Monthly State Let Maintenance Report For Dallas District As Of Feb 10, 2017 Page 1 Of 5

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6175-73-001
Proj IDRMC - 617573001
Work TypeSWEEPING, AGGREGATE AND DEBRIS
 
0.001247147.950.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
R RESPONSE DELIVERY SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6175-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07084004
Totals247147.950.000.000.0

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN ROCKWALL AND
ToCOLLIN COUNTIES
CSJ6179-66-001
Proj IDRMC - 617966001
Work TypeVEGETATION MANAGEMENT
 
0.001138484.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days94
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ABH TREE SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6179-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11094014
Totals138484.000.000.000.0

CountyKAUFMAN
HighwayFM3094
FromFM3094 IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6263-97-001
Proj IDRMC - 626397001
Work TypeCULVERT EXTENSION & CROSS DRAINAGE
 
0.001258873.760.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-06-17
Work Began02-06-17
Work Completed
Time Computed02-13-18
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6263-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164017
Totals258873.760.000.000.0

CountyKAUFMAN
HighwayUS0175
FromVARIOUS ROADWAYS IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6263-98-001
Proj IDRMC - 626398001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001481998.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days730
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6263-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154005
Totals481998.500.000.000.0

CountyDENTON
HighwayIH0035
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6264-18-001
Proj IDRMC - 626418001
Work TypeGENERAL PAVEMENT REPAIR
 
0.0106473250.004348694.0467.1
Work Order05-12-14
Work Began05-19-14
Work Completed
Time Computed05-19-14
Contract Working Days730
Addl Days Granted548
Working Days Charged983
Percent Time Used76
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6264-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03144029
Totals6473250.0082525.774348694.0467.1

CountyDALLAS
HighwayUS0175
FromVARIOUS HIGHWAYS IN EAST DALLAS
ToAND WEST DALLAS MAINTENANCE SECTIONS
CSJ6264-63-001
Proj IDRMC - 626463001
Work TypeGENERAL ROUTINE MAINTENANCE
 
0.00118850303.0419476754.9299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-17-14
Work Began11-01-14
Work Completed
Time Computed11-01-14
Contract Working Days730
Addl Days Granted62
Working Days Charged792
Percent Time Used100
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09144009
Totals18850303.040.0019476754.9299.9

CountyDALLAS
HighwayIH0020
FromVARIOUS ROADWAYS IN EAST AND WEST
ToDALLAS COUNTY MAINTENANCE SECTIONS
CSJ6264-64-001
Proj IDRMC - 626464001
Work TypePERFORMANCE BASED MAINTENANCE
 
0.00119290130.0017575361.9491.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-08-14
Work Began11-01-14
Work Completed
Time Computed11-01-14
Contract Working Days730
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
AMEY CONSULTING USA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07144015
Totals19290130.000.0017575361.9491.1

CountyDALLAS
HighwayIH0035E
FromVARIOUS ROADWAYS IN
ToTHE DALLAS DISTRICT
CSJ6270-44-001
Proj IDRMC - 627044001
Work TypeNON-SITE SPEC RDWY ILLUMINATION
 
0.001732800.00720769.3598.3
Work Order01-14-15
Work Began01-21-15
Work Completed
Time Computed01-21-15
Contract Working Days720
Addl Days Granted30
Working Days Charged736
Percent Time Used98
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11144205
Totals732800.0064855.95720769.3598.3

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6273-83-001
Proj IDRMC - 627383001
Work TypeSPECIALTY MARKINGS
 
0.100313584.49214795.8568.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-15
Work Began05-15-15
Work Completed
Time Computed05-25-15
Contract Working Days730
Addl Days Granted0
Working Days Charged612
Percent Time Used83
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6273-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02154016
Totals313584.490.00214795.8568.4

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN THE ELLIS COUNTY
ToMAINTENANCE SECTION
CSJ6276-62-001
Proj IDRMC - 627662001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001533147.4537063.576.9
Work Order04-16-15
Work Began05-01-15
Work Completed
Time Computed05-01-15
Contract Working Days365
Addl Days Granted730
Working Days Charged635
Percent Time Used57
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6276-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02154216
Totals533147.450.0037063.576.9

CountyKAUFMAN
HighwayIH0020
FromVARIOUS LOCATIONS IN THE KAUFMAN-
ToROCKWALL MAINTENANCE SECTION
CSJ6276-71-001
Proj IDRMC - 627671001
Work TypePOTHOLE REPAIR
 
