Monthly State Let Construction Report For Dallas District As Of Apr 12, 2024 Page 5 Of 7

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDENTON
HighwayFM 428
FromAT PECAN CREEK
To.
CSJ0817-01-025
Proj IDBR 2022(619)
Work TypeBRIDGE REPLACEMENT
 
0.2443733494.151842167.2749.3
CountyDENTON
HighwayFM 2153
FromAT CULP BRANCH
To.
CSJ2248-01-008
Proj IDBR 2022(620)
Work TypeBRIDGE REPLACEMENT
 
0.1712115046.701254970.9659.3
Work Order07-06-22
Work Began08-08-22
Work Completed
Time Computed08-08-22
Contract Working Days522
Addl Days Granted0
Working Days Charged271
Percent Time Used51
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0817-01-025
MORRIS COUNTY CONTRACTORS, L.L.C. (3.26)
TOTAL HIGHWAY MAINTENANCE, LLC (0.90)
TEXAS TRAFFIC AND BARRICADE, LLC (0.51)
BARRICADES UNLIMITED (0.77)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.00)
TRP CONSTRUCTION GROUP, LLC (0.49)
PENHALL COMPANY (0.14)
Contract #06223011
Totals5848540.85106928.943097138.2352.9

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-330
Proj IDC 918-00-330
Work TypeTRAFFIC CONTROL DEVICES
 
2444000.002107307.2886.2
Work Order10-14-21
Work Began07-19-22
Work Completed
Time Computed02-11-22
Contract Working Days913
Addl Days Granted0
Working Days Charged616
Percent Time Used67
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-330
ROAD MASTER STRIPING, LLC (3.31)
JR WEST TEXAS CONCRETE LLC (1.82)
Contract #09213010
Totals2444000.000.002107307.2886.2

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-351
Proj IDC 918-00-351
Work TypeTRAFFIC CONTROL DEVICES
 
4521287.50241940.775.3
Work Order10-06-22
Work Began08-11-23
Work Completed
Time Computed08-07-23
Contract Working Days913
Addl Days Granted0
Working Days Charged232
Percent Time Used25
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-351
ROAD MASTER STRIPING, LLC (1.85)
JR WEST TEXAS CONCRETE LLC (0.18)
SALCOMM, LLC (0.20)
Contract #09223209
Totals4521287.5067588.77241940.775.3

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-365
Proj IDSTP 2024(788)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
328723.320.000.0
CountyDENTON
HighwayFM 423
FromUS 380
ToFM 720
CSJ1315-02-015
Proj IDSTP 2024(793)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
41520.000.000.0
CountyDENTON
HighwayFM 423
FromFM 720
ToMAIN STREET
CSJ1567-01-043
Proj IDSTP 2024(793)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
35412.500.000.0
CountyDENTON
HighwayFM 423
FromMAIN STREET
ToLEBANON RD
CSJ1567-02-038
Proj IDSTP 2024(793)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
40487.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-365
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243230
Totals446143.320.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATION
ToIN THE DALLAS DISTRICT
CSJ0918-00-380
Proj IDF 2024(016)
Work TypeTRAFFIC CONTROL DEVICES
 
4157640.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days913
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-380
ROAD MASTER STRIPING, LLC (2.17)
Contract #09233017
Totals4157640.250.000.000.0

CountyKAUFMAN
HighwayCR
FromAT JONES CREEK
To.
CSJ0918-11-100
Proj IDBR 2022(518)
Work TypeBRIDGE REPLACEMENT
 
0.070548372.00261477.0447.6
CountyKAUFMAN
HighwayCR
FromAT BACHELOR CREEK RELIEF
To.
CSJ0918-11-101
Proj IDBR 2022(519)
Work TypeBRIDGE REPLACEMENT
 
0.087550994.00531023.9396.3
CountyKAUFMAN
HighwayCR
FromAT MUDDY CEDAR CREEK TRIBUTARY
To.
CSJ0918-11-102
Proj IDBR 2022(520)
Work TypeBRIDGE REPLACEMENT
 
0.047434943.50427510.0198.2
Work Order06-14-23
Work Began07-14-23
Work Completed
Time Computed07-14-23
Contract Working Days303
Addl Days Granted0
Working Days Charged149
Percent Time Used49
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-11-100
PEACHTREE CONSTRUCTION, LTD. (5.76)
MORRIS COUNTY CONTRACTORS, L.L.C. (4.44)
TORO BRAVO CONSTRUCTION, LLC (0.25)
FC TRAFFIC CONTROL, INC. (1.46)
WOLFE CONSTRUCTION GROUP, INCORPORATED (2.18)
Contract #05233233
Totals1534309.50124215.541220010.9879.5

