Monthly State Let Construction Report For El Paso District As Of Apr 11, 2014 Page 1 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway SH 20
From BOONE STREET
To 600 FT E OF CONCEPCION ST
CSJ 0002-01-074
Proj ID NH 2011(327)
Work Type INTERSECTION IMPROVEMENTS AND REHAB
 
0.875 5607003.00 0.00 6774095.10 99.9
CountyEL PASO
Highway SH 20
From BOONE STREET
To 600 FT E OF CONCEPCION ST
CSJ 0002-01-082
Proj ID RW 2-1-82
Work Type ROW ACQUISITION
 
1.472 1053076.70 0.00 1228957.67 99.9
Work Order 10-24-11
Work Began 01-23-12
Work Completed  
Time Computed 01-23-12
Contract Working Days 240
Addl Days Granted 128
Working Days Charged 368
Percent Time Used 100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-074
TRI STATE ELECTRIC, LTD. ( 12.27%)
A BROTHERS (1.06%)
ROAD MARKINGS INC. (0.90%)
THREE C"S CONTRACTORS, INC.(0.42%)
DH UNDERGROUND, INC. (0.30%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(6.50%)
RNJ CONCRETE, INC. (2.70%)
PMI PAVEMENT MARKING, INC. (0.92%)
Contract # 09113026
Totals 6660079.70 0.00 8003052.77 99.9

CountyEL PASO
Highway SH 20
From CONCEPCION ST
To GLENWOOD ST
CSJ 0002-01-090
Proj ID C 2-1-90
Work Type ROADWAY IMPROVEMENTS
 
0.700 9768518.24 1425524.14 2307755.44 23.6
CountyEL PASO
Highway SH 20
From CONCEPCION ST
To GLENWOOD ST
CSJ 0002-01-092
Proj ID RW 2-1-92
Work Type ADJUSTMENT OF UTILITIES
 
0.700 706816.30 50703.00 50703.00 7.1
Work Order 01-06-14
Work Began 01-20-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 280
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 18
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0002-01-090
A BROTHERS (OLD PRIME) (0.90%)
BORDER DEMOLITION & ENVIRONMENTAL INC. (1.06%)
D"AMBRA STEEL SERVICES, INC. (HUB) (3.74%)
FALC ENTERPRISES, LLC(0.00%)
PALO VERDE CONSTRUCTORS(1.13%)
PAVEMENT MARKINGS INC. (0.56%)
PRIME IRRIGATION & LANDSCAPE, INC. (2.72%)
QUARRY HILLS, LTD. (0.57%)
SANCHEZ CONSTRUCTION & LANDSCAPING (2.83%)
SATARAIN CONSTRUCTION, INC.(4.66%)
TRAFFIC BARRICADE SERVICE, INC.(0.83%)
TRI STATE ELECTRIC, LTD. ( 15.64%)
HARDY HOLE DRILLING(0.36%)
PMI PAVEMENT MARKING, INC. (0.56%)
Contract # 08133020
Totals 10475334.54 1476227.14 2358458.44 22.5

CountyEL PASO
Highway SH 20
From 0.06 MI N OF HORIZON BLVD
To 0.07 MI S OF HORIZON BLDV
CSJ 0002-02-050
Proj ID STP 2013(147)
Work Type RECONSTRUCT INTERSECTION
 
0.229 1129305.88 0.00 6800.00 0.6
CountyEL PASO
Highway MH
From 0.09 MI W OF SH 20 (ALAMEDA)
To 0.06 MI W OF FM 76 (NORTH LOOP)
CSJ 8056-24-001
Proj ID STP 2009(791)
Work Type RECONSTRUCTING AND WIDENING
 
1.190 4596242.98 4350.00 1568824.72 34.1
CountyEL PASO
Highway MH
From 0.09 MI W OF SH 20 (ALAMEDA)
To 0.06 MI W OF FM 76 (NORTH LOOP)
CSJ 8056-24-003
Proj ID RW 8056-24-3
Work Type ROW ACQ., UTL. ADJ.; RELOC. ASSIST.
 
