Monthly Local Let Maintenance Report For Lufkin District As Of Jan 11, 2017 Page 1 Of 6

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN AUGUSTINE
HighwayUS0096
FromUS 96 & VARIOUS LOCATIONS WITHIN
ToSAN AUGUSTINE MAINT SECTION
CSJ6243-02-001
Proj IDSUP - 624302001
Work TypePICNIC/GROUNDS/CURB AND GUTTER
 
0.01086588.8057479.6066.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-17-12
Work Began07-01-12
Work Completed
Time Computed07-01-12
Contract Working Days250
Addl Days Granted0
Working Days Charged151
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04121131
Totals86588.800.0057479.6066.3

CountySAN AUGUSTINE
HighwayUS0096
FromUS 96 & VARIOUS LOCATINS WITHIN
ToSAN AUGUSTINE MAINT SECTION
CSJ6243-89-001
Proj IDSUP - 624389001
Work TypeLITTER PICKUP MAINTENANCE
 
0.010261391.74257418.6398.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-07-12
Work Began08-01-12
Work Completed
Time Computed08-01-12
Contract Working Days190
Addl Days Granted0
Working Days Charged109
Percent Time Used57
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6243-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05121136
Totals261391.740.00257418.6398.4

CountyNACOGDOCHES
HighwayUS0059
FromUS 59 & VARIOUS LOCATIONS WITHIN
ToNACOGDOCHES MAINT SECTION
CSJ6244-23-001
Proj IDSUP - 624423001
Work TypeLITTER PICKUP MAINTENANCE
 
0.010208704.36151515.7872.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-10-12
Work Began08-01-12
Work Completed
Time Computed08-01-12
Contract Working Days190
Addl Days Granted0
Working Days Charged115
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6244-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05121138
Totals208704.360.00151515.7872.5

CountyTRINITY
HighwaySH0019
FromSH 19 AND VARIOUS ROADWAYS
ToIN TRINITY COUNTY
CSJ6261-02-001
Proj IDSUP - 626102001
Work TypeLITTER PICKUP
 
0.01058785.2835917.2761.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-13
Work Began08-01-13
Work Completed
Time Computed08-01-13
Contract Working Days190
Addl Days Granted0
Working Days Charged52
Percent Time Used27
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6261-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07131132
Totals58785.280.0035917.2761.0

CountySAN JACINTO
HighwayUS0059
FromUS 59 AND VARIOUS ROADWAYS
ToIN SAN JACINTO COUNTY
CSJ6261-11-001
Proj IDSUP - 626111001
Work TypeLITTER PICKUP
 
0.010141236.34110183.5578.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-13
Work Began08-01-13
Work Completed
Time Computed08-01-13
Contract Working Days190
Addl Days Granted0
Working Days Charged118
Percent Time Used62
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6261-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07131134
Totals141236.340.00110183.5578.0

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS IN
ToSAN AUGUSTINE COUNTY
CSJ6261-33-001
Proj IDSUP - 626133001
Work TypeREM/REPL DEL POST/OBJ MRK, MAILBOX
 
0.100100000.0097002.0097.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-01-13
Work Completed
Time Computed07-01-13
Contract Working Days150
Addl Days Granted0
Working Days Charged100
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06131141
Totals100000.000.0097002.0097.0

CountyANGELINA
HighwayBU0059
From1805 N. TIMBERLAND DR.
ToLUFKIN, TX
CSJ6261-53-001
Proj IDSUP - 626153001
Work TypeGROUNDS MAINT AT LUFKIN DIST.
 
0.01025400.0013335.0052.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-13
Work Began07-01-13
Work Completed
Time Computed07-01-13
Contract Working Days150
Addl Days Granted0
Working Days Charged21
Percent Time Used14
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06131132
Totals25400.000.0013335.0052.5

CountySHELBY
HighwaySH0087
FromVARIOUS LOCATIONS IN
ToSHELBY COUNTY
CSJ6262-96-001
Proj IDRMC - 626296001
Work TypeTREE REMOVAL
 
0.100334250.00556820.0099.9
Work Order01-06-14
Work Began05-05-14
Work Completed
Time Computed01-06-14
Contract Working Days175
Addl Days Granted175
Working Days Charged144
Percent Time Used41
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6262-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09131103
Totals334250.000.00556820.0099.9

CountySABINE
HighwayFM0083
FromVARIOUS LOCATIONS IN
ToSABINE COUNTY
CSJ6266-70-001
Proj IDRMC - 626670001
Work TypeCULVERT REPLACEMENT
 
0.010179810.00169656.8594.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-14
Work Began07-10-14
Work Completed
Time Computed07-01-14
Contract Working Days64
Addl Days Granted0
Working Days Charged35
Percent Time Used54
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6266-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05141108
Totals179810.000.00169656.8594.3

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS IN THE
ToSAN AUGUSTINE MAINTENANCE AREA
CSJ6267-79-001
Proj IDRMC - 626779001
Work TypeGUARD FENCE, ATTENUATOR & METAL
 
0.010118339.0085067.5171.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-03-14
Work Completed
Time Computed07-03-14
Contract Working Days200
Addl Days Granted0
Working Days Charged13
Percent Time Used6
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05141103
Totals118339.000.0085067.5171.8

