Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWEBB
HighwayIH0035
FromVARIOUS
ToVARIOUS
CSJ6248-35-001
Proj IDRMC - 624835001
Work TypeGUARDRAIL REPAIR
 
0.001347687.50575790.30100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-13
Work Began03-12-13
Work Completed09-10-14
Time Computed03-12-13
Contract Working Days365
Addl Days Granted142
Working Days Charged507
Percent Time Used100
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6248-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12124020
Totals347687.500.00575790.30100.0

CountyVAL VERDE
HighwayUS0277
FromVARIOUS
ToVARIOUS
CSJ6281-40-001
Proj IDRMC - 628140001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
318.800312486.72199742.0863.9
Work Order01-07-16
Work Began01-11-16
Work Completed
Time Computed01-11-16
Contract Working Days730
Addl Days Granted0
Working Days Charged387
Percent Time Used53
Contractor(s)
CROSBY RD CONSTRUCTION INC
SUBCONTRACTOR(S) FOR CCSJ: 6281-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154208
Totals312486.720.00199742.0863.9

CountyMAVERICK
HighwayBU0277N
FromBU 277
ToVARIOUS
CSJ6281-43-001
Proj IDRMC - 628143001
Work TypeROADWAY MILL AND INLAY
 
2.0002000462.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164216
Totals2000462.600.000.000.0

CountyWEBB
HighwayFM2050
FromVARIOUS
ToVARIOUS
CSJ6296-03-001
Proj IDRMC - 629603001
Work TypeROADWAY WIDENING AND SPOT BASE
 
0.0011802459.993083626.4299.9
Work Order05-11-16
Work Began05-16-16
Work Completed
Time Computed05-16-16
Contract Working Days244
Addl Days Granted0
Working Days Charged243
Percent Time Used99
Contractor(s)
J. CARROLL WEAVER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-03-001
FLASHER EQUIPMENT COMPANY (1.85)
JMHP, INC. (1.12)
HIGHWAY BARRICADES AND SERVICES, LLC (2.50)
Contract #03164207
Totals1802459.99250157.433083626.4299.9

CountyLASALLE
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6299-01-001
Proj IDRMC - 629901001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
192.400235030.04118389.2450.3
Work Order06-06-16
Work Began06-13-16
Work Completed
Time Computed06-13-16
Contract Working Days730
Addl Days Granted0
Working Days Charged233
Percent Time Used31
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6299-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164208
Totals235030.040.00118389.2450.3

CountyWEBB
HighwaySL0020
FromVARIOUS
ToVARIOUS
CSJ6302-21-001
Proj IDRMC - 630221001
Work TypeSEAL COAT TYPE WORK
 
81.2122476343.1728901.681.1
Work Order12-15-16
Work Began00-00-00
Work Completed
Time Computed12-15-16
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6302-21-001
FLASHER EQUIPMENT COMPANY (2.02)
VIZCAINO, L.P. (22.38)
Contract #09164019
Totals2476343.1713285.9628901.681.1

page 1