Monthly State Let Construction Report For El Paso District As Of Jan 11, 2017 Page 1 Of 2

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyEL PASO
Highway SH 20
From NM STATE LINE
To SH 20 MESA
CSJ 0001-01-058
Proj ID CM 2014(902)
Work Type TRAFFIC OPERATION
 
11.100 1133585.95 0.00 1124431.20 99.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-30-14
Work Began 01-12-15
Work Completed  
Time Computed 10-16-14
Contract Working Days 60
Addl Days Granted 40
Working Days Charged 140
Percent Time Used 140
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0001-01-058
TRAFFIC BARRICADE SERVICE, INC.(3.52%)
TRI STATE ELECTRIC, LTD. ( 31.02%)
HARDY HOLE DRILLING(0.23%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (2.44%)
Contract # 07143219
Totals 1133585.95 0.00 1124431.20 99.1

CountyEL PASO
Highway US 62
From 650 FT W OF EUCALYPTUS ST
To BARCELONA DR
CSJ 0001-04-094
Proj ID NH 1502(154)
Work Type VEGETATION LANDSCAPE
 
3.618 682967.00 0.00 807208.18 99.9
Work Order 08-04-15
Work Began 04-04-16
Work Completed  
Time Computed 04-04-16
Contract Working Days 60
Addl Days Granted 40
Working Days Charged 99
Percent Time Used 99
Contractor(s)
DOUBLE H CONTRACTING INC.
SUBCONTRACTOR(S) FOR CCSJ: 0001-04-094
APACHE BARRICADE & SIGN(1.53%)
BRAVO EL PASO LANDSCAPING AND IRRIGATION (3.66%)
SATARAIN CONSTRUCTION, INC.(8.45%)
TEXAS CONCRETE AND ASPHALT, INC. ( 10.24%)
TRI STATE ELECTRIC, LTD. (2.63%)
Contract # 05153020
Totals 682967.00 0.00 807208.18 99.9

CountyHUDSPETH
Highway IH 10 ETC
From 0.117 MI S OF SH 20
To 0.8 MI E OF FM 34
CSJ 0002-05-044
Proj ID STP 2016(638)HES
Work Type TEXTURIZE SHOULDERS
 
205.104 3057663.63 0.00 2723471.46 89.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 09-26-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 160
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 42
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0002-05-044
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163217
Totals 3057663.63 0.00 2723471.46 89.0

CountyHUDSPETH
Highway IH 10
From 0.194 MI W OF FM 34
To 2.573 MI E OF FM 34
CSJ 0002-06-049
Proj ID NH 2016(464)
Work Type MILL AND INLAY
 
3.686 3107215.26 0.00 804863.32 25.9
CountyCULBERSON
Highway IH 10
From 24.04 MI W CULBERSON/JEFF DAVIS C L
To 13.2 MI W CULBERSON/JEFF DAVIS C L
CSJ 0003-02-039
Proj ID NH 2016(464)
Work Type MILL AND INLAY
 
10.838 9482866.31 183547.57 17616811.94 99.9
CountyCULBERSON
Highway IH 10
From EVERGREEN RD
To 0.3 MI W OF BORACHO STATION
CSJ 0003-02-044
Proj ID STP 2016(647)HES
Work Type TEXTURIZE SHOULDERS
 
12.754 284617.58 0.00 257368.43 90.4
CountyZERO COUNTIES
Highway  
From  
To  
CSJ 0003-03-045
Proj ID  
Work Type  
 
  0.00 13900.00 944169.60 0.0
Work Order 00-00-00
Work Began 04-14-16
Work Completed  
Time Computed 04-14-16
Contract Working Days 160
Addl Days Granted 103
Working Days Charged 200
Percent Time Used 76
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0003-02-039
A BROTHERS MILLING, LLC(1.54%)
ANTIGO CONSTRUCTION, INC.(0.14%)
PAVEMENT MARKINGS INC. (3.14%)
HENRY TRUJILLO, INC. (0.43%)
TX TINMAN ENTERPRISES, LLC.(2.22%)
FALC ENTERPRISES, LLC(1.02%)
PENHALL COMPANY(0.09%)
Contract # 01163002
Totals 12874699.15 197447.57 19623213.29 99.9

CountyHUDSPETH
Highway IH 10
From 0.20 MI W OF JCT IH 10/RM 1111
To 0.20 MI E OF JCT IH 10/RM 1111
CSJ 0002-07-046
Proj ID BR 1502(391)
Work Type BRIDGE MAINTENANCE
 
