Monthly State Let Construction Report For Fort Worth District As Of Oct 14, 2014 Page 1 Of 6

Last Update: Tuesday, October 14, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPARKER
Highway US 180 ETC
From SP 312
To PALO PINTO C/L
CSJ 0008-02-072
Proj ID STP 2015(068)
Work Type MICROSURFACING
 
28.155 2644391.29 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-02-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143219
Totals 2644391.29 0.00 0.00 0.0

CountyPARKER
Highway IH 20
From AT FM 1187
To .
CSJ 0008-03-103
Proj ID IMD 1102(447)
Work Type GR, HMAC, CRCP, STR, SGN, PVT MK, & SGNLS
 
0.016 4795524.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143237
Totals 4795524.90 0.00 0.00 0.0

CountyPARKER
Highway FM 1187
From OAK STREET, IN ALEDO
To IH 20 SOUTH FR RD
CSJ 0008-09-033
Proj ID STP 1102(290)
Work Type GR, BS, PAVEMENT AND STRIPING
 
2.133 11725765.52 256001.70 10592395.81 90.5
Work Order 07-12-12
Work Began 10-01-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 416
Addl Days Granted 2
Working Days Charged 434
Percent Time Used 103
Contractor(s)
MCMAHON CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0008-09-033
BROCK ENVIRONMENTAL, LLC (0.23%)
DURABLE SPECIALTIES, INC.(3.88%)
ELITE LANDSCAPE(2.03%)
HIGHWAY TECHNOLOGIES, INC. (0.69%)
KLUTZ CONSTRUCTION, LLC(7.08%)
MAS-TEK ENGINEERING & ASSOCIATES, INC. (0.30%)
ORNELAS & SON"S TRUCKING (1.67%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 18.20%)
TEX OP CONSTRUCTION, LP(1.35%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
VENUS CONSTRUCTION (8.71%)
W.O.E. CONSTRUCTION(6.07%)
SONSHINE FENCE CO(0.84%)
METROPLEX PAVEMENT MARKINGS, LLC (1.03%)
GJ SEEDING, LLC(0.10%)
C.B. SERVICES, INC.(0.60%)
STORM WATER MANAGEMENT, INC. (0.24%)
JESUS MORALES TRUCKING (0.43%)
BUYERS BARRICADES, INC.(0.18%)
J.L. STEEL REINFORCING, LLC(0.13%)
STRIPE-A-ZONE, INC.(0.69%)
Contract # 05123201
Totals 11725765.52 256001.70 10592395.81 90.5

CountyTARRANT
Highway IH 820
From 665' N OF MEADOWBROOK
To SH 180 (E. LANCASTER)
CSJ 0008-13-226
Proj ID IM 8204(287)
Work Type HMAC OVERLAY
 
4.283 3047531.02 0.00 2909091.60 95.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-13
Work Began 03-11-13
Work Completed  
Time Computed 03-11-13
Contract Working Days 92
Addl Days Granted 12
Working Days Charged 93
Percent Time Used 89
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-226
HIGHWAY TECHNOLOGIES, INC. (0.24%)
TEX OP CONSTRUCTION, LP( 11.15%)
TRP CONSTRUCTION GROUP, LLC(6.87%)
EROSION CONTROL MANAGEMENT SERVICES(0.40%)
FORTSON CONTRACTING, INC.(0.40%)
O. TREVINO CONSTRUCTION, LLC ( 12.21%)
W.O.E. CONSTRUCTION(0.96%)
BRENDA PRICE TRUCKING(0.44%)
ARK CONTRACTING SERVICES, LLC(2.10%)
Contract # 12123028
Totals 3047531.02 0.00 2909091.60 95.4

CountyTARRANT
Highway IH 820
From IH 820 RAMPS
To IH 20
CSJ 0008-13-230
Proj ID NH 1402(113)
Work Type MILL, HOT MIX OVERLAY, PVT MARKINGS
 
0.513 1297272.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-15-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-230
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08143051
Totals 1297272.03 0.00 0.00 0.0