1.190 1779757.14 0.00 733982.28 41.2
Work Order 11-09-12
Work Began 07-08-13
Work Completed  
Time Computed 11-25-12
Contract Working Days 290
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 36
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 8056-24-001
HAWK CONSTRUCTION(5.97%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (0.59%)
TRI STATE ELECTRIC, LTD. (6.42%)
ALLIED PAVING CO.(0.10%)
PRIME IRRIGATION & LANDSCAPE, INC. (4.38%)
A BROTHERS MILLING, LLC(0.43%)
GREATER EL PASO SANDBLASTING (0.28%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.49%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.13%)
DH UNDERGROUND, INC. (2.04%)
Contract # 09123021
Totals 7505306.00 4350.00 2309607.00 30.7

CountyEL PASO
Highway SH 20
From AT INGLEWOOD
To .
CSJ 0002-02-052
Proj ID STP 2013(978)
Work Type INTERSECTION IMPROVEMENTS
 
1.000 235144.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-25-14
Work Began 00-00-00
Work Completed  
Time Computed 04-10-14
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0002-02-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143030
Totals 235144.68 0.00 0.00 0.0

CountyHUDSPETH
Highway IH 10
From 0.23 MI E OF FM 34
To 8.38 MI W OF FM 1111
CSJ 0002-06-051
Proj ID IM 0101(266)
Work Type INSTALL MEDIAN BARRIER
 
69.455 4277160.00 1216938.65 2903873.38 67.8
Work Order 10-17-13
Work Began 11-11-13
Work Completed  
Time Computed 11-02-13
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 52
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-06-051
HARDY HOLE DRILLING(1.99%)
LONE STAR HIGHWAY PRODUCTS, INC. ( 28.64%)
Contract # 09133041
Totals 4277160.00 1216938.65 2903873.38 67.8

CountyEL PASO
Highway FM 258
From 0.14 MI W OF SH 20 INTERSECTION
To 0.56 MI W OF SH 20 INTERSECTION
CSJ 0002-14-040
Proj ID STP 2013(941)
Work Type REPLACE STRUCTURE
 
0.420 322477.50 0.00 38601.59 11.9
Work Order 09-10-13
Work Began 00-00-00
Work Completed  
Time Computed 09-26-13
Contract Working Days 79
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-14-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133229
Totals 322477.50 0.00 38601.59 11.9

CountyBREWSTER
Highway US 67
From 0.128 MI W OF SH 118
To 0.622 MI E. OF FM 1703
CSJ 0020-11-048
Proj ID NH 2014(308)
Work Type REHABILITATION
 
2.769 4102195.56 0.00 0.00 0.0
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 02-02-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0020-11-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12133007
Totals 4102195.56 0.00 0.00 0.0

CountyEL PASO
Highway US 54
From AT LP 375
To .
CSJ 0167-01-106
Proj ID STP 1102(033)HES
Work Type IMPROVE TRAFFIC SIGNAL
 
0.100 359618.50 0.00 350591.56 97.4
CountyEL PASO
Highway LP 375
From US 54 (GATEWAY BLVD SOUTH)
To BU 54 (DYER ST)
CSJ 2552-01-036
Proj ID STP 1102(031)
Work Type CONSTRUCT MAIN LANES AND INTERCHANG
 
1.875 36214322.88 338357.14 38449583.51 99.9
CountyEL PASO
Highway LP 375
From 1 M WEST OF US 54
To US 54 (GATEWAY BLVD SOUTH)
CSJ 2552-01-038
Proj ID NH 1102(032)
Work Type CONSTRUCTION OF UNDERPASS MAINLANES
 
0.846 11122609.24 76125.86 9089240.30 81.7
CountyEL PASO
Highway LP 375
From US 54 (GATEWAY BLVD SOUTH)
To BU 54 (DYER STREET)
CSJ 2552-01-040
Proj ID NH 2011(936)
Work Type ROW ACQ & UTL ADJ
 
3.220 1970294.50 0.00 1946523.49 98.7
Work Order 05-25-11
Work Began 12-12-11
Work Completed  
Time Computed 06-10-11
Contract Working Days 504
Addl Days Granted 80
Working Days Charged 574
Percent Time Used 98
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2552-01-036
A BROTHERS MILLING, LLC(0.25%)
DANRIDGE CONSTRUCTION, LLC.(0.51%)
UNINTECH CONSULTING ENGINEERS, INC.(0.08%)
SATARAIN CONSTRUCTION, INC.(0.92%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.36%)
THREE C"S CONTRACTORS, INC.(0.16%)
HARDY HOLE DRILLING(1.40%)
HENRY TRUJILLO, INC. (0.32%)
SOUTH TEXAS PAINTING COMPANY (0.37%)
RIVER CITIES SAWING LLC(0.20%)
ROAD MARKINGS INC. (0.35%)
TRI STATE ELECTRIC, LTD. ( 10.22%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(4.42%)
STEEL EFFECTS(0.64%)
FORET COMPANIES(0.07%)
ACCURATE CORING, INC.(0.03%)
EARTH REINFORCEMENT SPECIALISTS(1.75%)
STAR CITY SEALANTS (0.01%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.31%)
BORDER DRILLING LLC(0.02%)
Contract # 04113201
Totals 49666845.12 414483.00 49835938.86 99.9

