Monthly State Let Construction Report For Dallas District As Of Jul 12, 2019 Page 9 Of 9

Last Update: Friday, July 12, 2019
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwayIH 20
FromWEST OF CARRIER PARKWAY
ToFM 1382 (BELT LINE ROAD)
CSJ2374-04-049
Proj IDNH 1602(427)
Work TypeCONSTRUCTION OF FRONTAGE ROAD
 
2.37254241512.3028978799.2653.4
Work Order07-20-17
Work Began01-18-18
Work Completed
Time Computed01-02-18
Contract Working Days791
Addl Days Granted0
Working Days Charged374
Percent Time Used47
Contractor(s)
FLUOR HEAVY CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-04-049
BUYERS BARRICADES, INC. (0.02)
WOLFE CONSTRUCTION GROUP, INC. (0.20)
TOTAL HIGHWAY MAINTENANCE, LLC (0.49)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (5.17)
COMEN ENTERPRISE LLC (0.73)
A R DANIEL CONSTRUCTION SERVICES, INC. (1.14)
W.O.E. CONSTRUCTION (0.01)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (6.48)
A BROTHERS MILLING, LLC (0.25)
THELIN RECYCLING COMPANY, L.P. (0.03)
COWBOY TRUCKING (2.43)
KLP COMMERCIAL, LLC (1.86)
TEXAS SHAFTS, INC. (4.74)
ROYAL REBAR (0.79)
RENAISSANCE CONTRACTORS, INC. (0.86)
FARR FOUNDATION, INC. (1.12)
PANIOLO CONSTRUCTION SERVICES, LLC (4.97)
STRAIGHT LINE SAWING & SEALING, INC. (0.12)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P. (0.26)
SCOTT DERR PAINTING CO, LLC (0.00)
PANTHER CREEK TRANSPORTATION, INC. (0.11)
W.O.E. CONSTRUCTION (1.11)
ALLIANCE GEOTECHNICAL GROUP, INC. (0.32)
Contract #06173002
Totals54241512.30735464.5528978799.2653.4

CountyDALLAS
HighwayIH 20
FromNORTH MAIN STREET
ToCAMP WISDOM ROAD IN DUNCANVILLE
CSJ2374-04-060
Proj IDSTP 2019(256)MM
Work TypeGRADING, PAVEMENT & STRUCTURES
 
0.77611973895.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-04-19
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days303
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FLUOR HEAVY CIVIL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2374-04-060
TEXOP CONSTRUCTION (0.28)
W.O.E. CONSTRUCTION (0.17)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.33)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC. (4.62)
Contract #12183213
Totals11973895.170.000.000.0

CountyCOLLIN
HighwayFM 2514
FromFM 2551
ToWEST OF FM 1378
CSJ2679-02-008
Proj IDSTP 1802(470)
Work TypePVT,DRAINAGE,STR,SIGNS,PVT MKGS
 
2.37716867791.754624712.3127.4
CountyCOLLIN
HighwayFM 2514
FromFM 2551
ToWEST OF FM 1378
CSJ2679-02-009
Proj IDSTP 2015(430)
Work TypeROW ACQ., AND UTL. ADJ.
 
2.5222213398.412413068.6299.9
Work Order07-19-18
Work Began10-26-18
Work Completed
Time Computed10-17-18
Contract Working Days450
Addl Days Granted0
Working Days Charged144
Percent Time Used32
Contractor(s)
MARIO SINACOLA & SONS EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2679-02-008
MASSEY CONTRACTORS, LLC (1.60)
VENUS CONSTRUCTION (8.71)
INTERCON ENVIRONMENTAL, INC. (0.55)
DAKOTA UTILITY CONTRACTORS, INC. (1.38)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (8.72)
DUSTROL, INC. (0.41)
BOWMAN ENGINEERING & CONSULTING, INC. (0.69)
ALLIANCE GEOTECHNICAL GROUP, INC. (0.41)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.70)
STRAIGHT LINE SAWING & SEALING, INC. (0.40)
WYLIE DRILLING & DRAINAGE, INC. (0.54)
COMEN ENTERPRISE LLC (0.18)
SLATON BROTHERS, INC. (0.23)
MELS ELECTRIC, L.P. (1.13)
SCOTT DERR PAINTING CO, LLC (0.03)
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED (0.40)
RCF CONSTRUCTION, LLC (4.78)
TOTAL HIGHWAY MAINTENANCE, LLC (0.67)
THELIN RECYCLING COMPANY, L.P. (0.13)
CHARRO BORING, INC. (0.34)
TOTAL SUPPORT SERVICES, INC. (0.02)
SOUTHWEST CONSTRUCTION SERVICES (0.02)
KEY"S TAPPING & CONSTRUCTION SERVICES, INC. (0.01)
STOIC CIVIL CONSTRUCTION, INC. (0.42)
Contract #06183203
Totals19081190.16604379.737037780.9336.8