CountyWISE
Highway US 81
From 2000' SOUTH OF SH 114
To TARRANT COUNTY LINE
CSJ 0013-08-126
Proj ID STP 2013(388)
Work Type HMAC OVERLAY
 
3.844 940340.80 68767.40 68767.40 7.3
Work Order 04-03-13
Work Began 00-00-00
Work Completed  
Time Computed 07-03-13
Contract Working Days 25
Addl Days Granted 4
Working Days Charged 3
Percent Time Used 10
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0013-08-126
O. TREVINO CONSTRUCTION, LLC (6.21%)
STRIPING TECHNOLOGY, L.P.(3.41%)
CROSSROADS, L.P. (0.41%)
DUSTROL, INC.(0.72%)
BRENDA PRICE TRUCKING(0.74%)
W.O.E. CONSTRUCTION(0.18%)
Contract # 02133229
Totals 940340.80 68767.40 68767.40 7.3

CountyWISE
Highway US 81
From US 81/@BU 81-SOUTH SIDE DECATUR
To US 81/@BU 81-SOUTH SIDE DECATUR
CSJ 0013-08-127
Proj ID NH 2013(802)
Work Type CONSTRUCT 4 LANE GRADE SEPARATION
 
2.105 12119453.03 1059518.32 5575623.01 46.0
Work Order 01-06-14
Work Began 01-20-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 543
Addl Days Granted 0
Working Days Charged 178
Percent Time Used 32
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0013-08-127
ALTUS TRAFFIC MANAGEMENT LLC (0.45%)
NORTH TEXAS CONTRACTING, INC.(4.12%)
PEACHTREE CONSTRUCTION, LTD. (3.02%)
STORM WATER MANAGEMENT, INC. (0.25%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(9.51%)
FORTSON CONTRACTING, INC.(0.77%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(2.34%)
O. TREVINO CONSTRUCTION, LLC (0.19%)
MCL CONTRACTING, LLC (0.17%)
SCOTT DERR PAINTING CO (0.16%)
STRIPING TECHNOLOGY, L.P.(1.21%)
TEXAS SHAFTS, INC. (0.48%)
W.O.E. CONSTRUCTION(1.86%)
J. E. GUZMAN CONSTRUCTION, INC.(0.33%)
BORE TECH CONSTRUCTION, LLC(0.16%)
INLET STRUCTURE SPECIALTIES LTD. (0.13%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.11%)
Contract # 08133007
Totals 12119453.03 1059518.32 5575623.01 46.0

CountyTARRANT
Highway IH 35W
From IH 820
To US 81/287 SPLIT
CSJ 0014-16-255
Proj ID IM 0355(151)
Work Type GR, BSE, DR, SURF & SIGN
 
3.580 120205602.75 2083759.69 55192272.06 45.9
CountyTARRANT
Highway IH 35W
From IH 820
To US 81/287_SPLIT
CSJ 0014-16-267
Proj ID NH 2012(657)
Work Type ROW ACQ, RELOC ASSIT, UTILITY ADJ
 
