Monthly State Let Construction Report For Brownwood District As Of Apr 10, 2015 Page 1 Of 2

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEASTLAND
Highway IH 20
From CALLAHAN C/L
To 2.443 MILES EAST
CSJ 0007-03-087
Proj ID STP 2015(057)HESG
Work Type INSTALL MEDIAN BARRIER
 
2.443 321299.40 0.00 326397.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 10-28-14
Work Completed 12-04-14
Time Computed 10-22-14
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 14
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-03-087
ALTUS TRAFFIC MANAGEMENT LLC (1.47%)
JUNIOR CONSTRUCTION COMPANY, INC.( 26.74%)
WOLFE CONSTRUCTION GROUP, INC. (0.43%)
Contract # 09143022
Totals 321299.40 0.00 326397.00 100.0

CountyEASTLAND
Highway IH 20 ETC
From EAST OVERPASS AT OLDEN
To COLONY CREEK BRIDGE (WESTBOUND)
CSJ 0007-04-120
Proj ID NH 2015(323)
Work Type SEAL COAT
 
104.121 2943828.19 0.00 0.00 0.0
Work Order 01-05-15
Work Began 00-00-00
Work Completed  
Time Computed 01-21-15
Contract Working Days 53
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0007-04-120
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11143207
Totals 2943828.19 0.00 0.00 0.0

CountyEASTLAND
Highway IH 20
From AT 0.5 MI. W OF FM 571 AND ALSO AT
To 2.5 MI. W OF SH 16
CSJ 0007-06-070
Proj ID STP 2005(276)TEG
Work Type CONSTRUCT TWO SAFETY REST AREAS
 
3.119 16358386.58 82012.00 14911585.55 91.1
Work Order 01-04-13
Work Began 02-01-13
Work Completed  
Time Computed 01-20-13
Contract Working Days 415
Addl Days Granted 84
Working Days Charged 431
Percent Time Used 86
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-070
EROSION CONTROL MANAGEMENT SERVICES(0.83%)
ABILENE SHEET METAL(1.43%)
CURTIS MECHANICAL CONTRACTORS, INC.(2.10%)
GRIZZLY GLASS & MIRROR, INC. (1.01%)
LONE OAK LANDSCAPE LLC (0.38%)
LONE STAR BARRIER SERVICES, LLC(0.66%)
PEACHTREE CONSTRUCTION, LTD. (4.79%)
SCR CONSTRUCTION CO., INC. (0.18%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.42%)
TIPPENN FABRICATION & ERECTION (5.06%)
ALVAREZ DRYWALL & ACCOUSTICS, INC. (0.57%)
BUFFALO GAP INSTRUMENTATION AND ELECTRICAL CO., INC. (9.53%)
CORPUS CHRISTI STAMP WORKS, INC. (0.05%)
FINLEY TERMITE AND PEST CONTROL, INC.(0.01%)
SOLID ROCK LAWN & LANDSCAPE(0.21%)
TEX OP CONSTRUCTION, LP(0.20%)
GOMEZ FLOOR COVERING, INC. (1.55%)
ENNIS ROOFING AND CONSTRUCTION, L.L.C. (2.07%)
B.A.D.J., INC. DBA THE TOPSPOT (0.21%)
WILKS MASONRY CORPORATION(4.34%)
LIBERTY PAINTING & DRYWALL (0.65%)
HUNTER KNEPSHIELD COMPANY(0.73%)
CLLA GROUP, LLC(1.46%)
AMERITEX FLAG & FLAGPOLE, LLC(0.03%)
A & A CONSTRUCTION (0.26%)
LIBERTY PAINTING & DRYWALL (0.65%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.11%)
CONROE WOOD PRODUCTS INC.(0.00%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
SAR TRANSPORTATION, LLC(0.00%)
CHAMPION FUEL SOLUTIONS(0.00%)
Contract # 10123203
Totals 16358386.58 82012.00 14911585.55 91.1

CountyEASTLAND
Highway IH 20
From 4.1 MI. E OF RANGER
To 0.6 MI. W OF SH 16
CSJ 0007-06-086
Proj ID STP 2014(439)SB
Work Type TRAFFIC BARRIER, LIGHTING, STRIPING
 