CountyEL PASO
Highway US 54
From SH 20 (ALAMEDA)
To 1 M N OF FM 2529 (MCCOMBS)
CSJ 0167-01-107
Proj ID STP 2013(044)MM
Work Type DYNAMIC MESSAGE SYS BOARDS INSTALLA
 
13.810 619752.75 0.00 635468.10 99.9
Work Order 10-12-12
Work Began 02-18-13
Work Completed  
Time Computed 02-18-13
Contract Working Days 295
Addl Days Granted 0
Working Days Charged 153
Percent Time Used 51
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-107
HARDY HOLE DRILLING(7.28%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (4.82%)
HAWK CONSTRUCTION(0.34%)
Contract # 09123023
Totals 619752.75 0.00 635468.10 99.9

CountyEL PASO
Highway US 54
From LP 375 (BORDER HIGHWAY)
To MCCOMBS
CSJ 0167-01-108
Proj ID CM 2014(024)
Work Type ALTERNATE ROUTES, PHASE II
 
14.000 1898217.38 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133221
Totals 1898217.38 0.00 0.00 0.0

CountyEL PASO
Highway US 62
From 0.663 MI W OF YARBROUGH DR INTERSEC
To 0.473 MI E OF LP 375 INTERSECTION
CSJ 0374-02-094
Proj ID C 374-2-94
Work Type WIDEN ROADWAY FROM 4 TO 6 LANE
 
5.008 5714604.40 0.00 52200.00 0.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-03-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08133025
Totals 5714604.40 0.00 52200.00 0.9

CountyEL PASO
Highway US 62
From 0.109 MI E. OF LP 375
To 4.902 MI W. OF RM 2775
CSJ 0374-02-099
Proj ID NH 2014(374)
Work Type OVERLAY
 
7.101 1920036.85 1172040.44 1172040.44 61.0
Work Order 02-19-14
Work Began 03-10-14
Work Completed  
Time Computed 03-07-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 46
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0374-02-099
BOWEN INDUSTRIAL CONTRACTORS, INC. (3.27%)
TRAFFIC BARRICADE SERVICE, INC.(0.83%)
FALC ENTERPRISES, LLC(0.54%)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.67%)
DUSTROL, INC.(1.23%)
CEMEX, INC.( 67.11%)
BLACK STALLION LB CONSTRUCTION (0.79%)
Contract # 01143008
Totals 1920036.85 1172040.44 1172040.44 61.0

CountyEL PASO
Highway SP 276
From SH 20, 0.168 MI N OF BORDERLAND RD
To SOUTH DESERT BLVD
CSJ 0608-01-001
Proj ID STP 2012(390)MM
Work Type GR, STRS, ACP, SIGN & DEL
 
2.198 12311210.24 425808.55 11877036.17 96.4
CountyEL PASO
Highway SP 276
From SH 20, 0.168 MI N OF BORDERLAND RD
To SOUTH DESERT BLVD
CSJ 0608-01-002
Proj ID STP 1102(539)MM
Work Type ROW ACQ. & UTIL ADJUST.
 
1.608 660927.00 0.00 857598.51 99.9
Work Order 10-18-12
Work Began 01-02-13
Work Completed  
Time Computed 01-02-13
Contract Working Days 576
Addl Days Granted 0
Working Days Charged 369
Percent Time Used 64
Contractor(s)
J.D. ABRAMS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0608-01-001
SATARAIN CONSTRUCTION, INC.(4.87%)
HARDY HOLE DRILLING(0.61%)
TRI STATE ELECTRIC, LTD. ( 16.69%)
ACCENT LANDSCAPE CONTRACTORS, INC. (3.41%)
A BROTHERS (OLD PRIME) (0.16%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.15%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.18%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.30%)
HENRY TRUJILLO, INC. (1.29%)
BORDER DRILLING LLC(0.02%)
WESTERN DEWATERING INC.(0.13%)
CONTRACTORS SOURCE, INC._(CSI) (0.00%)
HARDY HOLE DRILLING(0.02%)
Contract # 08123205
Totals 12972137.24 425808.55 12734634.68 98.1