2.735 3080289.85 375478.00 2252603.77 73.1
Work Order 11-01-12
Work Began 04-29-13
Work Completed  
Time Computed 04-29-13
Contract Working Days 847
Addl Days Granted 0
Working Days Charged 418
Percent Time Used 49
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0014-16-255
JACKSON CONSTRUCTION, LTD. (2.32%)
STRIPING TECHNOLOGY, L.P.(0.53%)
USA SWPPP INSPECTIONS, INC.(0.52%)
C.B. SERVICES, INC.(0.94%)
MAVERICK PUMP SERVICES, LLC(0.04%)
W.O.E. CONSTRUCTION(0.04%)
MICA CORPORATION (5.31%)
COWBELL TRAFFIC SERVICES, INC. (0.01%)
CROSSROADS, L.P. (0.09%)
FORTSON CONTRACTING, INC.(0.38%)
HOUSTON SAWING & DRILLING(0.02%)
FOUNDATION DRILLERS, INC.(1.60%)
GREAT WESTERN ERECTORS (0.04%)
LINDAMOOD DEMOLITION, INC. (0.23%)
FARR FOUNDATION, INC.(1.86%)
DURABLE SPECIALTIES, INC.(0.36%)
NORTH TEXAS BOMANITE, INC. (0.17%)
ANTIGO CONSTRUCTION, INC.(0.15%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(0.78%)
THELIN RECYCLING COMPANY, L.P. (0.02%)
TEX OP CONSTRUCTION, LP(0.33%)
BREDA COMPANY, INC.(0.39%)
BRENDA PRICE TRUCKING(0.00%)
CHOCTAW ERECTORS, INC. (4.52%)
CLEANSERVE, INC. (0.07%)
DANRIDGE CONSTRUCTION, LLC.(0.01%)
SCOTT DERR PAINTING CO, LLC(0.28%)
MASTERPIECE GRINDING & GROOVING, LLC (0.00%)
INDUS CONSTRUCTION, L.P. (0.02%)
MENDEZ EXCAVATION(0.03%)
WEBBER BARRIER SERVICES, LLC.(4.34%)
DCCS, LLC(2.44%)
Contract # 09123201
Totals 123285892.60 2459237.69 57444875.83 46.5

CountyJOHNSON
Highway SH 174
From SOUTH OF FM 731
To UPRR RR BRIDGE IN BURLESON
CSJ 0019-01-137
Proj ID STP 2012(683)
Work Type MEDIAN AND HMAC OVERLAY
 
2.737 4068872.21 52564.41 3668714.34 91.5
Work Order 10-18-12
Work Began 02-15-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 320
Addl Days Granted 4
Working Days Charged 383
Percent Time Used 118
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0019-01-137
AXIS CONTRACTING, INC. (9.95%)
BUYERS BARRICADES, INC.(0.38%)
FORTSON CONTRACTING, INC.(0.26%)
M-CO CONSTRUCTION, INC.(1.97%)
MELS ELECTRIC, L.P.(9.05%)
PEACHTREE CONSTRUCTION, LTD. (8.00%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (9.53%)
TEX OP CONSTRUCTION, LP(5.69%)
TOTAL HIGHWAY MAINTENANCE, LLC (4.46%)
INLET STRUCTURE SPECIALTIES LTD. (0.00%)
DOWN UNDER CONSTRUCTION(0.28%)
Contract # 08123026
Totals 4068872.21 52564.41 3668714.34 91.5

CountyJOHNSON
Highway SH 174
From AT STADUIM DRIVE
To IN JOSHUA
CSJ 0019-01-139
Proj ID CC 19-1-139
Work Type GR, BS, PAVEMENT AND SIGNAL
 
0.032 308495.22 28144.95 226683.34 81.5
Work Order 11-14-13
Work Began 03-18-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 64
Addl Days Granted 1
Working Days Charged 107
Percent Time Used 164
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0019-01-139
PEACHTREE CONSTRUCTION, LTD. (5.11%)
TEX OP CONSTRUCTION, LP(1.70%)
ALTUS TRAFFIC MANAGEMENT LLC (0.91%)
ROAD MASTER STRIPING LLC (1.07%)
TX DOWN UNDER CONSTRUCTION LLC (1.13%)
Contract # 08133241
Totals 308495.22 28144.95 226683.34 81.5

CountyERATH
Highway US 67
From AT BOSQUE RIVER
To CROSSING
CSJ 0079-05-052
Proj ID NH 2014(230)
Work Type EROSION CONTROL
 
0.022 87935.00 0.00 88339.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 01-15-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 100
Contractor(s)
MANN ROBINSON & SON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0079-05-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133006
Totals 87935.00 0.00 88339.00 99.9

CountyERATH
Highway SH 267
From SH 6
To 1.57 MI N OF FM 219/EXISTING US 67
CSJ 0079-08-001
Proj ID NH 2012(668)
Work Type GRADING, DRAINAGE, STRUCTURE & PAVE
 
