Monthly Local Let Maintenance Report For Dallas District As Of Mar 13, 2024 Page 5 Of 6

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6449-93-001
Proj IDRMC - 644993001
Work TypeVEGETATION MANAGEMENT
 
0.01063719.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days17
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RENEGADE SITE SOLUTIONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6449-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03241803
Totals63719.000.000.000.0

CountyCOLLIN
HighwaySH0005
FromCOLLIN COUNTY
ToMAINTENANCE SECTION
CSJ6450-11-001
Proj IDMMC - 645011001
Work TypeROCK/RIPRAP
 
0.0100.000.000.0
Work Order11-11-23
Work Began11-11-23
Work Completed
Time Computed11-11-23
Contract Working Days180
Addl Days Granted0
Working Days Charged103
Percent Time Used57
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231811
Totals0.000.000.000.0

CountyDALLAS
HighwayIH0030
FromVARIOUS ROADWAYS IN THE WEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6450-25-001
Proj IDRMC - 645025001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010235700.000.000.0
Work Order02-07-24
Work Began02-14-24
Work Completed
Time Computed02-14-24
Contract Working Days135
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SHALOM SERVICES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6450-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231806
Totals235700.000.000.000.0

CountyKAUFMAN
HighwayFM2728
FromKAUFMAN/ROCKWALL
ToMAINTENANCE SECTION
CSJ6450-55-001
Proj IDMMC - 645055001
Work TypeHYDRAULIC CEMENT
 
0.010105000.0030625.0029.1
Work Order09-26-23
Work Began09-26-23
Work Completed
Time Computed10-03-23
Contract Working Days180
Addl Days Granted180
Working Days Charged153
Percent Time Used42
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231812
Totals105000.0012250.0030625.0029.1

CountyKAUFMAN
HighwayFM2728
FromKAUFMAN/ROCKWALL
ToMAINTENANCE SECTION
CSJ6450-57-001
Proj IDMMC - 645057001
Work TypeROCK/RIPRAP
 
0.010152500.0029457.0019.3
Work Order10-21-23
Work Began10-21-23
Work Completed
Time Computed10-21-23
Contract Working Days180
Addl Days Granted180
Working Days Charged128
Percent Time Used35
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231814
Totals152500.0014498.5029457.0019.3

CountyKAUFMAN
HighwayFM2728
FromKAUFMAN/ROCKWALL
ToMAINTENANCE SECTION
CSJ6450-59-001
Proj IDMMC - 645059001
Work TypeEMULSION
 
0.010262200.0064469.3324.5
Work Order09-29-23
Work Began09-29-23
Work Completed
Time Computed10-06-23
Contract Working Days180
Addl Days Granted180
Working Days Charged150
Percent Time Used41
Contractor(s)
WRIGHT ASPHALT PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231815
Totals262200.0022905.8164469.3324.5

CountyKAUFMAN
HighwayFM2728
FromKAUFMAN/ROCKWALL
ToMAINTENANCE SECTION
CSJ6450-61-001
Proj IDMMC - 645061001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.01079776.0014878.8918.6
Work Order10-03-23
Work Began10-03-23
Work Completed
Time Computed10-10-23
Contract Working Days180
Addl Days Granted180
Working Days Charged142
Percent Time Used39
Contractor(s)
WALLER COUNTY ASPHALT INC.
SUBCONTRACTOR(S) FOR CCSJ: 6450-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231813
Totals79776.000.0014878.8918.6

CountyKAUFMAN
HighwayFM2728
FromKAUFMAN/ROCKWALL
ToMAINTENANCE SECTION
CSJ6450-65-001
Proj IDMMC - 645065001
Work TypeLIMESTONE ROCK ASPHALT
 
0.010244667.5091970.2237.5
Work Order10-03-23
Work Began10-03-23
Work Completed
Time Computed10-10-23
Contract Working Days180
Addl Days Granted0
Working Days Charged142
Percent Time Used78
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6450-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231808
Totals244667.500.0091970.2237.5

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6450-95-001
Proj IDRMC - 645095001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.010177605.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-26-24
Work Began00-00-00
Work Completed
Time Computed03-04-24
Contract Working Days69
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTGATE SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6450-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231805
Totals177605.000.000.000.0

CountyCOLLIN
HighwaySH0005
FromJANITORIAL AND GROUNDS MAINTENANCE
ToCOLLIN COUNTY OFFICE
CSJ6451-33-001
Proj IDSUP - 645133001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.01083306.007500.009.0
Work Order01-01-24
Work Began01-01-24
Work Completed
Time Computed01-01-24
Contract Working Days366
Addl Days Granted0
Working Days Charged56
Percent Time Used15
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6451-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01241831
Totals83306.003750.007500.009.0

CountyCOLLIN
HighwaySH0078
FromPICNIC AREA MAINTENANCE
ToON SH0078
CSJ6454-23-001
Proj IDSUP - 645423001
Work TypePICNIC AREA MAINTENANCE
 