CountyKAUFMAN
HighwayFM 2757
FromFM 740
ToFM 741
CSJ2815-01-008
Proj IDC 2815-1-8
Work TypeGRADING, STRUCTURES, PVMNT, SIGNS
 
3.6963946271.45773266.3219.5
Work Order03-18-19
Work Began04-22-19
Work Completed
Time Computed04-17-19
Contract Working Days192
Addl Days Granted0
Working Days Charged48
Percent Time Used25
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2815-01-008
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.74)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.77)
SYNERGY SIGNS & SERVICES LLC (0.60)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.76)
STRIPING TECHNOLOGY, L.P. (1.12)
TOTAL HIGHWAY MAINTENANCE, LLC (0.49)
COLLIER-MANPOWER, INC. (0.00)
TEXOP CONSTRUCTION (1.24)
Contract #02193209
Totals3946271.45365920.92773266.3219.5

CountyDALLAS
HighwaySH 161
FromSOUTH OF SH 183
ToNORTH OF BELT LINE RD
CSJ2964-01-048
Proj IDNH 1802(186)
Work TypeGR, STR, PVMT, SIGNS
 
3.23320927948.349862742.7247.1
Work Order07-19-18
Work Began10-02-18
Work Completed
Time Computed09-24-18
Contract Working Days377
Addl Days Granted0
Working Days Charged183
Percent Time Used48
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2964-01-048
STRIPING TECHNOLOGY, L.P. (1.56)
WYLIE DRILLING & DRAINAGE, INC. (0.53)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (7.24)
MICA CORPORATION (6.16)
DALLAS LITE AND BARRICADE, INC. (0.79)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.20)
COWBOY AND SONS LP DBA COWBOY TRUCKING (2.06)
LAYFIELD CONSTRUCTION, INC (0.54)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.12)
SOUTH TEXAS PAINTING COMPANY (0.07)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.80)
BOWMAN ENGINEERING & CONSULTING, INC. (0.79)
ACU CONSTRUCTION LLC (0.14)
W.O.E. CONSTRUCTION (0.09)
COWBOY TRUCKING (2.06)
Contract #06183202
Totals20927948.342902760.389862742.7247.1

CountyDALLAS
HighwaySH 190
FromNORTH OF LAKE RAY HUBBARD
ToSOUTH OF MILLER ROAD
CSJ2964-06-025
Proj IDC 2964-6-25
Work TypeINSTALL NOISE BARRIER
 
0.8141735986.701184519.2168.2
Work Order11-09-18
Work Began05-06-19
Work Completed
Time Computed05-06-19
Contract Working Days43
Addl Days Granted0
Working Days Charged37
Percent Time Used86
Contractor(s)
SELECT STRIPING LLC
SUBCONTRACTOR(S) FOR CCSJ: 2964-06-025
RAGLE CONSTRUCTION, INC. (0.11)
POST L GROUP, LLC. (9.44)
M W PANEL TECH, LLC (3.12)
Contract #10183226
Totals1735986.70216446.981184519.2168.2

CountyKAUFMAN
HighwayFM 2860
FromFM 1388
ToUS 175
CSJ3190-01-012
Proj IDSTP 1902(130)
Work TypeOV
 
4.8061098460.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 3190-01-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06193012
Totals1098460.500.000.000.0

CountyCOLLIN
HighwayFM 2786
FromSH 5
ToEAST OF ANGEL PARKWAY IN ALLEN
CSJ3392-01-008
Proj IDSTP 2015(397)MM
Work TypeSTR, PVMT, SIGNS, MEDIAN
 
0.9267976761.508268193.3799.9
CountyCOLLIN
HighwayFM 2786
FromEAST OF ANGEL PKWY IN ALLEN
ToFM 1378
CSJ3392-01-009
Proj IDC 3392-1-9
Work TypePVMT, DRAINAGE, SIGNS, MEDIAN
 
1.0087822942.398172526.4199.9
Work Order01-16-15
Work Began04-04-16
Work Completed
Time Computed04-04-16
Contract Working Days483
Addl Days Granted74
Working Days Charged557
Percent Time Used100
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 3392-01-008
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (1.61)
DURABLE SPECIALTIES, INC. (2.47)
OSCAR ORDUNO, INC. (1.10)
BREDA COMPANY, INC. (0.64)
BRENDA PRICE TRUCKING (0.06)
SCOTT DERR PAINTING CO, LLC (0.03)
TEX OP CONSTRUCTION, LP (1.10)
W.O.E. CONSTRUCTION (0.25)
LONE STAR BARRIER SERVICES, LLC (0.16)
PREMIER PAVING, LTD. (10.71)
STRIPING TECHNOLOGY, L.P. (0.88)
K & S UTILITY CONTRACTORS, INC. (0.14)
FORTSON CONTRACTING, INC. (0.01)
SYNERGY SIGNS & SERVICES, LLC (0.18)
Contract #12143203
Totals15799703.89128051.0516440719.7899.9