2.085 2844513.82 8700.00 3032631.56 100.0
Work Order 01-17-14
Work Began 04-01-14
Work Completed 11-05-14
Time Computed 04-01-14
Contract Working Days 138
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 74
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0007-06-086
BICK"S CONSTRUCTION, INC.( 26.27%)
D. I. J. CONSTRUCTION, INC.(2.23%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.( 15.24%)
INTERMOUNTAIN SLURRY SEAL, INC.(4.64%)
TEX OP CONSTRUCTION, LP(2.17%)
WEST TEXAS RUMBLE STRIP(0.14%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.00%)
AAA DRILLING FOUNDATION CO., INC.(0.35%)
Contract # 12133204
Totals 2844513.82 8700.00 3032631.56 100.0

CountyCOLEMAN
Highway US 84 ETC
From COLEMAN CL
To SANTA ANNA CL
CSJ 0054-04-104
Proj ID STP 2015(821)HES
Work Type TEXTURIZE SHOULDERS AND CENTERLINE
 
78.190 547099.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 49
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-04-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153210
Totals 547099.76 0.00 0.00 0.0

CountyBROWN
Highway US 84
From NEAR CR 312
To MILLS COUNTY LINE
CSJ 0054-07-081
Proj ID NH 1502(057)
Work Type PLANE, ACP OVERLAY
 
8.557 2342954.99 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BICK'S CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0054-07-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153254
Totals 2342954.99 0.00 0.00 0.0

CountyMCCULLOCH
Highway US 87
From 0.5 MI. WEST OF CR 138
To 0.3 MI. WEST OF US 283
CSJ 0070-06-047
Proj ID NH 2015(340)
Work Type ADD PASSING LANES
 
10.019 2729953.12 0.00 20750.00 0.7
Work Order 01-05-15
Work Began 00-00-00
Work Completed  
Time Computed 04-05-15
Contract Working Days 193
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0070-06-047
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10143226
Totals 2729953.12 0.00 20750.00 0.7

CountyEASTLAND
Highway US 183
From 0.599 MI. N
To BROWN C/L
CSJ 0127-02-140
Proj ID STP 2015(785)
Work Type ADD PASSING LANES
 
0.246 113364.13 0.00 0.00 0.0
CountyBROWN
Highway US 183
From EASTLAND C/L
To FM 1467
CSJ 0127-03-031
Proj ID STP 2015(785)
Work Type ADD PASSING LANES
 
7.886 2377048.46 0.00 0.00 0.0
CountyBROWN
Highway US 183
From FM 1467
To 3.6 MI N OF US 67(NEAR BWD AIRPORT)
CSJ 0127-04-032
Proj ID STP 1502(143)HES
Work Type ADD PASSING LANES
 
2.985 1788921.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0127-03-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153259
Totals 4279334.28 0.00 0.00 0.0

CountyBROWN
Highway US 377
From AT CROCKETT DRIVE
To .
CSJ 0128-01-106
Proj ID NH 2015(453)
Work Type CONSTRUCT NEW TRAFFIC SIGNAL
 
0.096 156330.88 18446.12 22091.12 14.1
Work Order 12-10-14
Work Began 03-24-15
Work Completed  
Time Computed 01-05-15
Contract Working Days 42
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 66
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0128-01-106
PRATER EQUIPMENT CO., INC. ( 23.69%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.77%)
Contract # 11143023
Totals 156330.88 18446.12 22091.12 14.1

CountyCOMANCHE
Highway SH 36
From 1 MI. S OF FM 1702
To HAMILTON C/L
CSJ 0183-01-037
Proj ID STP 2015(486)
Work Type BASE OVERLAY AND 2 COURSE SURF TRT
 
5.909 4034590.66 0.00 0.00 0.0
CountyCOMANCHE
Highway SH 36
From BRIDGES AT BARNET BRANCH, TATUM BR,
To AND AT DRAW
CSJ 0183-01-038
Proj ID BR 2015(630)
Work Type REPLACE BRIDGE RAIL
 
