Monthly State Let Construction Report For Fort Worth District As Of Aug 10, 2015 Page 1 Of 8

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPARKER
Highway US 180 ETC
From SP 312
To PALO PINTO C/L
CSJ 0008-02-072
Proj ID STP 2015(068)
Work Type MICROSURFACING
 
28.155 2644391.29 5353.00 3180686.00 99.9
Work Order 10-28-14
Work Began 11-07-14
Work Completed  
Time Computed 11-07-14
Contract Working Days 59
Addl Days Granted 3
Working Days Charged 57
Percent Time Used 91
Contractor(s)
NY-MAC ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-02-072
STRIPE-A-ZONE, INC.( 12.65%)
ALTUS TRAFFIC MANAGEMENT LLC (0.53%)
FLEX SUPPLY, LLC (0.17%)
Contract # 09143219
Totals 2644391.29 5353.00 3180686.00 99.9

CountyPARKER
Highway IH 20
From AT FM 1187
To .
CSJ 0008-03-103
Proj ID IMD 1102(447)
Work Type GR, HMAC, CRCP, STR, SGN, PVT MK, & SGNLS
 
0.016 4795524.90 130611.75 1324683.46 27.6
Work Order 10-27-14
Work Began 00-00-00
Work Completed  
Time Computed 11-12-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-03-103
W. W. FOUNDATION DRILLING, LTD.(1.02%)
DALLAS LITE AND BARRICADE INC. (0.33%)
WOLFE CONSTRUCTION GROUP, INC. (0.45%)
FORTSON CONTRACTING, INC.(0.39%)
STRIPING TECHNOLOGY, L.P.(0.76%)
EROSION CONTROL MANAGEMENT SERVICES(0.27%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(5.45%)
TEX OP CONSTRUCTION, LP(1.36%)
NORTHEASTERN PAVERS, INC.( 11.37%)
Contract # 08143237
Totals 4795524.90 130611.75 1324683.46 27.6

CountyPARKER
Highway FM 1187
From OAK STREET, IN ALEDO
To IH 20 SOUTH FR RD
CSJ 0008-09-033
Proj ID STP 1102(290)
Work Type GR, BS, PAVEMENT AND STRIPING
 
2.133 11725765.52 0.00 11461803.30 97.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-12-12
Work Began 10-01-12
Work Completed  
Time Computed 07-28-12
Contract Working Days 416
Addl Days Granted 61
Working Days Charged 477
Percent Time Used 100
Contractor(s)
MCMAHON CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0008-09-033
BROCK ENVIRONMENTAL, LLC (0.23%)
DURABLE SPECIALTIES, INC.(3.88%)
ELITE LANDSCAPE(2.03%)
HIGHWAY TECHNOLOGIES, INC. (0.69%)
KLUTZ CONSTRUCTION, LLC(7.08%)
MAS-TEK ENGINEERING & ASSOCIATES, INC. (0.30%)
ORNELAS & SON"S TRUCKING (1.67%)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY( 18.20%)
TEX OP CONSTRUCTION, LP(1.35%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
VENUS CONSTRUCTION (8.71%)
W.O.E. CONSTRUCTION(6.07%)
SONSHINE FENCE CO(0.84%)
METROPLEX PAVEMENT MARKINGS, LLC (1.03%)
GJ SEEDING, LLC(0.10%)
C.B. SERVICES, INC.(0.60%)
STORM WATER MANAGEMENT, INC. (0.24%)
JESUS MORALES TRUCKING (0.43%)
BUYERS BARRICADES, INC.(0.18%)
J.L. STEEL REINFORCING, LLC(0.13%)
STRIPE-A-ZONE, INC.(0.69%)
Contract # 05123201
Totals 11725765.52 0.00 11461803.30 97.7

CountyTARRANT
Highway IH 820
From 665' N OF MEADOWBROOK
To SH 180 (E. LANCASTER)
CSJ 0008-13-226
Proj ID IM 8204(287)
Work Type HMAC OVERLAY
 
4.283 3047531.02 0.00 2916741.60 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-29-13
Work Began 03-11-13
Work Completed 01-08-14
Time Computed 03-11-13
Contract Working Days 92
Addl Days Granted 12
Working Days Charged 93
Percent Time Used 89
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-226
HIGHWAY TECHNOLOGIES, INC. (0.24%)
TEX OP CONSTRUCTION, LP( 11.15%)
TRP CONSTRUCTION GROUP, LLC(6.87%)
EROSION CONTROL MANAGEMENT SERVICES(0.40%)
FORTSON CONTRACTING, INC.(0.40%)
O. TREVINO CONSTRUCTION, LLC ( 12.21%)
W.O.E. CONSTRUCTION(0.96%)
BRENDA PRICE TRUCKING(0.44%)
ARK CONTRACTING SERVICES, LLC(2.10%)
Contract # 12123028
Totals 3047531.02 0.00 2916741.60 100.0