CountyNAVARRO
HighwayCR
FromAT MILL CREEK
To.
CSJ0918-18-133
Proj IDBR 2022(309)
Work TypeBRIDGE REPLACEMENT
 
945715.800.000.0
CountyNAVARRO
HighwayCR
FromAT RUSH CREEK TRIBUTARY
To.
CSJ0918-18-136
Proj IDBR 2022(311)
Work TypeBRIDGE REPLACEMENT
 
529117.900.000.0
CountyNAVARRO
HighwayCR
FromAT PIN OAK CREEK
To.
CSJ0918-18-137
Proj IDBR 2022(308)
Work TypeBRIDGE REPLACEMENT
 
875988.900.000.0
CountyNAVARRO
HighwayCR
FromAT RUSH CREEK
To.
CSJ0918-18-138
Proj IDBR 2022(314)
Work TypeBRIDGE REPLACEMENT
 
1028699.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days210
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-18-133
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243210
Totals3379522.300.000.000.0

CountyCOLLIN
HighwayCR
FromCR 696 AT BRUSHY CREEK
To.
CSJ0918-24-254
Proj IDBR 2022(370)
Work TypeBRIDGE REPLACEMENT
 
1089606.63969766.7689.0
CountyCOLLIN
HighwayFM 547
FromAT SABINE CREEK BRANCH NO 1
To.
CSJ1014-01-014
Proj IDBR 2023(917)
Work TypeBRIDGE REPLACEMENT
 
0.0852029755.73708723.9534.9
CountyCOLLIN
HighwayFM 547
FromAT SABINE CREEK
To.
CSJ1014-01-015
Proj IDBR 2023(917)
Work TypeBRIDGE REPLACEMENT
 
0.0781779478.78266293.6014.9
Work Order07-19-23
Work Began08-29-23
Work Completed
Time Computed08-29-23
Contract Working Days290
Addl Days Granted0
Working Days Charged139
Percent Time Used47
Contractor(s)
INDUS ROAD & BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-254
WYLIE DRILLING & DRAINAGE, INC. (4.44)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.62)
DUSTROL, INC. (0.53)
HERMANOS STEEL, LLC (0.78)
ODUM SERVICES, LLC (1.35)
PEACHTREE CONSTRUCTION, LTD. (6.60)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.45)
HILBASH INVESTMENT LLC (10.40)
FC TRAFFIC CONTROL, INC. (0.39)
PENHALL COMPANY (0.48)
DFW REBAR, INC. (0.10)
Contract #06233223
Totals4898841.14167048.011944784.3139.6

CountyCOLLIN ETC
HighwayCS
FromRENNER RD AT SHILOH RD
ToIN THE CITY OF RICHARDSON
CSJ0918-24-266
Proj IDSTP 2022(621)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.9413050705.85543242.0617.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days480
Addl Days Granted0
Working Days Charged197
Percent Time Used41
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-266
JR WEST TEXAS CONCRETE LLC (11.45)
ROAD MASTER STRIPING, LLC (4.00)
SALCOMM, LLC (0.83)
Contract #06223220
Totals3050705.8565901.00543242.0617.8

CountyCOLLIN ETC
HighwayCS ETC
FromON FRANKFORD AT DALLAS PKWY
ToIN THE CITY OF DALLAS
CSJ0918-24-267
Proj IDSTP 2024(742)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4872332.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days220
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-267
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243224
Totals4872332.750.000.000.0

CountyCOLLIN
HighwayCS
FromAT HEDGECOXE RD
ToIN THE CITY OF ALLEN
CSJ0918-24-272
Proj IDSTP 2023(857)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.4002574587.50250.000.0
Work Order10-06-23
Work Began03-20-24
Work Completed
Time Computed02-03-24
Contract Working Days440
Addl Days Granted0
Working Days Charged33
Percent Time Used7
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-272
AAA DRILLING FOUNDATION COMPANY, INC. (0.81)
Contract #06233021
Totals2574587.50250.00250.000.0

CountyDENTON ETC
HighwayCS ETC
FromHICKORY ST AT FRY ST
ToIN THE CITY OF DENTON
CSJ0918-46-327
Proj IDSTP 2023(854)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.1332578292.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-25-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days260
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-327
LAYFIELD CONSTRUCTION, INC (0.94)
ROAD MASTER STRIPING, LLC (3.01)
JR WEST TEXAS CONCRETE LLC (11.95)
Contract #08233273
Totals2578292.400.000.000.0

CountyDENTON
HighwayVA
FromVARIOUS LOCATIONS
ToIN DENTON COUNTY
CSJ0918-46-345
Proj IDC 918-46-345
Work TypeREHABILITATION OF EXISTING ROAD
 