0.756 727181.00 0.00 34500.80 4.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-24-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
INTERNATIONAL EAGLE ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0002-07-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153039
Totals 727181.00 0.00 34500.80 4.7

CountyJEFF DAVIS
Highway IH 10
From 3.451 MI E OF SH 118
To 4.555 MI W OF IH 20
CSJ 0003-04-051
Proj ID NH 1602(311)
Work Type FY 2016 BRIDGE MAINTENANCE PROGRAM
 
1.992 563630.00 181825.00 513887.50 91.1
Work Order 07-27-16
Work Began 10-10-16
Work Completed  
Time Computed 10-10-16
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 66
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0003-04-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163233
Totals 563630.00 181825.00 513887.50 91.1

CountyJEFF DAVIS
Highway US 90
From CULBERSON/JEFF DAVIS COUNTY LINE
To 7.653 MI S OF FM 2017
CSJ 0020-03-019
Proj ID STP 1602(498)
Work Type ROADWAY REHABILITATION
 
9.236 3507766.37 0.00 0.00 0.0
CountyJEFF DAVIS
Highway US 90
From 7.653 MI S OF FM 2017
To 7.265 MI N OF RM 505
CSJ 0020-04-016
Proj ID STP 1602(498)
Work Type ROADWAY REHABILITATION
 
8.904 4954523.84 0.00 888001.89 17.9
CountyJEFF DAVIS
Highway US 90
From 7.265 MI N OF RM 505
To JEFF DAVIS/PRESIDIO COUNTY LINE
CSJ 0020-05-015
Proj ID STP 1602(498)
Work Type ROADWAY REHABILITATION
 
7.720 3360797.47 0.00 852118.04 25.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-08-16
Work Began 11-09-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 94
Working Days Charged 31
Percent Time Used 11
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0020-04-016
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.11%)
HENRY TRUJILLO, INC. (0.07%)
ENVIRONMENTAL SAFETY SERVICES, INC.(7.98%)
Contract # 08163206
Totals 11823087.68 0.00 1740119.93 14.7

CountyBREWSTER
Highway US 67
From JCT US 90
To 1.35 MI E OF SH 223
CSJ 0021-01-053
Proj ID NH 2017(324)
Work Type ROADWAY REHABILITATION
 
6.309 2339737.20 0.00 0.00 0.0
CountyBREWSTER
Highway US 90
From 0.298 MI E OF US 67/US 90 INTER
To 1.103 MI E OF US 67/US 90 INTER
CSJ 0021-01-055
Proj ID NH 2017(324)
Work Type FY 2016 BRIDGE MAINTENANCE PROGRAM
 
1.402 1208740.00 0.00 0.00 0.0
CountyBREWSTER
Highway US 90
From JCT US 67
To 1.63 MI E OF US 67
CSJ 0021-01-057
Proj ID NH 2017(324)
Work Type ROADWAY REHABILITATION
 
1.877 462080.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0021-01-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01173025
Totals 4010557.70 0.00 0.00 0.0

CountyBREWSTER
Highway US 90
From 6.89 MI E OF US 67
To 0.43 MI W OF US 385
CSJ 0021-02-024
Proj ID NH 2016(900)
Work Type HOT MIX SHOULDER LEVEL UP AND SC
 
51.338 5614637.07 0.00 4251254.95 75.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-16
Work Began 05-24-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 67
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0021-02-024
COX PAVING COMPANY OF TEXAS, INC.( 38.30%)
PAVEMENT MARKINGS INC. (1.26%)
Contract # 04163207
Totals 5614637.07 0.00 4251254.95 75.7

CountyEL PASO
Highway US 54
From LP 375 (BORDER HIGHWAY)
To MCCOMBS
CSJ 0167-01-108
Proj ID CM 2014(024)
Work Type ALTERNATE ROUTES, PHASE II
 
14.000 1898217.38 0.00 1634857.92 86.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-14
Work Began 04-20-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 76
Contractor(s)
TRI STATE ELECTRIC, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0167-01-108
HARDY HOLE DRILLING(0.23%)
BORDER DRILLING LLC(3.26%)
HAWK CONSTRUCTION(0.26%)
Contract # 11133221
Totals 1898217.38 0.00 1634857.92 86.1

