Monthly Local Let Maintenance Report For Laredo District As Of Feb 10, 2017 Page 1 Of 4

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWEBB
HighwayUS0083
FromVARIOUS
ToVARIOUS
CSJ6183-29-001
Proj IDRMC - 618329001
Work TypeINSTALL TRAFFIC SIGNALS, FLASHING
 
0.001245601.35276457.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-11-09
Work Began09-21-09
Work Completed
Time Computed09-21-09
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6183-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07092201
Totals245601.350.00276457.3899.9

CountyLASALLE
HighwayIH0035
FromIH 35 AT FM 468
ToIH 35 AT FM 468
CSJ6207-54-001
Proj IDRMC - 620754001
Work TypeCONST. CONSIST. OF ROADWAY
 
0.820127642.50122352.9095.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-10
Work Began09-01-10
Work Completed
Time Computed09-01-10
Contract Working Days80
Addl Days Granted0
Working Days Charged47
Percent Time Used58
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06102202
Totals127642.500.00122352.9095.8

CountyWEBB
HighwayUS0083
FromVARIOUS
ToVARIOUS
CSJ6210-68-001
Proj IDRMC - 621068001
Work TypeINSTALL TRAF SIG, FLASHING BEACONS,
 
0.001236431.55356107.4699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-24-10
Work Began08-24-10
Work Completed
Time Computed08-24-10
Contract Working Days365
Addl Days Granted99
Working Days Charged464
Percent Time Used100
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6210-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07102202
Totals236431.550.00356107.4699.9

CountyWEBB
HighwayIH0035
FromIH 35
ToIH 35
CSJ6221-66-001
Proj IDSUP - 622166001
Work TypeJANITORIAL/LANDSCAPING/LITTER
 
0.001251677.07235015.9593.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-03-11
Work Began01-03-11
Work Completed
Time Computed01-03-11
Contract Working Days731
Addl Days Granted0
Working Days Charged729
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6221-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12102231
Totals251677.070.00235015.9593.3

CountyVAL VERDE
HighwayUS0277
From5.00 MI N OF US 90
To5.37 MI N OF US 90
CSJ6235-72-001
Proj IDRMC - 623572001
Work TypeREHABILITATION OF A BRIDGE FACILITY
 
0.371174640.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days22
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WESTCHESTER FIRE INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6235-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06122202
Totals174640.000.000.000.0

CountyVAL VERDE
HighwayUS0090
FromUS 90
ToUS 90
CSJ6256-00-001
Proj IDSUP - 625600001
Work TypeJANITORIAL/GROUNDS/LANDSCAPING
 
0.00156598.4851018.8090.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-13
Work Began04-01-13
Work Completed
Time Computed04-01-13
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6256-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02132231
Totals56598.480.0051018.8090.1

CountyWEBB
HighwayIH0035
FromVARIOUS
To.
CSJ6269-76-001
Proj IDSUP - 626976001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00180486.5677762.1696.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-14
Work Began02-01-14
Work Completed
Time Computed02-01-14
Contract Working Days365
Addl Days Granted0
Working Days Charged212
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6269-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01142231
Totals80486.560.0077762.1696.6

CountyVAL VERDE
HighwayUS0090
FromVARIOUS
To.
CSJ6271-94-001
Proj IDSUP - 627194001
Work TypeJANITORIAL, GROUNDS, LANDSCAPING
 
0.00123990.4024774.4099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-14
Work Began00-00-00
Work Completed
Time Computed04-01-14
Contract Working Days153
Addl Days Granted0
Working Days Charged122
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6271-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03142231
Totals23990.400.0024774.4099.9

CountyZAVALA
HighwayUS0083
FromVARIOUS
ToVARIOUS
CSJ6279-80-001
Proj IDBPM - 627980001
Work TypeREHABILITATION OF VARIOUS BRIDGE
 
0.441291967.40209384.0071.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began05-23-16
Work Completed
Time Computed05-23-16
Contract Working Days80
Addl Days Granted0
Working Days Charged61
Percent Time Used76
Contractor(s)
SJ&J CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6279-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162207
Totals291967.400.00209384.0071.7

CountyWEBB
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6281-11-001
Proj IDRMC - 628111001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
65.020198985.20345662.0099.9
Work Order03-30-15
Work Began04-01-15
Work Completed
Time Computed04-01-15
Contract Working Days365
Addl Days Granted365
Working Days Charged672
Percent Time Used92
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02152204
Totals198985.2016599.00345662.0099.9

