Monthly State Let Construction Report For Dallas District As Of Apr 7, 2016 Page 11 Of 13

Last Update: Thursday, April 7, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDENTON
Highway FM 1171
From ON CORPS OF ENGINEERS PROPERTY
To NEAR WHITE'S BRANCH
CSJ 1311-01-053
Proj ID C 1311-1-53
Work Type TREES AND PLANTS
 
0.001 148908.50 0.00 61596.76 41.3
CountyDENTON
Highway FM 2499
From FM 2181
To HICKORY CREEK
CSJ 2681-01-022
Proj ID NH 1502(094)
Work Type LANDSCAPE DEVELOPMENT
 
1.112 299148.05 0.00 277336.91 92.7
Work Order 07-20-15
Work Began 08-04-15
Work Completed  
Time Computed 08-04-15
Contract Working Days 60
Addl Days Granted 2
Working Days Charged 34
Percent Time Used 54
Contractor(s)
APEX LANDSCAPE & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2681-01-022
ALTUS TRAFFIC MANAGEMENT LLC (0.85%)
AMAYA UTILITY(0.56%)
QUICK SET CONCRETE, INC. (5.50%)
Contract # 05153018
Totals 448056.55 0.00 338933.67 75.6

CountyDENTON
Highway FM 1385
From US 380
To APPROX. 2 MILES NORTH OF FM 428
CSJ 1315-01-025
Proj ID STP 1402(028)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
7.588 9063184.19 163479.80 5664477.02 62.4
Work Order 12-10-14
Work Began 07-10-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 378
Addl Days Granted 0
Working Days Charged 186
Percent Time Used 49
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-025
ALTUS TRAFFIC MANAGEMENT LLC (0.54%)
ASHLAR CONTRACTING COMPANY (8.41%)
SAMMY SMALLWOOD COMPANY(0.61%)
STRIPING TECHNOLOGY, L.P.(1.77%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(7.84%)
W.S. CONSTRUCTION COMPANY(6.71%)
JM YANEZ CONSTRUCTION(8.03%)
Contract # 09143208
Totals 9063184.19 163479.80 5664477.02 62.4

CountyDENTON
Highway FM 423
From US 380
To 0.8 MI SOUTH OF FM 2934
CSJ 1315-02-009
Proj ID C 1315-2-9
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.488 29826069.73 504263.72 15465745.11 51.8
Work Order 12-12-13
Work Began 10-08-14
Work Completed  
Time Computed 09-08-14
Contract Working Days 603
Addl Days Granted 0
Working Days Charged 372
Percent Time Used 61
Contractor(s)
MCM
SUBCONTRACTOR(S) FOR CCSJ: 1315-02-009
TOTAL HIGHWAY MAINTENANCE, LLC (0.96%)
STORM WATER MANAGEMENT, INC. (0.28%)
BOWMAN ENGINEERING & CONSULTING, INC.(0.84%)
FORTSON CONTRACTING, INC.(0.09%)
IEA, INC (9.39%)
JAGOE-PUBLIC COMPANY ( 10.82%)
OSCAR ORDUNO, INC. (0.23%)
ROADWAY SOLUTIONS, INC.(4.78%)
ROBERTS TRUCKING (1.98%)
RUSSO CORPORATION(0.55%)
DUSTROL, INC.(0.49%)
W.O.E. CONSTRUCTION(4.50%)
TRANSPORT TRUST(0.96%)
RICHMOND HYDROMULCH AND SEEDING, LLC (0.27%)
Contract # 09133204
Totals 29826069.73 504263.72 15465745.11 51.8

CountyCOLLIN
Highway FM 1378
From 585 SOUTH OF WHITE ROCK CREEK
To NORTH OF WHITE ROCK CREEK
CSJ 1392-01-035
Proj ID BR 2014(872)
Work Type REPL BRIDGE
 
0.526 1788995.75 65525.51 702713.38 39.2
Work Order 10-09-14
Work Began 08-10-15
Work Completed  
Time Computed 04-07-15
Contract Working Days 300
Addl Days Granted 10
Working Days Charged 156
Percent Time Used 50
Contractor(s)
ACCELERATED CRITICAL PATH, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-035
BREDA COMPANY, INC.(0.40%)
CROSSROADS, L.P. (0.90%)
D & S ENGINEERING LABS (0.45%)
DUSTROL, INC.(2.56%)
FOUNDATION DRILLERS, INC.(0.91%)
CRAIG OLDEN, INC.(1.77%)
LINDAMOOD DEMOLITION, INC. (1.39%)
MCRYAN HAULING, INC. (1.87%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.32%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.08%)
Contract # 07143231
Totals 1788995.75 65525.51 702713.38 39.2