3.096 8735147.51 39564.56 9614877.24 99.9
Work Order 10-12-12
Work Began 11-19-12
Work Completed  
Time Computed 11-19-12
Contract Working Days 340
Addl Days Granted 111
Working Days Charged 450
Percent Time Used 99
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0079-08-001
FORTSON CONTRACTING, INC.(0.28%)
D. I. J. CONSTRUCTION, INC.(0.63%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(3.43%)
WILLIS ELECTRIC CO., LP(0.84%)
J & M CONTRACTING, COMPANY (7.04%)
WEST TEXAS RUMBLE STRIP(0.04%)
Contract # 08123210
Totals 8735147.51 39564.56 9614877.24 99.9

CountyERATH
Highway US 67
From 1.75 MI N OF COMANCHE COUNTY LINE
To SH 6
CSJ 0079-08-003
Proj ID NH 2013(949)
Work Type GRADING, DRAINAGE, STRUCTURES & PAV
 
2.790 12608803.68 399080.61 4296828.76 34.0
Work Order 10-24-13
Work Began 01-06-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 380
Addl Days Granted 0
Working Days Charged 186
Percent Time Used 48
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0079-08-003
J & M CONTRACTING, COMPANY (4.36%)
COPPELL CONSTRUCTION CO., INC. ( 24.86%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(2.54%)
SAN-ANN-CO., INC.(0.58%)
D. I. J. CONSTRUCTION, INC.(0.44%)
WEST TEXAS RUMBLE STRIP(0.03%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 08133211
Totals 12608803.68 399080.61 4296828.76 34.0

CountyHOOD
Highway US 377
From FM 167 (FALL CREEK HWY)
To OLD FM 4 (ACTON HWY)
CSJ 0080-04-095
Proj ID STP 2015(070)
Work Type HMAC OVERLAY
 
4.169 2044369.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-09-14
Work Began 00-00-00
Work Completed  
Time Computed 10-25-14
Contract Working Days 27
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0080-04-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143028
Totals 2044369.55 0.00 0.00 0.0

CountyTARRANT
Highway US 377
From WINSCOTT RD/LAKEWAY
To RM 2871; IN BENBROOK
CSJ 0080-07-089
Proj ID NH 1102(454)
Work Type LANDSCAPING
 
1.581 644260.85 0.00 998098.36 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-19-11
Work Began 11-14-11
Work Completed  
Time Computed 11-04-11
Contract Working Days 128
Addl Days Granted 79
Working Days Charged 206
Percent Time Used 99
Contractor(s)
LEGENDS LANDSCAPES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0080-07-089
DOWN UNDER CONSTRUCTION(0.27%)
MEL"S ELECTRIC SERVICE, INC. (1.76%)
Contract # 08113274
Totals 644260.85 0.00 998098.36 99.9

CountyTARRANT
Highway US 377
From IH 20
To WINSCOTT/LAKEWAY
CSJ 0080-07-094
Proj ID C 80-7-94
Work Type GR, DR, STR AND PAVEMENT
 
1.350 19065202.71 0.00 0.00 0.0
Work Order 06-23-14
Work Began 00-00-00
Work Completed  
Time Computed 07-09-14
Contract Working Days 684
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0080-07-094
DALLAS LITE AND BARRICADE INC. (0.32%)
C.B. SERVICES, INC.(0.80%)
DUSTROL, INC.(1.52%)
MELS ELECTRIC, L.P.(7.57%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 11.27%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.09%)
INDUS CONSTRUCTION, L.P. (0.72%)
CLLA GROUP, LLC(7.33%)
INLET STRUCTURE SPECIALTIES LTD. (2.64%)
STRAIGHT LINE SAWING & SEALING (0.21%)
SCOTT DERR PAINTING CO (0.00%)
WYLIE DRILLING & DRAINAGE, INC.(0.26%)
Contract # 05143004
Totals 19065202.71 0.00 0.00 0.0