0.030 154143.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0183-01-037
D. I. J. CONSTRUCTION, INC.(2.27%)
JOY LATTIMER, LLC. (3.00%)
MPB, INC.(0.58%)
SAN-ANN-CO., INC.(1.07%)
LONE STAR BARRIER SERVICES, LLC(4.52%)
WOLFE CONSTRUCTION GROUP, INC. (0.34%)
Contract # 01153008
Totals 4188733.91 0.00 0.00 0.0

CountySAN SABA
Highway FM 580
From US 190
To LAMPASAS C/L
CSJ 0231-14-017
Proj ID STP 2015(389)HES
Work Type ADD'L PAVED SURF WIDTH, WDN STRS
 
14.144 5387952.96 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 474
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0231-14-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153225
Totals 5387952.96 0.00 0.00 0.0

CountyLAMPASAS
Highway US 281
From SULPHUR CREEK BRIDGE
To NEAR CR 4016
CSJ 0251-06-037
Proj ID NH 2015(449)
Work Type CONSTRUCT PEDESTRIAN SIDEWALK
 
0.700 210626.58 26874.50 75358.30 35.7
Work Order 01-05-15
Work Began 02-09-15
Work Completed  
Time Computed 01-21-15
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 62
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0251-06-037
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC. ( 12.97%)
N-LINE TRAFFIC MAINTENANCE, L.P. (2.44%)
Contract # 11143021
Totals 210626.58 26874.50 75358.30 35.7

CountyEASTLAND
Highway SH 6
From 4.4 MI. E OF CARBON
To COMANCHE C/L
CSJ 0257-04-025
Proj ID STP 2014(867)
Work Type BASE OVERLAY AND 2 COURSE SURF TRT
 
5.099 3574742.00 0.00 0.00 0.0
CountyCOMANCHE
Highway SH 6
From EASTLAND C/L
To 3.22 MI. E
CSJ 0257-05-044
Proj ID STP 2014(867)
Work Type RECONSTRUCT ROADWAY
 
3.219 1920300.43 0.00 0.00 0.0
Work Order 02-05-15
Work Began 03-16-15
Work Completed  
Time Computed 04-06-15
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 5
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0257-04-025
NORTHEASTERN PAVERS, INC.( 23.73%)
TEXAS ALTERNATIVE GRASSER, INC.(0.26%)
HJC FARMS, INC.(0.67%)
STRIPING TECHNOLOGY, L.P.(2.67%)
Contract # 07143216
Totals 5495042.43 0.00 0.00 0.0

CountyCOMANCHE
Highway SH 6
From 3.22 MI. E OF EASTLAND C/L
To NEAR SH 16
CSJ 0257-05-042
Proj ID STP 2015(058)
Work Type RECONSTRUCT ROADWAY
 
5.822 3990282.05 307167.33 307167.33 7.6
Work Order 02-05-15
Work Began 03-16-15
Work Completed  
Time Computed 04-06-15
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 6
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0257-05-042
D. I. J. CONSTRUCTION, INC.(2.16%)
HJC FARMS, INC.(0.45%)
TEXAS ALTERNATIVE GRASSER, INC.(0.36%)
Contract # 09143214
Totals 3990282.05 307167.33 307167.33 7.6

CountyBROWN
Highway SH 279 ETC
From FM 1849
To NEAR BROWNWOOD NORTH CITY LIMIT
CSJ 0480-01-032
Proj ID STP 2015(829)HES
Work Type UPGRADE GUARDRAIL & SFTY TRT STRS
 
48.004 1716374.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 344
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0480-01-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153009
Totals 1716374.55 0.00 0.00 0.0

CountyEASTLAND
Highway FM 8
From 0.273 MI. E OF FM 2214
To 0.06 MI. W OF HOG CREEK
CSJ 0550-01-023
Proj ID STP 2014(544)
Work Type GRADING, STRS, FLEX BASE, AND SURF
 
0.322 458987.68 0.00 1160.00 0.2
CountyEASTLAND
Highway FM 2214
From 0.5 MI E OF FM 571
To FM 8
CSJ 1697-02-019
Proj ID STP 2014(544)
Work Type GRADING, STRS, FLEX BASE AND SURFAC
 