CountyCOLLIN
Highway FM 1378
From FM 2514
To 0.2 MILE SOUTH OF FOREST GROVE RD
CSJ 1392-01-040
Proj ID STP 2015(395)
Work Type BASE REPAIR AND OVERLAY
 
6.057 2696578.78 37947.57 2372722.50 100.0
Work Order 02-13-15
Work Began 03-30-15
Work Completed 02-15-16
Time Computed 03-01-15
Contract Working Days 192
Addl Days Granted 0
Working Days Charged 190
Percent Time Used 98
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-040
WOLFE CONSTRUCTION GROUP, INC. (0.43%)
OLDEN, INC.(1.50%)
K & S UTILITY CONTRACTORS, INC.(3.09%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.52%)
TRP CONSTRUCTION GROUP, LLC(2.30%)
BROCK ENVIRONMENTAL, LLC (0.92%)
TRANSPORT TRUST(0.42%)
DUSTROL, INC.(8.19%)
COWBELL TRAFFIC SERVICE, INC.(0.22%)
DURABLE SPECIALTIES, INC.(0.58%)
PEACHTREE CONSTRUCTION, LTD. ( 12.71%)
Contract # 12143007
Totals 2696578.78 37947.57 2372722.50 100.0

CountyELLIS
Highway FM 1387
From WEST OF KENSINGTON DR
To EAST OF WALNUT GROVE RD
CSJ 1394-02-023
Proj ID CC 1394-2-23
Work Type GRADING, PAVING, STRUCTURES, SIGNS
 
0.925 4091255.00 0.00 3800144.97 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-06-13
Work Began 10-16-13
Work Completed 02-12-16
Time Computed 10-05-13
Contract Working Days 309
Addl Days Granted 0
Working Days Charged 460
Percent Time Used 148
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1394-02-023
BROCK ENVIRONMENTAL, LLC (1.34%)
MEL"S ELECTRIC SERVICE, INC. (3.36%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 16.40%)
RPM XCONSTRUCTION, LLC (8.29%)
STRIPING TECHNOLOGY, L.P.(1.65%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (6.50%)
DALLAS LITE AND BARRICADE INC. (0.65%)
DUSTROL, INC.(0.91%)
CROSSROADS, L.P. (0.37%)
T-BAR FENCE, INC.(0.09%)
W.O.E. CONSTRUCTION(7.41%)
FOUR STAR EXCAVATING INC (9.19%)
INLET STRUCTURE SPECIALTIES LTD. (1.66%)
IRON CONCRETE CONSTRUCTION COMPANY, INC. (1.66%)
J.R. STEEL TIE (0.83%)
SOUTHEAST GRINDING & GROOVING, LLC (0.12%)
Contract # 04133010
Totals 4091255.00 0.00 3800144.97 100.0

CountyKAUFMAN
Highway FM 1836
From FM 2515
To FM 90
CSJ 1397-01-030
Proj ID STP 2016(289)
Work Type SHLDR WDN, STR EXT, REMX, SC, PAV MRKS
 
6.905 6141935.93 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. L. LENNON INCORPORATED - CONTRACTOR
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-030
PEACHTREE CONSTRUCTION, LTD. (1.77%)
S & S BRIDGE PAINTING, INC.(4.51%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.11%)
TRP CONSTRUCTION GROUP, LLC(1.23%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.55%)
DUSTIN ALLEN, INC. (1.46%)
FARR FOUNDATION, INC.(1.51%)
K & S UTILITY CONTRACTORS, INC.(6.21%)
WITHERS CONSTRUCTION, LLC(0.63%)
ALTUS TRAFFIC MANAGEMENT LLC (0.20%)
CAMBRIDGEMOEN LLC(2.28%)
GIBSON & ASSOCIATES, INC.(1.87%)
Contract # 11153024
Totals 6141935.93 0.00 0.00 0.0

CountyKAUFMAN
Highway FM 1836
From SH 34
To 0.28 MI EAST OF CR 146
CSJ 1397-01-031
Proj ID C 1397-1-31
Work Type PROVIDE ADDITIONAL PAVED SURFACE
 
4.269 5943147.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 166
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1397-01-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163240
Totals 5943147.30 0.00 0.00 0.0