CountyTARRANT
Highway SP 347
From EB (WEATHERFORD ST)@ O-K-T BR & UP
To .
CSJ 0081-01-040
Proj ID BR 2011(154)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.320 6582743.90 0.00 7396420.07 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-23-10
Work Began 06-13-11
Work Completed  
Time Computed 05-23-11
Contract Working Days 406
Addl Days Granted 220
Working Days Charged 622
Percent Time Used 99
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0081-01-040
ATS DRILLING, L.P. (3.17%)
BREDA COMPANY, INC.(1.00%)
BUYERS BARRICADES, INC.(0.34%)
CLEMONS TRUCKING (0.50%)
C.T. AND S. METALWORKS, INC. (1.66%)
ENVIRONMENTAL STANDARDS(0.42%)
FARR FOUNDATION, INC.(0.55%)
FORTSON CONTRACTING, INC.(0.36%)
MICA CORPORATION (1.98%)
RIVER CITIES SAWING, LLC (0.15%)
ROAD MASTER STRIPING LLC (0.17%)
SOUTH TEXAS PAINTING COMPANY (0.85%)
TEX OP CONSTRUCTION, LP(0.56%)
W.O.E. CONSTRUCTION(2.95%)
HOUSTON SAWING & DRILLING(0.12%)
ENGINEERED EXPLOSIVE SERVICES(0.92%)
TEXAS STAR TRANSPORT, LP (0.00%)
Contract # 09103023
Totals 6582743.90 0.00 7396420.07 99.9

CountyTARRANT
Highway US 377
From AT EAST BELKNAP STREET
To IN HALTOM CITY
CSJ 0081-01-046
Proj ID CM 1102(122)
Work Type GR, DR, SIGNAL AND PAVEMENT
 
0.451 4198919.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-25-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 236
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAGLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0081-01-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143224
Totals 4198919.20 0.00 0.00 0.0

CountyTARRANT
Highway SH 183
From COMMERCE ST.
To NICHOLS ST.
CSJ 0094-01-030
Proj ID BR 2011(705)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.459 10591980.89 153564.94 3893157.51 36.3
Work Order 12-20-11
Work Began 12-03-13
Work Completed  
Time Computed 06-18-12
Contract Working Days 524
Addl Days Granted 80
Working Days Charged 183
Percent Time Used 30
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0094-01-030
1 PRIORITY ENVIRONMENTAL SERVICES, INC.(2.21%)
BREDA COMPANY, INC.(0.92%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.25%)
ATS DRILLING, INC. (3.07%)
CONCRETE CUTTING BY BOND (0.06%)
COWTOWN TRAFFIC CONTROL, INC.(0.23%)
DUSTROL, INC.(0.16%)
FARR FOUNDATION, INC.(0.59%)
HOUSTON SAWING & DRILLING(0.08%)
K & S UTILITY CONTRACTORS, INC.(4.32%)
MELS ELECTRIC, L.P.(1.26%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY(2.14%)
SCOTT DERR PAINTING CO, LLC(0.32%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.60%)
J.L. STEEL REINFORCING, LLC(0.14%)
Contract # 08113203
Totals 10591980.89 153564.94 3893157.51 36.3

CountyTARRANT
Highway SH 10
From IH 820
To 0.23 MILE EAST OF IH 820
CSJ 0094-02-120
Proj ID CC 94-2-120
Work Type GR, BS, PAVEMENT AND TRAFFIC SIGNAL
 
0.188 306881.92 0.00 327054.14 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-06-13
Work Began 09-23-13
Work Completed  
Time Computed 06-22-13
Contract Working Days 32
Addl Days Granted 19
Working Days Charged 51
Percent Time Used 100
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0094-02-120
CROSSROADS, L.P. (1.46%)
ROAD MASTER STRIPING LLC (1.66%)
PEACHTREE CONSTRUCTION, LTD. ( 17.87%)
W.O.E. CONSTRUCTION( 16.35%)
FOUNDATION DRILLERS, INC.(0.98%)
Contract # 02133028
Totals 306881.92 0.00 327054.14 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6