Monthly Local Let Maintenance Report For Lufkin District As Of Nov 9, 2016 Page 1 Of 6

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountySAN AUGUSTINE
Highway US0096
From US 96 & VARIOUS LOCATIONS WITHIN
To SAN AUGUSTINE MAINT SECTION
CSJ 6243-02-001
Proj ID SUP - 624302001
Work Type PICNIC / GROUNDS / CURB AND GUTTER MAINT
 
0.010 86588.80 0.00 57479.60 66.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-17-12
Work Began 07-01-12
Work Completed  
Time Computed 07-01-12
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 151
Percent Time Used 60
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04121131
Totals 86588.80 0.00 57479.60 66.3

CountySAN AUGUSTINE
Highway US0096
From US 96 & VARIOUS LOCATINS WITHIN
To SAN AUGUSTINE MAINT SECTION
CSJ 6243-89-001
Proj ID SUP - 624389001
Work Type LITTER PICKUP MAINTENANCE
 
0.010 261391.74 0.00 257418.63 98.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-07-12
Work Began 08-01-12
Work Completed  
Time Computed 08-01-12
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 109
Percent Time Used 57
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6243-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05121136
Totals 261391.74 0.00 257418.63 98.4

CountyNACOGDOCHES
Highway US0059
From US 59 & VARIOUS LOCATIONS WITHIN
To NACOGDOCHES MAINT SECTION
CSJ 6244-23-001
Proj ID SUP - 624423001
Work Type LITTER PICKUP MAINTENANCE
 
0.010 208704.36 0.00 151515.78 72.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-10-12
Work Began 08-01-12
Work Completed  
Time Computed 08-01-12
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 60
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6244-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05121138
Totals 208704.36 0.00 151515.78 72.5

CountyTRINITY
Highway SH0019
From SH 19 AND VARIOUS ROADWAYS
To IN TRINITY COUNTY
CSJ 6261-02-001
Proj ID SUP - 626102001
Work Type LITTER PICKUP
 
0.010 58785.28 0.00 35917.27 61.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-01-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 27
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6261-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131132
Totals 58785.28 0.00 35917.27 61.0

CountySAN JACINTO
Highway US0059
From US 59 AND VARIOUS ROADWAYS
To IN SAN JACINTO COUNTY
CSJ 6261-11-001
Proj ID SUP - 626111001
Work Type LITTER PICKUP
 
0.010 141236.34 0.00 110183.55 78.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-01-13
Work Began 08-01-13
Work Completed  
Time Computed 08-01-13
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 62
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6261-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07131134
Totals 141236.34 0.00 110183.55 78.0

CountySAN AUGUSTINE
Highway US0096
From VARIOUS IN
To SAN AUGUSTINE COUNTY
CSJ 6261-33-001
Proj ID SUP - 626133001
Work Type REM / REPL DEL POST / OBJ MRK, MAILBOX UGRD /
 
0.100 100000.00 0.00 97002.00 97.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-13
Work Began 07-01-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 100
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06131141
Totals 100000.00 0.00 97002.00 97.0

CountyANGELINA
Highway BU0059
From 1805 N. TIMBERLAND DR.
To LUFKIN, TX
CSJ 6261-53-001
Proj ID SUP - 626153001
Work Type GROUNDS MAINT AT LUFKIN DIST. COMPLEX
 
0.010 25400.00 0.00 13335.00 52.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-13
Work Began 07-01-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 14
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6261-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06131132
Totals 25400.00 0.00 13335.00 52.5

CountySHELBY
Highway SH0087
From VARIOUS LOCATIONS IN
To SHELBY COUNTY
CSJ 6262-96-001
Proj ID RMC - 626296001
Work Type TREE REMOVAL
 
0.100 334250.00 0.00 556820.00 99.9
Work Order 01-06-14
Work Began 05-05-14
Work Completed  
Time Computed 01-06-14
Contract Working Days 175
Addl Days Granted 175
Working Days Charged 144
Percent Time Used 41
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6262-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09131103
Totals 334250.00 0.00 556820.00 99.9

CountySABINE
Highway FM0083
From VARIOUS LOCATIONS IN
To SABINE COUNTY
CSJ 6266-70-001
Proj ID RMC - 626670001
Work Type CULVERT REPLACEMENT
 
0.010 179810.00 0.00 169656.85 94.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-01-14
Work Began 07-10-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 54
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6266-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141108
Totals 179810.00 0.00 169656.85 94.3

CountySAN AUGUSTINE
Highway US0096
From VARIOUS LOCATIONS IN THE
To SAN AUGUSTINE MAINTENANCE AREA
CSJ 6267-79-001
Proj ID RMC - 626779001
Work Type GUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010 118339.00 0.00 85067.51 71.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-03-14
Work Completed  
Time Computed 07-03-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 6
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141103
Totals 118339.00 0.00 85067.51 71.8

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS ON US59 AND US259
To IN VARIOUS COUNTIES
CSJ 6268-54-001
Proj ID SUP - 626854001
Work Type LARGE DEBRIS PICKUP AND REMOVAL
 
