Monthly Local Let Maintenance Report For Laredo District As Of Nov 9, 2016 Page 1 Of 4

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWEBB
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6183-29-001
Proj ID RMC - 618329001
Work Type INSTALL TRAFFIC SIGNALS, FLASHING BEACON
 
0.001 245601.35 0.00 276457.38 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-11-09
Work Began 09-21-09
Work Completed  
Time Computed 09-21-09
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07092201
Totals 245601.35 0.00 276457.38 99.9

CountyLASALLE
Highway IH0035
From IH 35 AT FM 468
To IH 35 AT FM 468
CSJ 6207-54-001
Proj ID RMC - 620754001
Work Type CONST. CONSIST. OF ROADWAY ILLUMINATION
 
0.820 127642.50 0.00 122352.90 95.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-23-10
Work Began 09-01-10
Work Completed  
Time Computed 09-01-10
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 58
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06102202
Totals 127642.50 0.00 122352.90 95.8

CountyWEBB
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6210-68-001
Proj ID RMC - 621068001
Work Type INSTALL TRAF SIG, FLASHING BEACONS, PVT.
 
0.001 236431.55 0.00 356107.46 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-24-10
Work Began 08-24-10
Work Completed  
Time Computed 08-24-10
Contract Working Days 365
Addl Days Granted 99
Working Days Charged 464
Percent Time Used 100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6210-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07102202
Totals 236431.55 0.00 356107.46 99.9

CountyWEBB
Highway IH0035
From IH 35
To IH 35
CSJ 6221-66-001
Proj ID SUP - 622166001
Work Type JANITORIAL / LANDSCAPING / LITTER PICKUP
 
0.001 251677.07 0.00 235015.95 93.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-03-11
Work Began 01-03-11
Work Completed  
Time Computed 01-03-11
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 729
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6221-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12102231
Totals 251677.07 0.00 235015.95 93.3

CountyVAL VERDE
Highway US0277
From 5.00 MI N OF US 90
To 5.37 MI N OF US 90
CSJ 6235-72-001
Proj ID RMC - 623572001
Work Type REHABILITATION OF A BRIDGE FACILITY
 
0.371 174640.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 22
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WESTCHESTER FIRE INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6235-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06122202
Totals 174640.00 0.00 0.00 0.0

CountyVAL VERDE
Highway US0090
From US 90
To US 90
CSJ 6256-00-001
Proj ID SUP - 625600001
Work Type JANITORIAL / GROUNDS / LANDSCAPING MAINTENAN
 
0.001 56598.48 0.00 51018.80 90.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6256-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132231
Totals 56598.48 0.00 51018.80 90.1

CountyWEBB
Highway IH0035
From VARIOUS
To .
CSJ 6269-76-001
Proj ID SUP - 626976001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 80486.56 0.00 77762.16 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-01-14
Work Began 02-01-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6269-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01142231
Totals 80486.56 0.00 77762.16 96.6

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6270-92-001
Proj ID RMC - 627092001
Work Type INSTALL RAISED MEDIAN, SIGNING & STRIPIN
 
0.001 298482.30 0.00 223070.60 74.7
Work Order 02-05-15
Work Began 02-09-15
Work Completed  
Time Computed 02-09-15
Contract Working Days 365
Addl Days Granted 266
Working Days Charged 620
Percent Time Used 98
Contractor(s)
GILMAR CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142201
Totals 298482.30 0.00 223070.60 74.7

CountyVAL VERDE
Highway US0090
From VARIOUS
To .
CSJ 6271-94-001
Proj ID SUP - 627194001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 23990.40 0.00 24774.40 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 00-00-00
Work Completed  
Time Computed 04-01-14
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6271-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03142231
Totals 23990.40 0.00 24774.40 99.9

CountyZAVALA
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6273-48-001
Proj ID RMC - 627348001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
264.000 255398.00 24559.86 252745.22 98.9
Work Order 12-04-14
Work Began 12-04-14
Work Completed  
Time Computed 12-04-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 667
Percent Time Used 91
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6273-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07142201
Totals 255398.00 24559.86 252745.22 98.9

CountyWEBB
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6274-84-001
Proj ID RMC - 627484001
Work Type TRAFFIC SIGNALS, FLASH BEACONS, PVT MRKG
 
