Monthly State Let Maintenance Report For Lufkin District As Of Feb 10, 2017 Page 1 Of 1

Last Update: Friday, February 10, 2017
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyPOLK
HighwayUS0059
FromVARIOUS ROADS IN POLK &
ToSAN JACINTO COUNTIES
CSJ6288-40-001
Proj IDRMC - 628840001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.010852421.30161238.4718.9
Work Order10-17-16
Work Began10-17-16
Work Completed
Time Computed10-17-16
Contract Working Days365
Addl Days Granted0
Working Days Charged107
Percent Time Used29
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6288-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164217
Totals852421.3048251.88161238.4718.9

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS IN ANGELINA,
ToNACOGDOCHES, & SHELBY COUNTIES
CSJ6300-04-001
Proj IDRMC - 630004001
Work TypeMILL AND INLAY
 
0.1001544078.631620251.3699.9
Work Order05-31-16
Work Began06-07-16
Work Completed
Time Computed06-07-16
Contract Working Days120
Addl Days Granted0
Working Days Charged61
Percent Time Used50
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6300-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164206
Totals1544078.630.001620251.3699.9

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS THROUGHOUT
ToLUFKIN AREA MAINTENANCE SECTIONS
CSJ6304-86-001
Proj IDRMC - 630486001
Work TypeON-CALL TRAFFIC CONTROL_SERVICES
 
0.010964900.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
NIXON ENGINEERING
SUBCONTRACTOR(S) FOR CCSJ: 6304-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164220
Totals964900.000.000.000.0

CountyNACOGDOCHES
HighwayUS0059
FromVARIOUS LOCATIONS THROUGHOUT
ToNACOGDOCHES AREA MAINT SECTIONS
CSJ6304-87-001
Proj IDRMC - 630487001
Work TypeON-CALL TRAFFIC CONTROL
 
0.0101238555.180.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-17
Work Began00-00-00
Work Completed
Time Computed02-06-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6304-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164018
Totals1238555.180.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToWITHIN THE LUFKIN DISTRICT
CSJ6309-64-001
Proj IDBPM - 630964001
Work TypeBRIDGE PREVENTATIVE MAINTENANCE
 
0.010329924.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174206
Totals329924.000.000.000.0

CountyPOLK
HighwayUS0059
FromVARIOUS LOCATIONS IN POLK & SHELBY
ToCOUNTY MAINTENANCE SECTIONS
CSJ6311-12-001
Proj IDRMC - 631112001
Work TypeMILL AND INLAY
 
0.1001257197.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6311-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174207
Totals1257197.390.000.000.0

CountyANGELINA
HighwayUS0059
FromVARIOUS LOCATIONS
ToWITHIN THE LUFKIN DISTRICT
CSJ6311-96-001
Proj IDBPM - 631196001
Work TypeBRIDGE AND SCOUR REPAIRS
 
0.010286936.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174217
Totals286936.000.000.000.0

page 1