0.010 293400.00 0.00 295050.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-02-14
Work Began 04-07-14
Work Completed 03-31-15
Time Computed 04-07-14
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 60
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6268-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03141130
Totals 293400.00 0.00 295050.00 100.0

CountySABINE
Highway SH0087
From VARIOUS LOCATIONS IN THE SABINE
To COUNTY MAINTENANCE AREA
CSJ 6272-20-001
Proj ID RMC - 627220001
Work Type REP AND MAINT OF MBGF
 
0.010 138755.40 0.00 51182.50 36.8
Work Order 01-26-15
Work Began 02-02-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 10
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-20-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141108
Totals 138755.40 0.00 51182.50 36.8

CountyANGELINA
Highway US0069
From LOCATED WITHIN THE LUFKIN STATE
To SUPPORTED LIVING CENTER ON US 69
CSJ 6273-13-001
Proj ID RMC - 627313001
Work Type SEAL COAT, REHAB & MISC. CONSTRUCTION
 
0.010 164328.00 0.00 157822.00 96.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 08-17-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 60
Contractor(s)
NEWMAN & KENG PAVING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05151104
Totals 164328.00 0.00 157822.00 96.0

CountySAN AUGUSTINE
Highway US0096
From VARIOUS LOCATIONS WITHIN
To SAN AUGUSTINE COUNTY
CSJ 6273-35-001
Proj ID SUP - 627335001
Work Type REMOVAL AND DISPOSAL OF LITTER ON ROW
 
0.010 78790.92 0.00 61131.93 77.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-30-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 127
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6273-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05141131
Totals 78790.92 0.00 61131.93 77.5

CountyANGELINA
Highway US0059
From VARIOUS LOCATIONS IN
To THE LUFKIN DISTRICT
CSJ 6274-24-001
Proj ID RMC - 627424001
Work Type LARGE SIGN MAINTENANCE DISTRICT WIDE
 
0.010 175373.40 0.00 67717.27 38.6
Work Order 12-05-14
Work Began 12-16-14
Work Completed  
Time Computed 12-16-14
Contract Working Days 365
Addl Days Granted 180
Working Days Charged 533
Percent Time Used 97
Contractor(s)
ANALYTICAL TECHNOLOGY CONSULTANTS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141103
Totals 175373.40 0.00 67717.27 38.6

CountySHELBY
Highway US0096
From VARIOUS LOCATIONS IN THE
To SHELBY COUNTY MAINTENANCE AREA
CSJ 6274-68-001
Proj ID RMC - 627468001
Work Type GUARD FENCE, ATTENUATOR & METAL RAIL RPR
 
0.010 184237.00 9717.50 218425.00 99.9
Work Order 11-04-14
Work Began 11-03-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 16
Contractor(s)
ACE CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09141109
Totals 184237.00 9717.50 218425.00 99.9

CountySHELBY
Highway SH0007
From VARIOUS LOCATIONS WITHIN
To SHELBY COUNTY
CSJ 6275-22-001
Proj ID SUP - 627522001
Work Type MAILBOX AND DELINEATOR MAINTENANCE
 
0.010 0.00 0.00 56420.13 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-27-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 343
Percent Time Used 93
Contractor(s)
TIBH INDUSTRIES, INC.
GATEWAY COMMUNITY PARTNERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06141139
Totals 0.00 0.00 56420.13 0.0

CountyHOUSTON
Highway US0287
From VARIOUS LOCATIONS WITHIN
To HOUSTON COUNTY
CSJ 6276-15-001
Proj ID RMC - 627615001
Work Type TREE TRIMMING / TREE REMOVAL
 
0.100 126280.00 0.00 161715.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-23-15
Work Began 02-06-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 32
Contractor(s)
NATURAL COLORS PAINTING
SUBCONTRACTOR(S) FOR CCSJ: 6276-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141105
Totals 126280.00 0.00 161715.00 99.9

CountyANGELINA
Highway US0059
From LUFKIN DISTRICT
To OFFICE
CSJ 6277-24-001
Proj ID SUP - 627724001
Work Type WASHING AND DETAILING VEHICLES
 
0.010 7193.25 0.00 1244.44 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-30-14
Work Began 08-01-14
Work Completed 09-01-15
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 358
Percent Time Used 98
Contractor(s)
TIBH INDUSTRIES, INC.
OAK CREEK DAY HABILITATION/VOCATION CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6277-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07141136
Totals 7193.25 0.00 1244.44 100.0

CountySAN JACINTO
Highway US0059
From VARIOUS LOCATIONS IN
To SAN JACINTO MAINTENANCE AREA
CSJ 6277-47-001
Proj ID RMC - 627747001
Work Type TREE REMOVAL AND TRIMMING
 
0.100 241000.00 21640.00 154265.00 64.0
Work Order 01-22-15
Work Began 04-28-15
Work Completed  
Time Computed 02-02-15
Contract Working Days 200
Addl Days Granted 0
Working Days Charged 58
Percent Time Used 29
Contractor(s)
K & R CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 6277-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10141106
Totals 241000.00 21640.00 154265.00 64.0