0.001 369118.40 8849.00 370346.80 99.9
Work Order 04-29-15
Work Began 05-05-15
Work Completed  
Time Computed 05-05-15
Contract Working Days 365
Addl Days Granted 38
Working Days Charged 403
Percent Time Used 100
Contractor(s)
AUSTIN TRAFFIC SIGNAL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-84-001
GILMAR CONSTRUCTION, LTD.( 12.80%)
PAVEMENT MARKINGS INC. (9.85%)
GREEN LIGHT IN THE GROUND(0.78%)
Contract # 12142201
Totals 369118.40 8849.00 370346.80 99.9

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6277-44-001
Proj ID RMC - 627744001
Work Type MAINTENANCE OF LARGE SIGNS
 
0.001 234525.00 0.00 302488.98 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-23-15
Work Began 01-23-15
Work Completed  
Time Computed 01-23-15
Contract Working Days 365
Addl Days Granted 38
Working Days Charged 403
Percent Time Used 100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10142201
Totals 234525.00 0.00 302488.98 99.9

CountyZAVALA
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6279-80-001
Proj ID BPM - 627980001
Work Type REHABILITATION OF VARIOUS BRIDGE FACILIT
 
0.441 291967.40 0.00 209371.20 71.7
Work Order 05-16-16
Work Began 05-23-16
Work Completed  
Time Computed 05-23-16
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 60
Percent Time Used 75
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6279-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01162207
Totals 291967.40 0.00 209371.20 71.7

CountyWEBB
Highway US0083
From US 83
To VARIOUS
CSJ 6281-11-001
Proj ID RMC - 628111001
Work Type CLEANING AND SWEEPING OF HIGHWAYS
 
65.020 198985.20 16599.00 295865.00 99.9
Work Order 03-30-15
Work Began 04-01-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 580
Percent Time Used 79
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02152204
Totals 198985.20 16599.00 295865.00 99.9

CountyWEBB
Highway IH0035
From IH 35
To SL 20, ETC.
CSJ 6281-22-001
Proj ID RMC - 628122001
Work Type CLEANING AND SWEEPING OF HIGHWAYS
 
70.700 258121.80 18385.20 301386.80 99.9
Work Order 03-30-15
Work Began 04-01-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 365
Addl Days Granted 365
Working Days Charged 580
Percent Time Used 79
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02152203
Totals 258121.80 18385.20 301386.80 99.9

CountyKINNEY
Highway US0090
From VARIOUS
To VARIOUS
CSJ 6281-33-001
Proj ID RMC - 628133001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
202.810 243882.80 41705.76 145590.36 59.6
Work Order 12-09-15
Work Began 12-21-15
Work Completed  
Time Computed 12-21-15
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 316
Percent Time Used 43
Contractor(s)
K & M ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10152202
Totals 243882.80 41705.76 145590.36 59.6

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6281-35-001
Proj ID RMC - 628135001
Work Type TIRE RUBBER DEBRIS REMOVAL ON ROADWAYS
 
141.500 284169.60 16063.20 170933.98 60.1
Work Order 03-29-16
Work Began 04-01-16
Work Completed  
Time Computed 04-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 58
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6281-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01162202
Totals 284169.60 16063.20 170933.98 60.1

CountyVAL VERDE
Highway US0090
From US 90
To US 90
CSJ 6282-21-001
Proj ID SUP - 628221001
Work Type JANITORIAL MAINTENANCE @ DEL RIO COMPLEX
 
0.001 30190.00 1172.28 28760.81 95.2
Work Order 12-01-14
Work Began 12-01-14
Work Completed  
Time Computed 12-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 699
Percent Time Used 95
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6282-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11142231
Totals 30190.00 1172.28 28760.81 95.2

CountyDUVAL
Highway SH0016
From FREER MAINTENANCE OFFICE
To FREER MAINTENANCE OFFICE
CSJ 6283-78-001
Proj ID SUP - 628378001
Work Type JANITORIAL SERVICES / FREER MAINT. OFFICE
 
0.001 20403.96 772.39 15970.44 78.2
Work Order 01-30-15
Work Began 02-01-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 638
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01152231
Totals 20403.96 772.39 15970.44 78.2

CountyMAVERICK
Highway US0277
From EAGLE PASS MAINTENANCE OFFICE
To EAGLE PASS MAINTENANCE OFFICE
CSJ 6283-80-001
Proj ID SUP - 628380001
Work Type JANITORIAL SERVICES / EAGLE PASS MAINTENAN
 
0.001 20403.96 772.39 17153.49 84.0
Work Order 01-30-15
Work Began 02-01-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 639
Percent Time Used 87
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01152232
Totals 20403.96 772.39 17153.49 84.0

page 1 | page 2 | page 3 | page 4