CountyELLIS
Highway FM 55
From AT LITTLE ONION CREEK
To .
CSJ 1451-01-020
Proj ID BR 2005(274)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.312 2010620.16 18707.00 142729.91 7.0
Work Order 07-24-15
Work Began 02-18-16
Work Completed  
Time Computed 11-21-15
Contract Working Days 340
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 8
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-020
TEXOP CONSTRUCTION (1.10%)
FORTSON CONTRACTING, INC.(2.27%)
SAN-ANN-CO., INC.(0.96%)
USA EROSION, INC.(4.31%)
STRIPING TECHNOLOGY, L.P.(1.50%)
Contract # 05153220
Totals 2010620.16 18707.00 142729.91 7.0

CountyELLIS
Highway FM 55
From 0.14 MILE SOUTH OF NASH HOWARD RD
To US 77
CSJ 1451-01-023
Proj ID STP 2015(655)HES
Work Type GR, BASE, PVMT, PVMT MKGS, SIGNS
 
5.500 4975101.65 246313.12 3237637.27 65.0
Work Order 05-15-15
Work Began 06-29-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 192
Percent Time Used 89
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-023
ALTUS TRAFFIC MANAGEMENT LLC (0.31%)
RAMBO CONTRACTING, INC.(4.29%)
BEAR CREEK CONSTRUCTION, LLC ( 14.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.62%)
STRIPING TECHNOLOGY, L.P.(0.91%)
SAN-ANN-CO., INC.(0.99%)
FORTSON CONTRACTING, INC.(1.01%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.65%)
SOUTHWEST MAINTENANCE, LTD (0.01%)
Contract # 03153011
Totals 4975101.65 246313.12 3237637.27 65.0

CountyELLIS
Highway FM 55
From SH 34
To 0.14 MI S OF NASH HOWARD RD
CSJ 1451-01-024
Proj ID STP 2014(874)
Work Type GR, BASE, PVMT MKGS, SIGNS
 
5.052 5538628.87 342195.90 4626115.68 85.1
Work Order 10-02-14
Work Began 12-01-14
Work Completed  
Time Computed 10-18-14
Contract Working Days 263
Addl Days Granted 0
Working Days Charged 344
Percent Time Used 130
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-024
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(3.86%)
STRIPING TECHNOLOGY, L.P.(0.83%)
SAN-ANN-CO., INC.(1.01%)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.(0.25%)
FORTSON CONTRACTING, INC.(3.25%)
OLDEN, INC.(5.14%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.49%)
Contract # 07143018
Totals 5538628.87 342195.90 4626115.68 85.1

CountyELLIS
Highway FM 55
From AT BIG ONION CREEK
To .
CSJ 1451-01-025
Proj ID BR 1502(533)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.135 1530409.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 183
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-01-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153020
Totals 1530409.40 0.00 0.00 0.0

CountyKAUFMAN
Highway FM 1565
From FM 986
To HUNT COUNTY LINE
CSJ 1494-02-008
Proj ID STP 2015(485)
Work Type GR, BASE, ACP OVERLAY, PVMT MKGS
 
1.623 1652146.23 0.00 686626.40 41.5
Work Order 03-02-15
Work Began 04-09-15
Work Completed  
Time Computed 03-18-15
Contract Working Days 159
Addl Days Granted 6
Working Days Charged 97
Percent Time Used 58
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1494-02-008
J & M CONTRACTING, COMPANY ( 15.62%)
STRIPING TECHNOLOGY, L.P.(1.25%)
GJ SEEDING, LLC(4.19%)
LONE STAR BARRIER SERVICES, LLC(1.14%)
ALTUS TRAFFIC MANAGEMENT LLC (0.56%)
C & J TREE SERVICE (0.18%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.63%)
Contract # 01153215
Totals 1652146.23 0.00 686626.40 41.5

CountyKAUFMAN
Highway FM 3486
From FM 986
To SH 34
CSJ 1494-03-001
Proj ID C 1494-3-1
Work Type GR, STRS, BASE & SURF
 
2.490 4849821.37 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 168
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1494-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163222
Totals 4849821.37 0.00 0.00 0.0

CountyDENTON
Highway FM 720
From AT HARTS BRANCH
To .
CSJ 1567-01-021
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.080 1726268.66 368.00 1650996.63 95.6
CountyDENTON
Highway FM 720
From AT LITTLE ELM CREEK BRANCH OF LAKE
To LEWISVILLE
CSJ 1567-01-022
Proj ID BR 2010(983)
Work Type REPL BR & APPRS
 
0.484 15758790.61 39593.60 15876178.12 99.9
CountyDENTON
Highway FM 720
From 0.2 MI W OF GARZA LANE (W OF LAKE L
To 0.1 MI WEST OF FM 423
CSJ 1567-01-029
Proj ID STP 2010(982)MM
Work Type GRADING, STR, PVMT, SIGNS
 
4.493 33538923.64 623921.46 36905691.08 99.9
CountyDENTON
Highway FM 720
From 0.2 MILE WEST OF GARZA LANE
To 0.1 MILE WEST OF FM 423
CSJ 1567-01-032
Proj ID RW 1567-1-32
Work Type ROW ACQ. AND UTIL. ADJUST.
 