CountyTARRANT
Highway IH 820
From US 287/IH 820 SPLIT
To NORTH OF SUN VALLEY DRIVE
CSJ 0008-13-229
Proj ID STP 2015(850)HES
Work Type TRAFFIC PROTECTION DEVICES
 
0.558 675364.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-01-15
Work Began 00-00-00
Work Completed  
Time Computed 07-02-15
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-229
BROCK ENVIRONMENTAL SERVICES, LLC(0.39%)
Contract # 04153238
Totals 675364.70 0.00 0.00 0.0

CountyTARRANT
Highway IH 820
From IH 820 RAMPS
To IH 20
CSJ 0008-13-230
Proj ID NH 1402(113)
Work Type MILL, HOT MIX OVERLAY, PVT MARKINGS
 
0.513 1297272.03 507914.35 936390.34 73.3
Work Order 09-15-14
Work Began 04-15-15
Work Completed  
Time Computed 03-26-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 151
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-13-230
ALTUS TRAFFIC MANAGEMENT LLC (0.33%)
O. TREVINO CONSTRUCTION, LLC ( 20.92%)
STRAIGHT LINE SAWING & SEALING (0.86%)
TEX OP CONSTRUCTION, LP( 10.58%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.35%)
Contract # 08143051
Totals 1297272.03 507914.35 936390.34 73.3

CountyTARRANT
Highway IH 20
From AT IH 20
To ON BRYANT IRVIN ROAD
CSJ 0008-16-036
Proj ID STP 1502(095)MM
Work Type GR, LIM TRT, HMA, PCCP, BRG, PAV MK
 
0.220 3864789.85 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-24-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 363
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
IEA INC.
SUBCONTRACTOR(S) FOR CCSJ: 0008-16-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153244
Totals 3864789.85 0.00 0.00 0.0

CountyWISE
Highway US 81
From MONTAGUE COUNTY LINE
To FM1655
CSJ 0013-06-042
Proj ID NH 2015(467)
Work Type HMAC OVERLAY
 
11.685 3343656.91 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-16-15
Work Began 00-00-00
Work Completed  
Time Computed 04-01-15
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0013-06-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153220
Totals 3343656.91 0.00 0.00 0.0

CountyWISE
Highway US 81
From 2000' SOUTH OF SH 114
To TARRANT COUNTY LINE
CSJ 0013-08-126
Proj ID STP 2013(388)
Work Type HMAC OVERLAY
 
3.844 940340.80 0.00 193971.20 20.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 09-22-14
Work Completed  
Time Computed 07-03-13
Contract Working Days 25
Addl Days Granted 4
Working Days Charged 10
Percent Time Used 34
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0013-08-126
O. TREVINO CONSTRUCTION, LLC (6.21%)
STRIPING TECHNOLOGY, L.P.(3.41%)
CROSSROADS, L.P. (0.41%)
DUSTROL, INC.(0.72%)
BRENDA PRICE TRUCKING(0.74%)
W.O.E. CONSTRUCTION(0.18%)
Contract # 02133229
Totals 940340.80 0.00 193971.20 20.6

CountyWISE
Highway US 81
From US 81/@BU 81-SOUTH SIDE DECATUR
To US 81/@BU 81-SOUTH SIDE DECATUR
CSJ 0013-08-127
Proj ID NH 2013(802)
Work Type CONSTRUCT 4 LANE GRADE SEPARATION
 
2.105 12119453.03 139876.31 8879616.07 73.2
Work Order 01-06-14
Work Began 01-20-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 543
Addl Days Granted 0
Working Days Charged 389
Percent Time Used 71
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0013-08-127
ALTUS TRAFFIC MANAGEMENT LLC (0.45%)
NORTH TEXAS CONTRACTING, INC.(4.12%)
PEACHTREE CONSTRUCTION, LTD. (3.02%)
STORM WATER MANAGEMENT, INC. (0.25%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(9.51%)
FORTSON CONTRACTING, INC.(0.77%)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.(2.34%)
O. TREVINO CONSTRUCTION, LLC (0.19%)
MCL CONTRACTING, LLC (0.17%)
SCOTT DERR PAINTING CO (0.16%)
STRIPING TECHNOLOGY, L.P.(1.21%)
TEXAS SHAFTS, INC. (0.48%)
W.O.E. CONSTRUCTION(1.86%)
J. E. GUZMAN CONSTRUCTION, INC.(0.33%)
BORE TECH CONSTRUCTION, LLC(0.16%)
INLET STRUCTURE SPECIALTIES LTD. (0.13%)
N.L. SCHUTTE FOUNDATION DRILLING, INC. (0.11%)
Contract # 08133007
Totals 12119453.03 139876.31 8879616.07 73.2