CountyWEBB
HighwayIH0035
FromIH 35
ToSL 20, ETC.
CSJ6281-22-001
Proj IDRMC - 628122001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
70.700258121.80353340.7099.9
Work Order03-30-15
Work Began04-01-15
Work Completed
Time Computed04-01-15
Contract Working Days365
Addl Days Granted365
Working Days Charged672
Percent Time Used92
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02152203
Totals258121.8017241.70353340.7099.9

CountyKINNEY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6281-33-001
Proj IDRMC - 628133001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
202.810243882.80145590.3659.6
Work Order12-09-15
Work Began12-21-15
Work Completed
Time Computed12-21-15
Contract Working Days730
Addl Days Granted0
Working Days Charged408
Percent Time Used55
Contractor(s)
K & M ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10152202
Totals243882.800.00145590.3659.6

CountyWEBB
HighwayIH0035
FromVARIOUS
ToVARIOUS
CSJ6281-35-001
Proj IDRMC - 628135001
Work TypeTIRE RUBBER DEBRIS REMOVAL ON
 
141.500284169.60220769.2377.6
Work Order03-29-16
Work Began04-01-16
Work Completed
Time Computed04-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged306
Percent Time Used83
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6281-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162202
Totals284169.6015111.00220769.2377.6

CountyDUVAL
HighwaySH0016
FromFREER MAINTENANCE OFFICE
ToFREER MAINTENANCE OFFICE
CSJ6283-78-001
Proj IDSUP - 628378001
Work TypeJANITORIAL SERVICES/FREER MAINT.
 
0.00120403.9618287.6189.6
Work Order01-30-15
Work Began02-01-15
Work Completed
Time Computed02-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged730
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01152231
Totals20403.96772.3918287.6189.6

CountyMAVERICK
HighwayUS0277
FromEAGLE PASS MAINTENANCE OFFICE
ToEAGLE PASS MAINTENANCE OFFICE
CSJ6283-80-001
Proj IDSUP - 628380001
Work TypeJANITORIAL SERVICES/EAGLE PASS
 
0.00120403.9620403.9699.9
Work Order01-30-15
Work Began02-01-15
Work Completed
Time Computed02-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01152232
Totals20403.96772.3920403.9699.9

CountyVAL VERDE
HighwayUS0090
FromUS 90
ToUS 277, ETC.
CSJ6283-94-001
Proj IDSUP - 628394001
Work TypePICNIC AREA MAINTENANCE
 
0.00173486.8471050.2496.6
Work Order01-28-15
Work Began02-01-15
Work Completed
Time Computed02-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01152233
Totals73486.844682.7071050.2496.6

CountyKINNEY
HighwayUS0090
FromUS 90
ToUS 277
CSJ6283-98-001
Proj IDSUP - 628398001
Work TypePICNIC AREA MAINTENANCE
 
0.00172067.8473000.3599.9
Work Order01-30-15
Work Began02-01-15
Work Completed
Time Computed02-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged750
Percent Time Used102
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01152234
Totals72067.844410.9973000.3599.9

CountyWEBB
HighwayLP0020
FromLP 20
ToLP 20
CSJ6284-10-001
Proj IDSUP - 628410001
Work TypeLANDSCAPE MAINTENANCE SERVICE AT
 
0.00158594.0650093.5485.4
Work Order01-30-15
Work Began02-01-15
Work Completed
Time Computed02-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01152235
Totals58594.061182.6950093.5485.4

CountyWEBB
HighwaySH0255T
FromSH 255T
ToSH 255T
CSJ6284-48-001
Proj IDSUP - 628448001
Work TypeLANDSCAPE MAINTENANCE SERVICE AT
 
0.0017950.706360.5680.0
Work Order01-30-15
Work Began02-01-15
Work Completed
Time Computed02-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged731
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01152236
Totals7950.70795.076360.5680.0

CountyLASALLE
HighwayFM0468
FromCOTULLA MAINTENANCE OFFICE
ToCOTULLA MAINTENANCE OFFICE
CSJ6284-89-001
Proj IDSUP - 628489001
Work TypeJANITORIAL SERVICES - COTULLA
 
0.00115961.3015345.4296.1
Work Order02-24-15
Work Began03-01-15
Work Completed
Time Computed03-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged703
Percent Time Used96
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02152231
Totals15961.30615.8815345.4296.1