0.001 3297279.80 0.00 460852.58 13.9
Work Order 09-13-10
Work Began 07-14-11
Work Completed  
Time Computed 03-12-11
Contract Working Days 577
Addl Days Granted 307
Working Days Charged 774
Percent Time Used 87
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-029
ATS DRILLING, L.P. (5.77%)
BRENDA PRICE TRUCKING(0.22%)
CRAIG OLDEN, INC.(0.61%)
DALLAS LITE AND BARRICADE INC. (0.11%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.21%)
HIGHWAY TECHNOLOGIES, INC. (0.31%)
L & E HART ENTERPRISES, INC. (2.09%)
MICA CORPORATION (4.78%)
NORTH TEXAS REBAR, LLC (5.54%)
PENHALL COMPANY(0.05%)
RAMBO CONTRACTING, INC.(2.62%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(6.26%)
S & V CONSTRUCTION LLC (0.05%)
SOUTH TEXAS PAINTING COMPANY (0.15%)
STORM WATER MANAGEMENT, INC. (0.10%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.28%)
TEX OP CONSTRUCTION, LP(0.99%)
WEIR BROS.,INC.(5.19%)
GREAT WESTERN ERECTORS (0.12%)
DURABLE SPECIALTIES, INC.(1.39%)
LAYFIELD CONSTRUCTION, INC (0.01%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
GREAT WESTERN ERECTORS (0.49%)
HAVEN LANDSCAPING & IRRIGATION, INC. (0.50%)
Contract # 07103001
Totals 54321262.71 663883.06 54893718.41 99.9

CountyDENTON
Highway FM 720
From ELDORADO PKWY (FM 720)
To SOUTH OF MARTOP
CSJ 1567-01-025
Proj ID C 1567-1-25
Work Type GR, STRS & PVT
 
2.565 15597320.25 775367.10 2098647.97 13.4
Work Order 04-11-14
Work Began 10-26-15
Work Completed  
Time Computed 01-06-15
Contract Working Days 420
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 21
Contractor(s)
HAYDON BUILDING CORP.
SUBCONTRACTOR(S) FOR CCSJ: 1567-01-025
S & S BRIDGE PAINTING, INC.(0.02%)
C.T. AND S. METALWORKS, INC. (0.11%)
ACU CONSTRUCTION LLC (0.69%)
W.O.E. CONSTRUCTION(1.22%)
BREDA COMPANY, INC.(0.99%)
USA SWPPP INSPECTIONS, INC.(1.99%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.04%)
FORTSON CONTRACTING, INC.(0.02%)
DURABLE SPECIALTIES, INC.(1.69%)
MARCOM"S MOWING SERVICE, LLC (0.10%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 15.66%)
DALLAS LITE AND BARRICADE INC. (0.66%)
THELIN RECYCLING COMPANY, L.P. (0.21%)
A.E.A. TRANSPORTATION(0.21%)
Contract # 02143001
Totals 15597320.25 775367.10 2098647.97 13.4

CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-032
Proj ID C 1567-2-32
Work Type WIDEN TO 6 LANE DIVIDED URBAN
 
3.761 49691109.92 502699.87 20010087.46 40.2
CountyDENTON
Highway FM 423
From STEWARTS CREEK ROAD
To SH 121
CSJ 1567-02-033
Proj ID RW 1567-2-33
Work Type ADJUSTMENT OF UTILITIES
 