CountyEL PASO
Highway BU 54-A
From TIGER EYE
To 0.376 MI N OF ASHLEY
CSJ 0167-02-058
Proj ID STP 2017(024)HES
Work Type INSTALL CONTINUOUS TURN LANE
 
2.493 570813.35 0.00 560253.67 98.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-07-16
Work Began 11-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 100
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0167-02-058
A BROTHERS MILLING, LLC(4.67%)
STRIPE-A-ZONE, INC.( 11.10%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (1.00%)
Contract # 09163005
Totals 570813.35 0.00 560253.67 98.1

CountyCULBERSON
Highway US 62
From 8.683 MI E OF SH 54 JUNCTION
To 19.302 MI E OF SH 54 JUNCTION
CSJ 0233-01-045
Proj ID NH 2014(850)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
33.019 6441134.87 0.00 8947190.75 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 05-11-15
Work Completed  
Time Computed 10-30-15
Contract Working Days 60
Addl Days Granted 118
Working Days Charged 152
Percent Time Used 85
Contractor(s)
ALLIED PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0233-01-045
FALC ENTERPRISES, LLC(2.26%)
COX PAVING COMPANY, L.P. ( 10.71%)
DOUBLE A CONTRACTING, L.P. (2.73%)
TRAFFIC BARRICADE SERVICE, INC.(0.69%)
WEST TEXAS RUMBLE STRIP(0.16%)
DUSTROL, INC.(0.83%)
Contract # 07143044
Totals 6441134.87 0.00 8947190.75 99.9

CountyHUDSPETH
Highway US 62
From 17.705 MI W OF RM 2317
To 2.916 MI W OF RM 2317
CSJ 0374-05-025
Proj ID STP 1502(370)HES
Work Type ADD PASSING LANES
 
30.791 3121216.06 0.00 3031046.93 97.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 10-20-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 44
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0374-05-025
PALO VERDE CONSTRUCTORS(2.77%)
BOWEN INDUSTRIAL CONTRACTORS, INC. ( 22.55%)
DUSTROL, INC.(0.96%)
Contract # 07153238
Totals 3121216.06 0.00 3031046.93 97.1

CountyJEFF DAVIS
Highway SH 166
From 8.609 MI S OF SH 118
To 9.462 MI E OF RM 505
CSJ 0415-03-021
Proj ID STP 1602(499)HES
Work Type INSTALL GUARDRAIL TO STANDARDS
 
20.780 188280.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0415-03-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163031
Totals 188280.00 0.00 0.00 0.0

CountyEL PASO
Highway FM 76
From 0.3 MI W OF THE CITY LIMITS
To 0.28 MI E OF FM 1281 (HORIZON BLVD)
CSJ 0674-01-037
Proj ID STP 2012(183)
Work Type GR, STRS & SURF
 
2.850 17477183.46 969749.83 17195238.92 98.3
CountyEL PASO
Highway FM 76
From 0.3 MILES WEST OF THE CITY LIMITS
To 0.28 MILES E. OF FM 1281 (HORIZON B
CSJ 0674-01-058
Proj ID RW 674-1-58
Work Type ACQUISITION, UTILITIES AND RELOCATI
 
0.001 1317086.00 0.00 1925257.05 99.9
Work Order 00-00-00
Work Began 07-02-12
Work Completed  
Time Computed 02-01-12
Contract Working Days 510
Addl Days Granted 129
Working Days Charged 485
Percent Time Used 75
Contractor(s)
JORDAN FOSTER CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0674-01-037
PRIME IRRIGATION & LANDSCAPE, INC. (0.89%)
SANCHEZ CONSTRUCTION & LANDSCAPING (1.98%)
TRI STATE ELECTRIC, LTD. ( 11.87%)
RNJ CONCRETE, INC. (5.82%)
PALO VERDE CONSTRUCTORS(3.03%)
C & C ROAD CONSTRUCTION, INC.(0.20%)
TRAFFIC BARRICADE SERVICE, INC.(0.69%)
HENRY TRUJILLO, INC. (1.33%)
A BROTHERS MILLING, LLC(0.24%)
PMI PAVEMENT MARKING, INC. (0.86%)
MFH ENVIRONMENTAL CORP.(0.01%)
SATARAIN CONSTRUCTION, INC.(6.32%)
D"AMBRA CONSTRUCTION CORPORATION (8.20%)
VENEGAS ENGINEERING MANAGEMENT AND CONSTRUCTION, INC.(0.27%)
HARDY HOLE DRILLING(0.04%)
Contract # 12113202
Totals 18794269.46 969749.83 19120495.97 99.9