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS ON US59 AND US259
ToIN VARIOUS COUNTIES
CSJ6268-54-001
Proj IDSUP - 626854001
Work TypeLARGE DEBRIS PICKUP AND REMOVAL
 
0.010293400.00295050.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-02-14
Work Began04-07-14
Work Completed03-31-15
Time Computed04-07-14
Contract Working Days120
Addl Days Granted0
Working Days Charged73
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6268-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03141130
Totals293400.000.00295050.00100.0

CountySABINE
HighwaySH0087
FromVARIOUS LOCATIONS IN THE SABINE
ToCOUNTY MAINTENANCE AREA
CSJ6272-20-001
Proj IDRMC - 627220001
Work TypeREP AND MAINT OF MBGF
 
0.010138755.40128566.0092.6
Work Order01-26-15
Work Began02-02-15
Work Completed
Time Computed02-01-15
Contract Working Days200
Addl Days Granted0
Working Days Charged29
Percent Time Used14
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07141108
Totals138755.4037880.00128566.0092.6

CountyANGELINA
HighwayUS0069
FromLOCATED WITHIN THE LUFKIN STATE
ToSUPPORTED LIVING CENTER ON US 69
CSJ6273-13-001
Proj IDRMC - 627313001
Work TypeSEAL COAT, REHAB & MISC.
 
0.010164328.00157822.0096.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began08-17-15
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged24
Percent Time Used60
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05151104
Totals164328.000.00157822.0096.0

CountySAN AUGUSTINE
HighwayUS0096
FromVARIOUS LOCATIONS WITHIN
ToSAN AUGUSTINE COUNTY
CSJ6273-35-001
Proj IDSUP - 627335001
Work TypeREMOVAL AND DISPOSAL OF LITTER ON
 
0.01078790.9261131.9377.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-30-14
Work Began06-02-14
Work Completed
Time Computed06-02-14
Contract Working Days190
Addl Days Granted0
Working Days Charged127
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05141131
Totals78790.920.0061131.9377.5

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToTHE LUFKIN DISTRICT
CSJ6274-24-001
Proj IDRMC - 627424001
Work TypeLARGE SIGN MAINTENANCE DISTRICT
 
0.010175373.4067717.2738.6
Work Order12-05-14
Work Began12-16-14
Work Completed
Time Computed12-16-14
Contract Working Days365
Addl Days Granted180
Working Days Charged533
Percent Time Used97
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09141103
Totals175373.400.0067717.2738.6

CountySHELBY
HighwayUS0096
FromVARIOUS LOCATIONS IN THE
ToSHELBY COUNTY MAINTENANCE AREA
CSJ6274-68-001
Proj IDRMC - 627468001
Work TypeGUARD FENCE, ATTENUATOR & METAL
 
0.010184237.00229825.0099.9
Work Order11-04-14
Work Began11-03-14
Work Completed
Time Computed11-10-14
Contract Working Days200
Addl Days Granted0
Working Days Charged36
Percent Time Used18
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09141109
Totals184237.002900.00229825.0099.9

CountySHELBY
HighwaySH0007
FromVARIOUS LOCATIONS WITHIN
ToSHELBY COUNTY
CSJ6275-22-001
Proj IDSUP - 627522001
Work TypeMAILBOX AND DELINEATOR MAINTENANCE
 
0.0100.0056420.130.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-14
Work Began07-01-14
Work Completed
Time Computed07-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged343
Percent Time Used93
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06141139
Totals0.000.0056420.130.0

CountyHOUSTON
HighwayUS0287
FromVARIOUS LOCATIONS WITHIN
ToHOUSTON COUNTY
CSJ6276-15-001
Proj IDRMC - 627615001
Work TypeTREE TRIMMING/TREE REMOVAL
 
0.100126280.00161715.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-23-15
Work Began02-06-15
Work Completed08-17-15
Time Computed02-01-15
Contract Working Days150
Addl Days Granted0
Working Days Charged49
Percent Time Used32
Contractor(s)
NATURAL COLORS PAINTING
SUBCONTRACTOR(S) FOR CCSJ: 6276-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10141105
Totals126280.000.00161715.00100.0

CountyANGELINA
HighwayUS0059
FromLUFKIN DISTRICT
ToOFFICE
CSJ6277-24-001
Proj IDSUP - 627724001
Work TypeWASHING AND DETAILING VEHICLES
 
0.0107193.251244.44100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-30-14
Work Began08-01-14
Work Completed09-01-15
Time Computed08-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged358
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6277-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07141136
Totals7193.250.001244.44100.0

CountySAN JACINTO
HighwayUS0059
FromVARIOUS LOCATIONS IN
ToSAN JACINTO MAINTENANCE AREA
CSJ6277-47-001
Proj IDRMC - 627747001
Work TypeTREE REMOVAL AND TRIMMING
 
0.100241000.00188820.0078.3
Work Order01-22-15
Work Began04-28-15
Work Completed
Time Computed02-02-15
Contract Working Days200
Addl Days Granted0
Working Days Charged73
Percent Time Used36
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6277-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10141106
Totals241000.0019625.00188820.0078.3

page 1 | page 2 | page 3 | page 4 | page 5 | page 6