CountyTARRANT
Highway BU 287P
From AT FM 718 (AVONDALE HASLET ROAD)
To IN NORTH TARRANT COUNTY
CSJ 0013-10-070
Proj ID STP 2015(851)
Work Type INTERSEC.IMPRVMNT INCLD TRAF.SIGNAL
 
0.100 823422.86 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 69
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07153056
Totals 823422.86 0.00 0.00 0.0

CountyTARRANT
Highway BU 287P ETC
From BAILEY BOSWELL
To IH 820
CSJ 0013-10-081
Proj ID STP 1502(535)HES
Work Type PROFILE PAVEMENT MARKERS
 
16.737 123477.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0013-10-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153230
Totals 123477.25 0.00 0.00 0.0

CountyTARRANT
Highway US 81
From AT FM 156 (BLUE MOUND RD)
To IN FORT WORTH
CSJ 0014-15-039
Proj ID STP 2015(852)HES
Work Type INSTALL TRAFFIC SIGNAL
 
0.544 177985.19 0.00 0.00 0.0
Work Order 05-15-15
Work Began 00-00-00
Work Completed  
Time Computed 06-15-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-15-039
ROADMASTER, INC. (2.01%)
Contract # 04153040
Totals 177985.19 0.00 0.00 0.0

CountyTARRANT
Highway IH 35W
From IH 820
To US 81/287 SPLIT
CSJ 0014-16-255
Proj ID IM 0355(151)
Work Type GR, BSE, DR, SURF & SIGN
 
3.580 120205602.75 1478441.02 71004241.95 59.0
CountyTARRANT
Highway IH 35W
From IH 820
To US 81/287_SPLIT
CSJ 0014-16-267
Proj ID NH 2012(657)
Work Type ROW ACQ, RELOC ASSIT, UTILITY ADJ
 
2.735 3080289.85 0.00 2604669.54 84.5
Work Order 11-01-12
Work Began 04-29-13
Work Completed  
Time Computed 04-29-13
Contract Working Days 847
Addl Days Granted 0
Working Days Charged 663
Percent Time Used 78
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0014-16-255
JACKSON CONSTRUCTION, LTD. (2.32%)
STRIPING TECHNOLOGY, L.P.(0.53%)
USA SWPPP INSPECTIONS, INC.(0.39%)
C.B. SERVICES, INC.(0.94%)
MAVERICK PUMP SERVICES, LLC(0.04%)
W.O.E. CONSTRUCTION(0.04%)
MICA CORPORATION (5.31%)
COWBELL TRAFFIC SERVICES, INC. (0.01%)
CROSSROADS, L.P. (0.09%)
FORTSON CONTRACTING, INC.(0.38%)
HOUSTON SAWING & DRILLING(0.02%)
FOUNDATION DRILLERS, INC.(1.60%)
GREAT WESTERN ERECTORS (0.04%)
LINDAMOOD DEMOLITION, INC. (0.23%)
FARR FOUNDATION, INC.(1.86%)
DURABLE SPECIALTIES, INC.(0.36%)
NORTH TEXAS BOMANITE, INC. (0.17%)
ANTIGO CONSTRUCTION, INC.(0.15%)
CEN CONCRETE CONSTRUCTION COMPANY, INC.(0.54%)
THELIN RECYCLING COMPANY, L.P. (0.02%)
TEX OP CONSTRUCTION, LP(0.33%)
BREDA COMPANY, INC.(0.39%)
BRENDA PRICE TRUCKING(0.00%)
CHOCTAW ERECTORS, INC. (4.52%)
CLEANSERVE, INC. (0.07%)
DANRIDGE CONSTRUCTION, LLC.(0.01%)
SCOTT DERR PAINTING CO, LLC(0.28%)
MASTERPIECE GRINDING & GROOVING, LLC (0.00%)
INDUS CONSTRUCTION, L.P. (0.02%)
MENDEZ EXCAVATION(0.03%)
WEBBER BARRIER SERVICES, LLC.(4.34%)
DCCS, LLC(2.62%)
RAMBO CONTRACTING, INC.(0.06%)
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. (0.06%)
ACTION CONSTRUCTORS(0.39%)
CENTRAL NORTH CONSTRUCTION, LLC(0.07%)
Contract # 09123201
Totals 123285892.60 1478441.02 73608911.49 59.7

CountyJOHNSON
Highway IH 35W
From NB & SB IH 35 @ CR 391 & FM 916
To .
CSJ 0014-22-031
Proj ID BR 1502(330)
Work Type UPGRADE BRIDGE & APPROACH RAILING
 