CountyEL PASO
Highway VA
From DISTRICTWIDE
To .
CSJ 0924-00-086
Proj ID STP 2013(863)
Work Type METAL BEAM GUARD FENCE / SGT UPGRADES
 
3.282 1408923.00 9173.00 694889.98 60.0
Work Order 10-24-13
Work Began 11-14-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 408
Percent Time Used 217
Contractor(s)
SURETEC INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0924-00-086
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133012
Totals 1408923.00 9173.00 694889.98 60.0

CountyEL PASO
Highway CS
From SH 20 (ALAMEDA AVENUE)
To STILES/FRANKLIN DRIVE
CSJ 0924-06-154
Proj ID BR 2008(321)
Work Type OFF - SYSTEM BRIDGE REPLACEMENT
 
0.267 7490552.40 805354.65 5161241.23 68.9
CountyEL PASO
Highway CS
From SH 20 (ALAMEDA AVENUE)
To STILES/FRANKLIN DRIVE
CSJ 0924-06-521
Proj ID ROW 924-6-521
Work Type UTILITY ADJUSTMENT
 
0.267 357978.91 1680.00 231166.95 64.5
Work Order 05-18-16
Work Began 06-13-16
Work Completed  
Time Computed 05-31-16
Contract Working Days 218
Addl Days Granted 0
Working Days Charged 136
Percent Time Used 62
Contractor(s)
LESNA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-154
ALLEN CONCRETE, INC. (9.18%)
DH UNDERGROUND, INC. (0.64%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.11%)
HARDY HOLE DRILLING(3.65%)
TRI STATE ELECTRIC, LTD. (6.31%)
TRAFFIC BARRICADE SERVICE, INC.(1.10%)
O.D. CONSTRUCTION(3.32%)
CHOCTAW ERECTORS, INC. (5.00%)
3C&A CRANE SERVICE (0.82%)
NATIONWIDE REBAR INC (0.09%)
Contract # 01163230
Totals 7848531.31 807034.65 5392408.18 68.7

CountyEL PASO
Highway CS
From 0.35 MI S OF SH 20
To IH 10
CSJ 0924-06-311
Proj ID CBI 2012(231)
Work Type NEW LOCATION NON FREEWAY
 
3.880 15520544.41 215976.47 15660025.20 99.9
Work Order 10-06-15
Work Began 01-04-16
Work Completed  
Time Computed 01-04-16
Contract Working Days 280
Addl Days Granted 0
Working Days Charged 252
Percent Time Used 90
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-311
ZTEX CONSTRUCTION, INC.( 22.55%)
HARDY HOLE DRILLING(7.42%)
PAVEMENT MARKINGS INC. (0.35%)
PENHALL COMPANY(0.19%)
SATARAIN CONSTRUCTION, INC.(0.95%)
HAWK CONSTRUCTION(2.43%)
A BROTHERS MILLING, LLC(0.16%)
BOWEN INDUSTRIAL CONTRACTORS, INC. (0.24%)
SCOTT DERR PAINTING CO, LLC(0.23%)
EL PASO FENCE CO (0.77%)
NATIONWIDE REBAR INC (0.13%)
FALC ENTERPRISES, LLC(0.00%)
NATIONWIDE REBAR INC (0.51%)
CRANE SERVICES, INC. (0.43%)
TRI STATE ELECTRIC, LTD. (0.07%)
SJ CONCRETE PUMPING(0.04%)
CONCRETE PUMPING, INC. DBA CPI (0.06%)
Contract # 07153264
Totals 15520544.41 215976.47 15660025.20 99.9

CountyEL PASO
Highway CS
From ALBERTON AVE
To 200 FT S OF LTV RD
CSJ 0924-06-457
Proj ID STP 2015(455)MM
Work Type WIDEN ROAD
 
1.250 6591274.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-03-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. A. R. CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-457
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163204
Totals 6591274.78 0.00 0.00 0.0

CountyEL PASO
Highway VA
From EL PASO COUNTYWIDE
To .
CSJ 0924-06-491
Proj ID CM 1602(500)
Work Type REGIONAL BIKE IMPROVEMENTS (ON ST)
 
36.052 324898.83 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-06-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0924-06-491
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163221
Totals 324898.83 0.00 0.00 0.0

page 1 | page 2