3.761 8252384.38 168937.23 5673369.20 68.7
Work Order 08-27-14
Work Began 10-20-14
Work Completed  
Time Computed 09-12-14
Contract Working Days 756
Addl Days Granted 0
Working Days Charged 376
Percent Time Used 49
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-032
ATS DRILLING, INC. (1.12%)
C.T. AND S. METALWORKS, INC. (0.32%)
DUSTROL, INC.(0.52%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.08%)
HOUSTON SAWING & DRILLING(0.00%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (0.31%)
MEL"S ELECTRIC SERVICE, INC. (6.02%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(8.40%)
DALLAS LITE AND BARRICADE INC. (0.14%)
SCOTT DERR PAINTING CO, LLC(0.66%)
STORM WATER MANAGEMENT, INC. (0.14%)
STRIPING TECHNOLOGY, L.P.(0.73%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.13%)
WEST TEXAS REBAR PLACERS INC.(0.35%)
W.O.E. CONSTRUCTION(4.60%)
MCL CONTRACTING, LLC (0.06%)
BORE COMPANY (2.11%)
GUIDO CONSTRUCTION, INC. DBA GUIDO"S TRUCKS(0.19%)
TEXAS STAR TRANSPORT, LP (0.69%)
INDUS CONSTRUCTION, L.P. (4.75%)
FORTSON CONTRACTING, INC.(0.09%)
ACTION CONSTRUCTORS(0.54%)
SYNERGY SIGNS & SERVICES, LLC(0.11%)
RICE TUNNELING & BORING, INC.(0.15%)
HIGH QUALITY ELECTRIC(0.04%)
ALLIED DRILLING COMPANY(0.08%)
TOMAS REYES TRUCKING, INC. (0.68%)
ROAD MAKER CONTRACTORS (0.44%)
PANIOLO CONSTRUCTION SERVICES, LLC (0.40%)
DALE BROWN, INC. (0.15%)
URBAN INFRACONSTRUCTION, LLC (0.14%)
Contract # 05143001
Totals 57943494.30 671637.10 25683456.66 44.3

CountyDENTON
Highway FM 407
From FM 1830
To WEST OF LANTANA TRAIL
CSJ 1785-01-028
Proj ID C 1785-1-28
Work Type GR, STRS & PVT.
 
6.126 12873212.87 43099.65 14442956.71 100.0
Work Order 09-16-11
Work Began 03-01-12
Work Completed 06-25-15
Time Computed 03-01-12
Contract Working Days 497
Addl Days Granted 195
Working Days Charged 692
Percent Time Used 100
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 1785-01-028
BREDA COMPANY, INC.(1.11%)
BRENDA PRICE TRUCKING(0.93%)
CONCRETE CUTTING BY BOND (0.50%)
FARR FOUNDATION, INC.(0.24%)
FORTSON CONTRACTING, INC.(0.13%)
HIGHWAY TECHNOLOGIES, INC. (0.00%)
IOWA BRIDGE & CULVERT, LC(1.16%)
MICA CORPORATION (2.69%)
MIKE ALBERT, INC.(4.47%)
TEXAS CURB CUT, LP (0.05%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.82%)
THELIN RECYCLING CO., LLC(0.23%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.45%)
C.T. AND S. METALWORKS, INC. (0.00%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(2.03%)
PENHALL COMPANY(0.00%)
STRIPING TECHNOLOGY, L.P.(0.99%)
DURABLE SPECIALTIES, INC.(2.56%)
Contract # 07113205
Totals 12873212.87 43099.65 14442956.71 100.0

CountyDENTON
Highway FM 407
From FM 1830
To JETER RD
CSJ 1785-01-035
Proj ID STP 1502(498)
Work Type LANDSCAPE DEVELOPMENT
 
9.160 498172.50 6200.00 37200.00 7.4
Work Order 11-02-15
Work Began 12-07-15
Work Completed  
Time Computed 12-07-15
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 48
Contractor(s)
C. GREEN SCAPING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1785-01-035
RICE TUNNELING & BORING, INC.(2.10%)
Contract # 07153027
Totals 498172.50 6200.00 37200.00 7.4

CountyDENTON
Highway FM 407
From W. OF CHIN CHAPEL
To W. OF BRIARHILL BLVD.
CSJ 1950-01-026
Proj ID C 1950-1-26
Work Type GRADING, STRUCTURES, BAND AND SURF
 
1.369 5419912.44 0.00 6259052.37 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-16-10
Work Began 09-21-10
Work Completed 12-18-14
Time Computed 05-17-10
Contract Working Days 300
Addl Days Granted 209
Working Days Charged 485
Percent Time Used 95
Contractor(s)
TISEO PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1950-01-026
AXIS CONTRACTING, INC. (1.90%)
BROCK ENVIRONMENTAL, LLC (0.38%)
BUYERS BARRICADES, INC.(0.52%)
DURABLE SPECIALTIES, INC.(1.95%)
FORTSON CONTRACTING, INC.(0.02%)
IOWA BRIDGE & CULVERT, LC(1.45%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 17.25%)
STRIPE-A-ZONE, INC.(1.19%)
T & R EXCAVATION, INC. ( 21.56%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.21%)
TOMAS REYES TRUCKING, INC. (2.93%)
W.O.E. CONSTRUCTION(0.14%)
TEXAS INLETS, INC. (3.48%)
DUSTROL, INC.(3.03%)
Contract # 01103007
Totals 5419912.44 0.00 6259052.37 100.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13