 2467685.81 99.9

CountyBROWN
Highway CR
From ON CR 225 AT CLEAR CREEK
To .
CSJ 0923-06-056
Proj ID BR 2015(387)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 603204.63 0.00 190224.39 31.5
CountyBROWN
Highway CR
From ON CR 258 AT DOUDLE CREEK
To .
CSJ 0923-06-070
Proj ID BR 2015(388)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 416710.32 0.00 376006.50 90.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-16
Work Began 09-06-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 143
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 47
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-056
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.69%)
JB FARM & RANCH( 17.76%)
MORRIS COUNTY CONTRACTORS, L.L.C.(2.90%)
WOLFE CONSTRUCTION GROUP, INC. (0.48%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.70%)
Contract # 04163217
Totals 1019914.95 0.00 566230.89 55.5

CountyBROWN
Highway CR
From ON CR 334 AT SALT CREEK
To .
CSJ 0923-06-071
Proj ID BR 2016(004)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 404729.68 0.00 37830.77 9.3
CountyBROWN
Highway CR
From ON CR 121 AT TURKEY CREEK
To .
CSJ 0923-06-072
Proj ID BR 2016(258)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 401041.38 0.00 365600.74 91.1
CountyBROWN
Highway CR
From ON CR 291 AT BLANKET CREEK
To .
CSJ 0923-06-073
Proj ID BR 2016(005)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 343043.52 0.00 338891.25 98.7
CountyBROWN
Highway FM 3021
From 0.8 MI. E OF SH 279
To 0.9 MI. E OF SH 279
CSJ 3102-01-008
Proj ID STP 2016(926)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
0.100 132695.39 0.00 132419.73 99.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-02-16
Work Began 07-05-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 183
Addl Days Granted 5
Working Days Charged 117
Percent Time Used 62
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-071
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.50%)
MCL CONTRACTING, LLC (0.54%)
FOUNDATION DRILLERS, INC.(3.58%)
Contract # 04163034
Totals 1281509.97 0.00 874742.49 68.2

CountyCOMANCHE
Highway CR
From ON CR 403 AT DRAW
To .
CSJ 0923-17-076
Proj ID BR 2015(346)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 217652.00 0.00 59076.00 27.1
CountyCOMANCHE
Highway CR
From ON CR 304 AT INDIAN CREEK
To .
CSJ 0923-17-078
Proj ID BR 2016(003)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 568174.50 0.00 64190.00 11.2
CountyCOMANCHE
Highway FM 1689
From AT WALNUT CREEK
To .
CSJ 1033-04-021
Proj ID BR 1602(572)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 994764.15 0.00 106390.00 10.6
CountyCOMANCHE
Highway FM 1477
From AT N COPPERAS CREEK
To .
CSJ 1366-01-009
Proj ID BR 1602(573)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.100 684261.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-01-16
Work Began 12-07-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 264
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 5
Contractor(s)
PIERCE R & B LLC
SUBCONTRACTOR(S) FOR CCSJ: 1033-04-021
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.69%)
ODUM SERVICES, L.P.(2.90%)
PEACHTREE CONSTRUCTION, LTD. (3.50%)
STRIPE-A-ZONE, INC.(0.53%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67%)
Contract # 08163217
Totals 2464851.85 0.00 229656.00 9.3

page 1 | page 2