CountyEL PASO
Highway FM 76
From 0.3 MI W OF THE CITY LIMITS
To 0.28 MI E OF FM 1281 (HORIZON BLVD)
CSJ 0674-01-037
Proj ID STP 2012(183)
Work Type GR, STRS & SURF
 
2.850 17477183.46 52540.95 2778159.65 15.8
CountyEL PASO
Highway FM 76
From 0.3 MILES WEST OF THE CITY LIMITS
To 0.28 MILES E. OF FM 1281 (HORIZON B
CSJ 0674-01-058
Proj ID RW 674-1-58
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 1317086.00 0.00 0.00 0.0
Work Order 01-31-12
Work Began 07-02-12
Work Completed  
Time Computed 02-01-12
Contract Working Days 510
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 25
Contractor(s)
CF JORDAN CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0674-01-037
D"AMBRA STEEL SERVICES, INC. (HUB) (8.20%)
A BROTHERS (0.24%)
PRIME IRRIGATION & LANDSCAPE, INC. (0.89%)
SANCHEZ CONSTRUCTION & LANDSCAPING (1.98%)
TRI STATE ELECTRIC, LTD. ( 11.87%)
RNJ CONCRETE, INC. (5.82%)
PALO VERDE CONSTRUCTORS(3.03%)
C & C ROAD CONSTRUCTION, INC.(1.19%)
TRAFFIC BARRICADE SERVICE, INC.(0.69%)
Contract # 12113202
Totals 18794269.46 52540.95 2778159.65 14.7

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-065
Proj ID STP 2013(862)
Work Type SIGNING PROJECT
 
62.000 656177.04 161637.49 279572.37 42.6
Work Order 01-06-14
Work Began 00-00-00
Work Completed  
Time Computed 01-22-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-065
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133020
Totals 656177.04 161637.49 279572.37 42.6

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-079
Proj ID STP 2014(375)G
Work Type STRIPING PROJECT
 
107.820 1897340.49 0.00 0.00 0.0
Work Order 02-14-14
Work Began 04-03-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-079
PAVEMENT MARKINGS INC. ( 67.11%)
Contract # 01143213
Totals 1897340.49 0.00 0.00 0.0

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-086
Proj ID STP 2013(863)
Work Type METAL BEAM GUARD FENCE / SGT UPGRADES
 
3.282 1408923.00 37161.25 330951.23 23.4
Work Order 10-24-13
Work Began 11-14-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 42
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133012
Totals 1408923.00 37161.25 330951.23 23.4

CountyEL PASO
Highway VA
From BRIDGE MAINTENANCE
To (DISTRICTWIDE)
CSJ 0924-00-093
Proj ID STP 2014(573)
Work Type BRIDGE MAINTENANCE PROJECTS
 
1.000 1390036.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-093
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143022
Totals 1390036.00 0.00 0.00 0.0

CountyEL PASO
Highway VA
From CITYWIDE
To .
CSJ 0924-06-377
Proj ID NH 2013(045)
Work Type HIGHWAY ADVISORY RADIO SYSTEM
 
0.100 340789.00 0.00 334564.50 98.1
Work Order 10-12-12
Work Began 08-13-13
Work Completed  
Time Computed 10-28-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 96
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-377
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09123218
Totals 340789.00 0.00 334564.50 98.1

CountyEL PASO
Highway VA
From CAMPESTRE ELEMENTARY
To (CITY OF SOCORRO)
CSJ 0924-06-389
Proj ID STP 2012(244)SRS
Work Type SRTS INFRASTRUCTURE PROJECT
 
8.000 2069631.03 0.00 2125989.86 99.9
Work Order 11-30-12
Work Began 01-10-13
Work Completed  
Time Computed 12-16-12
Contract Working Days 160
Addl Days Granted 42
Working Days Charged 198
Percent Time Used 98
Contractor(s)
GARCOM, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-389
TRI STATE ELECTRIC, LTD. ( 14.27%)
TEXAS BARRICADE SERVICE(2.31%)
PAVEMENT MARKINGS INC. (1.02%)
Contract # 11123010
Totals 2069631.03 0.00 2125989.86 99.9

page 1 | page 2 | page 3