0.01064065.0011540.0018.0
Work Order10-01-23
Work Began10-02-23
Work Completed
Time Computed10-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged147
Percent Time Used40
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6454-23-001
LIBERTY PROCLAIMED MINISTRY (0.00)
Contract #09231833
Totals64065.001860.0011540.0018.0

CountyNAVARRO
HighwayIH0045
FromVARIOUS ROADWAYS IN THE
ToNAVARRO COUNTY MAINTENANCE SECTION
CSJ6454-25-001
Proj IDSUP - 645425001
Work TypeLITTER REMOVAL
 
0.01081128.0832011.0439.4
Work Order10-01-23
Work Began10-02-23
Work Completed
Time Computed10-02-23
Contract Working Days365
Addl Days Granted0
Working Days Charged147
Percent Time Used40
Contractor(s)
WORKQUEST
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6454-25-001
CEN-TEX ASSOCIATION FOR RETARDED CH (0.00)
Contract #09231830
Totals81128.0810849.7632011.0439.4

CountyNAVARRO
HighwaySH0031
FromNAVARRO
ToMAINTENANCE SECTION
CSJ6454-69-001
Proj IDMMC - 645469001
Work TypeAGGREGATE
 
0.010172300.0020153.9711.6
Work Order11-15-23
Work Began11-23-23
Work Completed
Time Computed11-23-23
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
ARCOSA LWS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6454-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231806
Totals172300.000.0020153.9711.6

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN
ToELLIS COUNTY - EAST
CSJ6455-07-001
Proj IDSUP - 645507001
Work TypeLITTER REMOVAL
 
0.01095664.0039852.0041.6
Work Order10-01-23
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged148
Percent Time Used40
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-07-001
A LIFT FOR LIFE OUTREACH CENTER, INC. (0.00)
Contract #09231831
Totals95664.0013284.0039852.0041.6

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN
ToELLIS COUNTY - EAST
CSJ6455-09-001
Proj IDSUP - 645509001
Work TypeLITTER REMOVAL
 
0.010201364.0072282.0035.8
Work Order10-01-23
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged148
Percent Time Used40
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09231832
Totals201364.004137.0072282.0035.8

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE
ToWEST DALLAS COUNTY MAINTENANCE
CSJ6455-11-001
Proj IDSUP - 645511001
Work TypeLITTER REMOVAL
 
0.010246515.0078712.5531.9
Work Order11-01-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged117
Percent Time Used32
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231830
Totals246515.0018236.0078712.5531.9

CountyDALLAS
HighwayIH0045
FromVARIOUS ROADWAYS IN
ToDALLAS COUNTY - EAST
CSJ6455-13-001
Proj IDSUP - 645513001
Work TypeLITTER REMOVAL
 
0.010278860.0084036.0030.1
Work Order11-08-23
Work Began11-08-23
Work Completed
Time Computed11-08-23
Contract Working Days365
Addl Days Granted0
Working Days Charged110
Percent Time Used30
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231831
Totals278860.0024252.0084036.0030.1

CountyCOLLIN
HighwaySH0205
FromVARIOUS ROADWAYS IN
ToCOLLIN COUNTY
CSJ6455-15-001
Proj IDSUP - 645515001
Work TypeLITTER REMOVAL
 
0.010367296.8485747.2323.3
Work Order00-00-00
Work Began12-06-23
Work Completed
Time Computed12-06-23
Contract Working Days365
Addl Days Granted0
Working Days Charged82
Percent Time Used22
Contractor(s)
WORKQUEST
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6455-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12231830
Totals367296.8450903.1485747.2323.3

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN
ToELLIS COUNTY
CSJ6455-19-001
Proj IDSUP - 645519001
Work TypeJANITORIAL, GROUNDS AND/OR LANDSCAPE SE
 
0.01074802.368500.5911.3
Work Order11-08-23
Work Began12-01-23
Work Completed
Time Computed11-08-23
Contract Working Days365
Addl Days Granted0
Working Days Charged88
Percent Time Used24
Contractor(s)
WORKQUEST
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10231832
Totals74802.362833.538500.5911.3

CountyROCKWALL
HighwayIH0030
FromJANITORIAL AND GROUNDS MAINTENANCE
ToFOR ROCKWALL COUNTY OFFICES
CSJ6455-90-001
Proj IDSUP - 645590001
Work TypeJANITORIAL MAINTENANCE
 
0.01028913.701521.025.2
Work Order02-01-24
Work Began02-01-24
Work Completed
Time Computed02-08-24
Contract Working Days366
Addl Days Granted0
Working Days Charged25
Percent Time Used6
Contractor(s)
WORKQUEST
U&I
SUBCONTRACTOR(S) FOR CCSJ: 6455-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01241830
Totals28913.701521.021521.025.2

page 1 | page 2 | page 3 | page 4 | page 5 | page 6