0.400 1323249.06 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0014-22-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153234
Totals 1323249.06 0.00 0.00 0.0

CountyJOHNSON
Highway SH 174
From SOUTH OF FM 731
To UPRR RR BRIDGE IN BURLESON
CSJ 0019-01-137
Proj ID STP 2012(683)
Work Type MEDIAN AND HMAC OVERLAY
 
2.737 4068872.21 13879.49 4081302.31 99.9
Work Order 10-18-12
Work Began 02-15-13
Work Completed  
Time Computed 11-03-12
Contract Working Days 320
Addl Days Granted 122
Working Days Charged 477
Percent Time Used 107
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 0019-01-137
AXIS CONTRACTING, INC. (9.95%)
BUYERS BARRICADES, INC.(0.38%)
FORTSON CONTRACTING, INC.(0.26%)
M-CO CONSTRUCTION, INC.(1.97%)
MELS ELECTRIC, L.P.(9.05%)
PEACHTREE CONSTRUCTION, LTD. (8.00%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (9.53%)
TEX OP CONSTRUCTION, LP(5.69%)
TOTAL HIGHWAY MAINTENANCE, LLC (4.46%)
INLET STRUCTURE SPECIALTIES LTD. (0.87%)
DOWN UNDER CONSTRUCTION(0.28%)
Contract # 08123026
Totals 4068872.21 13879.49 4081302.31 99.9

CountyJOHNSON
Highway SH 174
From AT STADUIM DRIVE
To IN JOSHUA
CSJ 0019-01-139
Proj ID CC 19-1-139
Work Type GR, BS, PAVEMENT AND SIGNAL
 
0.032 308495.22 0.00 232351.95 100.0
Work Order 11-14-13
Work Began 03-18-14
Work Completed 03-23-15
Time Computed 11-30-13
Contract Working Days 64
Addl Days Granted 1
Working Days Charged 146
Percent Time Used 224
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0019-01-139
PEACHTREE CONSTRUCTION, LTD. (5.11%)
TEX OP CONSTRUCTION, LP(1.70%)
ALTUS TRAFFIC MANAGEMENT LLC (0.91%)
ROAD MASTER STRIPING LLC (1.07%)
TX DOWN UNDER CONSTRUCTION LLC (1.13%)
Contract # 08133241
Totals 308495.22 0.00 232351.95 100.0

CountyERATH
Highway US 67
From AT BOSQUE RIVER
To CROSSING
CSJ 0079-05-052
Proj ID NH 2014(230)
Work Type EROSION CONTROL
 
0.022 87935.00 0.00 89139.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 01-15-14
Work Completed 02-25-14
Time Computed 01-22-14
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 100
Contractor(s)
MANN ROBINSON & SON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0079-05-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133006
Totals 87935.00 0.00 89139.00 100.0

CountyERATH
Highway SH 267
From SH 6
To 1.57 MI N OF FM 219/EXISTING US 67
CSJ 0079-08-001
Proj ID NH 2012(668)
Work Type GRADING, DRAINAGE, STRUCTURE & PAVE
 
3.096 8735147.51 26798.80 9755416.86 100.0
Work Order 10-12-12
Work Began 11-19-12
Work Completed 05-25-15
Time Computed 11-19-12
Contract Working Days 340
Addl Days Granted 136
Working Days Charged 474
Percent Time Used 99
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0079-08-001
FORTSON CONTRACTING, INC.(0.28%)
D. I. J. CONSTRUCTION, INC.(0.63%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(3.43%)
WILLIS ELECTRIC CO., LP(1.83%)
J & M CONTRACTING, COMPANY (7.04%)
WEST TEXAS RUMBLE STRIP(0.04%)
Contract # 08123210
Totals 8735147.51 26798.80 9755416.86 100.0

CountyERATH
Highway US 67
From 1.75 MI N OF COMANCHE COUNTY LINE
To SH 6
CSJ 0079-08-003
Proj ID NH 2013(949)
Work Type GRADING, DRAINAGE, STRUCTURES & PAV
 
2.790 12608803.68 919260.76 10578358.31 83.8
Work Order 10-24-13
Work Began 01-06-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 380
Addl Days Granted 62
Working Days Charged 398
Percent Time Used 90
Contractor(s)
PRATER EQUIPMENT CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0079-08-003
J & M CONTRACTING, COMPANY (4.38%)
COPPELL CONSTRUCTION CO., INC. ( 24.86%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(2.54%)
SAN-ANN-CO., INC.(0.58%)
D. I. J. CONSTRUCTION, INC.(0.44%)
WEST TEXAS RUMBLE STRIP(0.03%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
RICE ENVIRONMENTAL SERVICES(0.53%)
Contract # 08133211
Totals 12608803.68 919260.76 10578358.31 83.8

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8