Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | DALLAS |
Highway | IH 20 |
From | WEST OF CARRIER PARKWAY |
To | FM 1382 (BELT LINE ROAD) |
CSJ | 2374-04-049 |
Proj ID | NH 1602(427) |
Work Type | CONSTRUCTION OF FRONTAGE ROAD |
|
| 2.372 | 54241512.30 | | 28978799.26 | 53.4 |
Work Order | 07-20-17 |
Work Began | 01-18-18 |
Work Completed | |
Time Computed | 01-02-18 |
Contract Working Days | 791 |
Addl Days Granted | 0 |
Working Days Charged | 374 |
Percent Time Used | 47 |
Contractor(s) |
FLUOR HEAVY CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 2374-04-049 BUYERS BARRICADES, INC. (0.02) WOLFE CONSTRUCTION GROUP, INC. (0.20) TOTAL HIGHWAY MAINTENANCE, LLC (0.49) HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (5.17) COMEN ENTERPRISE LLC (0.73) A R DANIEL CONSTRUCTION SERVICES, INC. (1.14) W.O.E. CONSTRUCTION (0.01) REYNOLDS ASPHALT & CONSTRUCTION COMPANY (6.48) A BROTHERS MILLING, LLC (0.25) THELIN RECYCLING COMPANY, L.P. (0.03) COWBOY TRUCKING (2.43) KLP COMMERCIAL, LLC (1.86) TEXAS SHAFTS, INC. (4.74) ROYAL REBAR (0.79) RENAISSANCE CONTRACTORS, INC. (0.86) FARR FOUNDATION, INC. (1.12) PANIOLO CONSTRUCTION SERVICES, LLC (4.97) STRAIGHT LINE SAWING & SEALING, INC. (0.12) SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.26) SCOTT DERR PAINTING CO, LLC (0.00) PANTHER CREEK TRANSPORTATION, INC. (0.11) W.O.E. CONSTRUCTION (1.11) ALLIANCE GEOTECHNICAL GROUP, INC. (0.32)
|
Contract # | 06173002 |
| Totals | 54241512.30 | 735464.55 | 28978799.26 | 53.4 |
|
County | DALLAS |
Highway | IH 20 |
From | NORTH MAIN STREET |
To | CAMP WISDOM ROAD IN DUNCANVILLE |
CSJ | 2374-04-060 |
Proj ID | STP 2019(256)MM |
Work Type | GRADING, PAVEMENT & STRUCTURES |
|
| 0.776 | 11973895.17 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 06-04-19 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 303 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
FLUOR HEAVY CIVIL, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 2374-04-060 TEXOP CONSTRUCTION (0.28) W.O.E. CONSTRUCTION (0.17) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.33) HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.62)
|
Contract # | 12183213 |
| Totals | 11973895.17 | 0.00 | 0.00 | 0.0 |
|
County | COLLIN |
Highway | FM 2514 |
From | FM 2551 |
To | WEST OF FM 1378 |
CSJ | 2679-02-008 |
Proj ID | STP 1802(470) |
Work Type | PVT,DRAINAGE,STR,SIGNS,PVT MKGS |
|
| 2.377 | 16867791.75 | | 4624712.31 | 27.4 |
County | COLLIN |
Highway | FM 2514 |
From | FM 2551 |
To | WEST OF FM 1378 |
CSJ | 2679-02-009 |
Proj ID | STP 2015(430) |
Work Type | ROW ACQ., AND UTL. ADJ. |
|
| 2.522 | 2213398.41 | | 2413068.62 | 99.9 |
Work Order | 07-19-18 |
Work Began | 10-26-18 |
Work Completed | |
Time Computed | 10-17-18 |
Contract Working Days | 450 |
Addl Days Granted | 0 |
Working Days Charged | 144 |