4.701 4840589.80 278113.30 727844.56 15.0
Work Order 08-07-14
Work Began 01-06-15
Work Completed  
Time Computed 12-10-14
Contract Working Days 272
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 14
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1697-02-019
MARCOM"S MOWING SERVICE, LLC (0.49%)
NORTH EASTERN PAVERS ( 11.45%)
S & S BRIDGE PAINTING, INC.(0.55%)
TEXAS ALTERNATIVE GRASSER, INC.(0.62%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.37%)
WILLIS ELECTRIC CO., LP(2.05%)
SHINN & GREGORY, INC.(0.48%)
EROSION CONTROL MANAGEMENT SERVICES(0.61%)
ELLIS-MCGINNIS CONSTRUCTION CO.(3.96%)
Contract # 05143002
Totals 5299577.48 278113.30 729004.56 13.7

CountyEASTLAND
Highway FM 571
From AT LEON RIVER
To .
CSJ 0570-01-019
Proj ID BR 2015(462)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.133 821742.40 0.00 0.00 0.0
CountyCOMANCHE
Highway CR
From ON CR 435 AT SABANA RIVER
To .
CSJ 0923-17-063
Proj ID BR 2012(743)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.070 379885.40 0.00 0.00 0.0
CountyCOMANCHE
Highway CR
From ON CR 178 AT SABANA RIVER DRAW
To .
CSJ 0923-17-070
Proj ID BR 2014(382)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 134401.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-05-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0570-01-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12143211
Totals 1336028.80 0.00 0.00 0.0

CountyEASTLAND
Highway FM 2461
From IH 20
To FM 2214
CSJ 0714-05-018
Proj ID STP 2015(836)HES
Work Type UPGRADE GUARDRAIL & SFTY TREAT STRS
 
8.435 444021.50 0.00 0.00 0.0
CountyEASTLAND
Highway FM 2461
From IH 20
To FM 2214
CSJ 0714-05-020
Proj ID STP 2015(835)
Work Type REHABILITATION OF EXISTING ROADWAY
 
8.435 1998843.11 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 238
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0714-05-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153011
Totals 2442864.61 0.00 0.00 0.0

CountyBROWN
Highway CS
From MARKETPLACE ROAD IN BROWNWOOD
To US 67/84
CSJ 0923-06-062
Proj ID C 923-6-62
Work Type CONSTRUCT NEW 2 LANE ROADWAY
 
0.644 1394201.67 2400.00 1520991.90 100.0
Work Order 08-02-13
Work Began 08-26-13
Work Completed 10-30-14
Time Computed 09-16-13
Contract Working Days 150
Addl Days Granted 16
Working Days Charged 164
Percent Time Used 98
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-06-062
D. I. J. CONSTRUCTION, INC.(0.88%)
BEAR CREEK CONSTRUCTION, LLC ( 18.97%)
KARMY CONSTRUCTION INC (4.76%)
TEXAS ALTERNATIVE GRASSER, INC.(0.10%)
HJC FARMS, INC.(0.61%)
WILLIS ELECTRIC CO., LP( 11.78%)
Contract # 06133207
Totals 1394201.67 2400.00 1520991.90 100.0

CountyEASTLAND
Highway CR
From ON CR 107 AT COTTONWOOD CREEK
To .
CSJ 0923-09-052
Proj ID BR 2013(282)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 178335.00 -8491.07 177340.30 99.4
CountySTEPHENS
Highway CR
From ON CR 187 AT HOG BRANCH
To .
CSJ 0923-22-019
Proj ID BR 2013(763)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.056 249255.00 0.00 238958.32 95.8
CountySTEPHENS
Highway CR
From ON ELM STREET AT GONZALES DRAW
To .
CSJ 0923-22-020
Proj ID BR 1302(087)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.041 286320.80 41943.80 272470.80 95.1
Work Order 02-19-14
Work Began 03-10-14
Work Completed  
Time Computed 03-07-14
Contract Working Days 150
Addl Days Granted 5
Working Days Charged 154
Percent Time Used 99
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0923-09-052
CONTRACTORS SERVICE COMPANY(1.18%)
DUSTIN ALLEN, INC. (3.76%)
TEXAS ALTERNATIVE GRASSER, INC.(0.84%)
Contract # 01143007
Totals 713910.80 33452.73 688769.42 96.4

page 1 | page 2