Monthly State Let Maintenance Report For Laredo District As Of Nov 9, 2016 Page 1 Of 1

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6248-35-001
Proj ID RMC - 624835001
Work Type GUARDRAIL REPAIR
 
0.001 347687.50 0.00 575790.30 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-12-13
Work Began 03-12-13
Work Completed 09-10-14
Time Computed 03-12-13
Contract Working Days 365
Addl Days Granted 142
Working Days Charged 507
Percent Time Used 100
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6248-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12124020
Totals 347687.50 0.00 575790.30 100.0

CountyVAL VERDE
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6281-40-001
Proj ID RMC - 628140001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
318.800 312486.72 32901.05 122174.05 39.0
Work Order 01-07-16
Work Began 01-11-16
Work Completed  
Time Computed 01-11-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 295
Percent Time Used 40
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6281-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11154208
Totals 312486.72 32901.05 122174.05 39.0

CountyMAVERICK
Highway BU0277N
From BU 277
To VARIOUS
CSJ 6281-43-001
Proj ID RMC - 628143001
Work Type ROADWAY MILL AND INLAY
 
2.000 2000462.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04164216
Totals 2000462.60 0.00 0.00 0.0

CountyWEBB
Highway FM2050
From VARIOUS
To VARIOUS
CSJ 6296-03-001
Proj ID RMC - 629603001
Work Type ROADWAY WIDENING AND SPOT BASE REPAIRS
 
0.001 1802459.99 41365.40 2424430.08 99.9
Work Order 05-11-16
Work Began 05-16-16
Work Completed  
Time Computed 05-16-16
Contract Working Days 244
Addl Days Granted 0
Working Days Charged 165
Percent Time Used 67
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-03-001
FLASHER EQUIPMENT COMPANY(1.85%)
JMHP, INC. (1.12%)
Contract # 03164207
Totals 1802459.99 41365.40 2424430.08 99.9

CountyLASALLE
Highway IH0035
From IH 35
To VARIOUS
CSJ 6299-01-001
Proj ID RMC - 629901001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
192.400 235030.04 0.00 57973.75 24.6
Work Order 06-06-16
Work Began 06-13-16
Work Completed  
Time Computed 06-13-16
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 141
Percent Time Used 19
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6299-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03164208
Totals 235030.04 0.00 57973.75 24.6

CountyWEBB
Highway SL0020
From VARIOUS
To VARIOUS
CSJ 6302-21-001
Proj ID RMC - 630221001
Work Type SEAL COAT TYPE WORK
 
81.212 2476343.17 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6302-21-001
FLASHER EQUIPMENT COMPANY(2.02%)
VIZCAINO, L.P. ( 22.38%)
Contract # 09164019
Totals 2476343.17 0.00 0.00 0.0

page 1