Monthly State Let Construction Report For Lufkin District As Of Apr 12, 2024 Page 3 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOUSTON
HighwayFM 2781
FromCR 551
ToTRINITY COUNTY LINE
CSJ2707-01-011
Proj IDF 2023(209)
Work TypeRESTORATION
 
4491439.922865452.1063.7
CountyHOUSTON
Highway0000000
FromSH 7
ToCOUNTY ROAD 551
CSJ2707-01-014
Proj IDSTP 2023(210)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
7612481.332549335.6933.4
Work Order12-08-22
Work Began01-20-23
Work Completed
Time Computed01-07-23
Contract Working Days333
Addl Days Granted0
Working Days Charged180
Percent Time Used54
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2707-01-011
STRIPING TECHNOLOGY, L.P. (2.42)
SOUTHWEST ENVIRONMENT SERVICES LLC (1.72)
DUSTIN ALLEN, INC. (0.32)
PANOLA SIGN & BARRICADE, INC. (0.50)
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.35)
CEN TEX HYDROSEED, INC. (0.93)
COLD CREEK CONSTRUCTION, LTD (4.31)
Contract #11223208
Totals12103921.25176262.755414787.7944.7

CountyANGELINA
HighwayFM 2680
FromEND OF PAVEMENT
ToUS 69
CSJ2750-01-005
Proj IDSTP 2023(393)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2660027.40919304.6834.5
Work Order04-19-23
Work Began07-18-23
Work Completed
Time Computed07-18-23
Contract Working Days114
Addl Days Granted0
Working Days Charged58
Percent Time Used50
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 2750-01-005
AMERICAN REMEDIATION OPTIONS, INC. (2.30)
A R BROTHERS CONSTRUCTION SERVICES, INC. (20.92)
PANOLA SIGN & BARRICADE, INC. (0.47)
STRIPING TECHNOLOGY, L.P. (1.90)
FREDONIA CONSTRUCTION SERVICES (0.15)
Contract #03233232
Totals2660027.408500.00919304.6834.5

CountySAN JACINTO
HighwayFM 3278
FromAT TRINITY RIVER BRIDGE
To.
CSJ3198-02-018
Proj IDBR 2B24(063)
Work TypeBRIDGE MAINTENANCE
 
1771676.600.000.0
CountyPOLK
HighwayFM 3278
FromAT TRINITY RIVER
To.
CSJ3198-03-007
Proj IDBR 2B24(063)
Work TypeBRIDGE MAINTENANCE
 
3107025.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days348
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3198-02-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243007
Totals4878702.100.000.000.0

CountyANGELINA
HighwayFM 326
From0.510 MILES NORTH OF US 69
ToUS 69
CSJ3264-01-010
Proj IDF 2023(012)
Work TypeREHABILITATION OF EXISTING ROAD
 
0.5002637474.142194322.8483.5
Work Order10-11-22
Work Began01-16-23
Work Completed
Time Computed01-09-23
Contract Working Days171
Addl Days Granted24
Working Days Charged207
Percent Time Used106
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3264-01-010
PANOLA SIGN & BARRICADE, INC. (0.54)
DUSTROL, INC. (0.42)
STRIPING TECHNOLOGY, L.P. (1.28)
PINTO CONSTRUCTION CO., INC. (11.71)
J & M CONTRACTING, COMPANY (26.56)
AMERICAN REMEDIATION OPTIONS, INC. (2.83)
AT STAFFING (0.00)
Contract #09223016
Totals2637474.14292354.652194322.8483.5

page 1 | page 2 | page 3