0.0012875000.00828408.9028.8
Work Order05-11-15
Work Began05-18-15
Work Completed
Time Computed05-18-15
Contract Working Days730
Addl Days Granted0
Working Days Charged618
Percent Time Used84
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6276-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154012
Totals2875000.000.00828408.9028.8

CountyKAUFMAN
HighwayIH0020
FromVARIOUS ROADWAYS IN
ToKAUFMAN COUNTY
CSJ6276-80-001
Proj IDRMC - 627680001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.001568906.90381039.2866.9
Work Order05-06-15
Work Began05-13-15
Work Completed
Time Computed05-13-15
Contract Working Days730
Addl Days Granted0
Working Days Charged624
Percent Time Used85
Contractor(s)
R RESPONSE DELIVERY SERVICE
SUBCONTRACTOR(S) FOR CCSJ: 6276-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154213
Totals568906.9020160.00381039.2866.9

CountyDENTON
HighwayIH0035W
FromIH, US, SH, LP, AND BU ROADWAYS IN THE
ToDENTON COUNTY MAINTENANCE SECTION
CSJ6277-58-001
Proj IDRMC - 627758001
Work TypePERFORMANCE BASED VEGETATION
 
0.1001853000.001019700.0055.0
Work Order03-09-15
Work Began03-09-15
Work Completed
Time Computed03-16-15
Contract Working Days1,096
Addl Days Granted0
Working Days Charged686
Percent Time Used62
Contractor(s)
MANN ROBINSON & SON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01154012
Totals1853000.0041126.401019700.0055.0

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToELLIS COUNTY
CSJ6280-68-001
Proj IDRMC - 628068001
Work TypeFLEXIBLE PVMT STRUCTURE REPAIR &
 
0.0014787375.003076999.9964.2
Work Order04-24-15
Work Began05-04-15
Work Completed
Time Computed05-04-15
Contract Working Days365
Addl Days Granted730
Working Days Charged634
Percent Time Used57
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6280-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154209
Totals4787375.00201991.363076999.9964.2

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6280-74-001
Proj IDRMC - 628074001
Work TypeCALL OUT REFLECTORIZED PAVMENT
 
0.001893845.00179151.4420.0
Work Order06-09-15
Work Began06-15-15
Work Completed
Time Computed06-16-15
Contract Working Days730
Addl Days Granted0
Working Days Charged586
Percent Time Used80
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6280-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154010
Totals893845.000.00179151.4420.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6282-57-001
Proj IDRMC - 628257001
Work TypePOTHOLE REPAIR & EDGE REPAIR
 
0.001651630.00364281.2955.9
Work Order08-12-15
Work Began08-24-15
Work Completed
Time Computed08-24-15
Contract Working Days730
Addl Days Granted0
Working Days Charged521
Percent Time Used71
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154204
Totals651630.000.00364281.2955.9

CountyDALLAS
HighwayIH0030
FromNEAR ERVAY ST
ToNORTHWEST DRIVE
CSJ6285-62-001
Proj IDRMC - 628562001
Work TypePERFORM BASE O & M OF HOV LANE &
 
11.10010595000.003618500.0034.1
Work Order09-23-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days1,460
Addl Days Granted0
Working Days Charged483
Percent Time Used33
Contractor(s)
LINDSAY CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6285-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08154010
Totals10595000.00220312.503618500.0034.1

CountyROCKWALL
HighwayIH0030
FromVARIOUS ROADWAYS IN
ToROCKWALL COUNTY
CSJ6285-83-001
Proj IDRMC - 628583001
Work TypeSWEEPING & DEBRIS REMOVAL
 
0.001376732.00201298.4553.4
Work Order09-21-15
Work Began10-01-15
Work Completed
Time Computed10-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged483
Percent Time Used66
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6285-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07154008
Totals376732.0010711.65201298.4553.4

CountyDENTON
HighwayIH0035W
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAITNENANCE SECTION
CSJ6290-32-001
Proj IDRMC - 629032001
Work TypeSWEEPING/DEBRIS REMOVAL
 
0.0011810867.00130809.557.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged87
Percent Time Used11
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6290-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164005
Totals1810867.000.00130809.557.2

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN_THE
ToELLIS COUNTY_MAINTENANCE SECTION
CSJ6290-53-001
Proj IDRMC - 629053001
Work TypeGUARDRAIL UPGRADE/REPAIR
 
0.001584050.00325110.0055.6
Work Order03-08-16
Work Began03-15-16
Work Completed
Time Computed03-15-16
Contract Working Days730
Addl Days Granted0
Working Days Charged316
Percent Time Used43
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6290-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164012
Totals584050.0048670.00325110.0055.6

page 1 | page 2 | page 3 | page 4 | page 5