1824550.780.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAFFIC HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-46-345
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243022
Totals1824550.780.000.000.0

CountyDALLAS
HighwayCS
FromZANGS BLVD AT CLARENDEN DR
ToIN THE CITY OF DALLAS
CSJ0918-47-212
Proj IDSTP 2021(496)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.0012040000.001357340.6669.4
Work Order07-01-21
Work Began04-13-22
Work Completed
Time Computed10-29-21
Contract Working Days360
Addl Days Granted0
Working Days Charged453
Percent Time Used125
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-212
JR WEST TEXAS CONCRETE LLC (15.30)
ROAD MASTER STRIPING, LLC (3.93)
SALCOMM, LLC (1.31)
Contract #04213215
Totals2040000.0011055.001357340.6669.4

CountyDALLAS
HighwayCS
FromOATES DR AT LA PRADA DR
ToIN THE CITY OF DALLAS
CSJ0918-47-215
Proj IDSTP 2021(337)HES
Work TypeTRAFFIC CONTROL DEVICES
 
1.0001886400.001723843.9697.2
Work Order04-01-21
Work Began08-03-21
Work Completed
Time Computed07-30-21
Contract Working Days367
Addl Days Granted0
Working Days Charged507
Percent Time Used138
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-215
ROAD MASTER STRIPING, LLC (4.92)
JR WEST TEXAS CONCRETE LLC (7.30)
Contract #02213219
Totals1886400.000.001723843.9697.2

CountyDALLAS
HighwayCS
FromELSIE FAYE HEGGINS ST AT MALCOLM X BLVD
ToIN THE CITY OF DALLAS
CSJ0918-47-248
Proj IDSTP 2022(431)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1824000.00406086.0022.2
Work Order05-10-22
Work Began02-26-24
Work Completed
Time Computed04-17-23
Contract Working Days270
Addl Days Granted0
Working Days Charged193
Percent Time Used71
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-248
JR WEST TEXAS CONCRETE LLC (23.09)
ROAD MASTER STRIPING, LLC (2.97)
SALCOMM, LLC (6.20)
Contract #04223016
Totals1824000.00153255.00406086.0022.2

CountyDALLAS
HighwayCS
FromMCMILLAN AVE AT MOCKINGBIRD LN
ToIN THE CITY OF DALLAS
CSJ0918-47-249
Proj IDSTP 2022(338)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.5921724000.00339464.0019.6
Work Order05-10-22
Work Began03-14-24
Work Completed
Time Computed04-17-24
Contract Working Days360
Addl Days Granted0
Working Days Charged192
Percent Time Used53
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-249
JR WEST TEXAS CONCRETE LLC (13.16)
ROAD MASTER STRIPING, LLC (4.95)
SALCOMM, LLC (9.49)
Contract #02223216
Totals1724000.0039472.00339464.0019.6

CountyDALLAS
HighwayCS ETC
FromVARIOUS INTERSECTIONS
ToIN THE CITY OF DALLAS
CSJ0918-47-342
Proj IDSTP 2023(705)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8002762362.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-30-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days360
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-342
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05233223
Totals2762362.500.000.000.0

CountyDALLAS
HighwayCS
FromAT OVERTON RD
ToIN THE CITY OF DALLAS.
CSJ0918-47-347
Proj IDSTP 2023(440)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.8001765418.201045962.7659.2
Work Order03-16-23
Work Began10-16-23
Work Completed
Time Computed09-05-23
Contract Working Days340
Addl Days Granted0
Working Days Charged106
Percent Time Used31
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-347
WG ENGINEERING & CONSTRUCTION, LLC (60.74)
GOMEZ PROPERTY SOLUTIONS LLC (0.00)
Contract #02233229
Totals1765418.20117648.071045962.7659.2

CountyDALLAS
HighwayFD
FromWEST SPINE ROAD
ToWITHIN CEDAR HILL STATE PARK
CSJ0918-47-359
Proj IDC 918-47-359
Work TypeREHABILITATION OF EXISTING ROAD
 
1.4512217976.401248133.3756.2
Work Order08-03-23
Work Began10-12-23
Work Completed
Time Computed10-09-23
Contract Working Days105
Addl Days Granted0
Working Days Charged85
Percent Time Used80
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-47-359
BUYERS BARRICADES, INC. (0.23)
DIIBS SPECIALISTS, LLC (1.18)
TEXAS SELECT EROSION, LLC (0.79)
Q. ROBERTS TRUCKING INCORPORATED (3.38)
COWBOY TRUCKING (3.38)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.37)
STRIPE-A-ZONE, LLC (1.79)
Contract #06233630
Totals2217976.40319035.881248133.3756.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7