Percent Time Used | 32 |
Contractor(s) |
MARIO SINACOLA & SONS EXCAVATING, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2679-02-008 MASSEY CONTRACTORS, LLC (1.60) VENUS CONSTRUCTION (8.71) INTERCON ENVIRONMENTAL, INC. (0.55) DAKOTA UTILITY CONTRACTORS, INC. (1.38) REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.72) DUSTROL, INC. (0.41) BOWMAN ENGINEERING & CONSULTING, INC. (0.69) ALLIANCE GEOTECHNICAL GROUP, INC. (0.41) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.70) STRAIGHT LINE SAWING & SEALING, INC. (0.40) WYLIE DRILLING & DRAINAGE, INC. (0.54) COMEN ENTERPRISE LLC (0.18) SLATON BROTHERS, INC. (0.23) MELS ELECTRIC, L.P. (1.13) SCOTT DERR PAINTING CO, LLC (0.03) A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.40) RCF CONSTRUCTION, LLC (4.78) TOTAL HIGHWAY MAINTENANCE, LLC (0.67) THELIN RECYCLING COMPANY, L.P. (0.13) CHARRO BORING, INC. (0.34) TOTAL SUPPORT SERVICES, INC. (0.02) SOUTHWEST CONSTRUCTION SERVICES (0.02) KEY"S TAPPING & CONSTRUCTION SERVICES, INC. (0.01) STOIC CIVIL CONSTRUCTION, INC. (0.42)
|
Contract # | 06183203 |
| Totals | 19081190.16 | 604379.73 | 7037780.93 | 36.8 |
|
County | KAUFMAN |
Highway | FM 2757 |
From | FM 740 |
To | FM 741 |
CSJ | 2815-01-008 |
Proj ID | C 2815-1-8 |
Work Type | GRADING, STRUCTURES, PVMNT, SIGNS |
|
| 3.696 | 3946271.45 | | 773266.32 | 19.5 |
Work Order | 03-18-19 |
Work Began | 04-22-19 |
Work Completed | |
Time Computed | 04-17-19 |
Contract Working Days | 192 |
Addl Days Granted | 0 |
Working Days Charged | 48 |
Percent Time Used | 25 |
Contractor(s) |
LONGVIEW BRIDGE AND ROAD, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 2815-01-008 USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.74) SOUTHWEST ENVIRONMENT SERIVES, LLC (0.77) SYNERGY SIGNS & SERVICES LLC (0.60) MORRIS COUNTY CONTRACTORS, L.L.C. (1.76) STRIPING TECHNOLOGY, L.P. (1.12) TOTAL HIGHWAY MAINTENANCE, LLC (0.49) COLLIER-MANPOWER, INC. (0.00) TEXOP CONSTRUCTION (1.24)
|
Contract # | 02193209 |
| Totals | 3946271.45 | 365920.92 | 773266.32 | 19.5 |
|
County | DALLAS |
Highway | SH 161 |
From | SOUTH OF SH 183 |
To | NORTH OF BELT LINE RD |
CSJ | 2964-01-048 |
Proj ID | NH 1802(186) |
Work Type | GR, STR, PVMT, SIGNS |
|
| 3.233 | 20927948.34 | | 9862742.72 | 47.1 |
Work Order | 07-19-18 |
Work Began | 10-02-18 |
Work Completed | |
Time Computed | 09-24-18 |
Contract Working Days | 377 |
Addl Days Granted | 0 |
Working Days Charged | 183 |
Percent Time Used | 48 |
Contractor(s) |
J.D. ABRAMS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 2964-01-048 STRIPING TECHNOLOGY, L.P. (1.56) WYLIE DRILLING & DRAINAGE, INC. (0.53) REYNOLDS ASPHALT & CONSTRUCTION COMPANY (7.24) MICA CORPORATION (6.16) DALLAS LITE AND BARRICADE, INC. (0.79) HIGHWAY PAVEMENT SPECIALTIES, INC. (0.20) COWBOY AND SONS LP DBA COWBOY TRUCKING (2.06) LAYFIELD CONSTRUCTION, INC (0.54) USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.12) SOUTH TEXAS PAINTING COMPANY (0.07) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.80) BOWMAN ENGINEERING & CONSULTING, INC. (0.79) ACU CONSTRUCTION LLC (0.14) W.O.E. CONSTRUCTION (0.09) COWBOY TRUCKING (2.06)
|
Contract # | 06183202 |
| Totals | 20927948.34 | 2902760.38 | 9862742.72 | 47.1 |
|
County | DALLAS |
Highway | SH 190 |
From | NORTH OF LAKE RAY HUBBARD |
To | SOUTH OF MILLER ROAD |
CSJ | 2964-06-025 |
Proj ID | C 2964-6-25 |
Work Type | INSTALL NOISE BARRIER |
|
| 0.814 | 1735986.70 | | 1184519.21 | 68.2 |
Work Order | 11-09-18 |
Work Began | 05-06-19 |
Work Completed | |
Time Computed | 05-06-19 |
Contract Working Days | 43 |
Addl Days Granted | 0 |
Working Days Charged | 37 |
Percent Time Used | 86 |
Contractor(s) |
SELECT STRIPING LLC |
SUBCONTRACTOR(S) FOR CCSJ: 2964-06-025 RAGLE CONSTRUCTION, INC. (0.11) POST L GROUP, LLC. (9.44) M W PANEL TECH, LLC (3.12)
|
Contract # | 10183226 |
| Totals | 1735986.70 | 216446.98 | 1184519.21 | 68.2 |
|
County | KAUFMAN |
Highway | FM 2860 |
From | FM 1388 |
To | US 175 |
CSJ | 3190-01-012 |
Proj ID | STP 1902(130) |
Work Type | OV |
|
| 4.806 | 1098460.50 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 40 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
FOUTSCO PAVING COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 3190-01-012 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 06193012 |
| Totals | 1098460.50 | 0.00 | 0.00 | 0.0 |
|
County | COLLIN |
Highway | FM 2786 |
From | SH 5 |
To | EAST OF ANGEL PARKWAY IN ALLEN |
CSJ | 3392-01-008 |
Proj ID | STP 2015(397)MM |
Work Type | STR, PVMT, SIGNS, MEDIAN |
|
| 0.926 | 7976761.50 | | 8268193.37 | 99.9 |
County | COLLIN |
Highway | FM 2786 |
From | EAST OF ANGEL PKWY IN ALLEN |
To | FM 1378 |
CSJ | 3392-01-009 |
Proj ID | C 3392-1-9 |
Work Type | PVMT, DRAINAGE, SIGNS, MEDIAN |
|
| 1.008 | 7822942.39 | | 8172526.41 | 99.9 |
Work Order | 01-16-15 |
Work Began | 04-04-16 |
Work Completed | |
Time Computed | 04-04-16 |
Contract Working Days | 483 |
Addl Days Granted | 74 |
Working Days Charged | 557 |
Percent Time Used | 100 |
Contractor(s) |
ED BELL CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 3392-01-008 WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.61) DURABLE SPECIALTIES, INC. (2.47) OSCAR ORDUNO, INC. (1.10) BREDA COMPANY, INC. (0.64) BRENDA PRICE TRUCKING (0.06) SCOTT DERR PAINTING CO, LLC (0.03) TEX OP CONSTRUCTION, LP (1.10) W.O.E. CONSTRUCTION (0.25) LONE STAR BARRIER SERVICES, LLC (0.16) PREMIER PAVING, LTD. (10.71) STRIPING TECHNOLOGY, L.P. (0.88) K & S UTILITY CONTRACTORS, INC. (0.14) FORTSON CONTRACTING, INC. (0.01) SYNERGY SIGNS & SERVICES, LLC (0.18)
|
Contract # | 12143203 |
| Totals | 15799703.89 | 128051.05 | 16440719.78 | 99.9 |
|