Monthly State Let Maintenance Report For Paris District As Of Dec 9, 2016 Page 1 Of 1

Last Update: Friday, December 9, 2016
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyLAMAR
Highway US0082
From US 82 W
To US 271 N
CSJ 6203-38-001
Proj ID RMC - 620338001
Work Type SEAL COAT SHOULDERS / CLEAN & SEAL JOINTS
 
3.560 372768.26 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6203-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05104002
Totals 372768.26 0.00 0.00 0.0

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS IN
To PARIS DISTRICT
CSJ 6259-31-001
Proj ID RMC - 625931001
Work Type TRAFFIC SIGNAL MAINTENANCE
 
0.001 605150.00 0.00 495402.50 81.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 04-01-14
Work Completed  
Time Computed 04-08-14
Contract Working Days 250
Addl Days Granted 240
Working Days Charged 369
Percent Time Used 75
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6259-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12134025
Totals 605150.00 0.00 495402.50 81.8

CountyHUNT
Highway FM0499
From FM 499
To IN HUNT COUNTY
CSJ 6266-53-001
Proj ID RMC - 626653001
Work Type DRAINAGE DESIGN
 
0.001 964757.00 7851.00 967214.33 99.9
Work Order 09-25-15
Work Began 10-12-15
Work Completed  
Time Computed 10-19-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 155
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6266-53-001
TOTAL HIGHWAY MAINTENANCE, LLC (0.46%)
MOORE CONSTRUCTION, INC. (6.30%)
WITHERS CONSTRUCTION, LLC(2.79%)
Contract # 07154201
Totals 964757.00 7851.00 967214.33 99.9

CountyGRAYSON
Highway US0075
From VARIOUS ROADWAYS IN GRAYSON, FANNIN,
To LAMAR, DELTA, AND RED RIVER COUNTY
CSJ 6269-45-001
Proj ID RMC - 626945001
Work Type ON CALL TY I & SPECIALTY STRIPING
 
0.001 1167978.75 90297.44 568460.76 48.6
Work Order 01-13-16
Work Began 00-00-00
Work Completed  
Time Computed 01-19-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 317
Percent Time Used 86
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6269-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11154002
Totals 1167978.75 90297.44 568460.76 48.6

CountyLAMAR
Highway US0082
From DISTRICT WIDE
To FLAGGING AND TRAFFIC CONTROL
CSJ 6272-45-001
Proj ID RMC - 627245001
Work Type ON CALL TRAFFIC CONTROL SERVICES
 
0.001 2299990.00 147759.20 4989767.08 99.9
Work Order 08-14-14
Work Began 09-02-14
Work Completed  
Time Computed 09-09-14
Contract Working Days 365
Addl Days Granted 419
Working Days Charged 783
Percent Time Used 99
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6272-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06144001
Totals 2299990.00 147759.20 4989767.08 99.9

CountyGRAYSON
Highway SH0056
From VARIOUS LOCATIONS IN
To GRAYSON COUNTY
CSJ 6281-31-001
Proj ID RMC - 628131001
Work Type HIGH EDGE REMOVAL
 
0.001 543753.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GHB EQUIPMENT COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6281-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02154001
Totals 543753.75 0.00 0.00 0.0

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN HUNT, RAINS,
To HOPKINS AND FRANKLIN COUNTIES
CSJ 6283-76-001
Proj ID RMC - 628376001
Work Type ON CALL TY I & SPECIALTY STRIPING
 
0.001 772192.15 175686.28 572010.27 74.0
Work Order 01-13-16
Work Began 00-00-00
Work Completed  
Time Computed 01-19-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 317
Percent Time Used 86
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6283-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11154003
Totals 772192.15 175686.28 572010.27 74.0

CountyLAMAR
Highway FM0137
From VARIOUS LOCATIONS IN LAMAR, RED RIVER,
To DELTA, HOPKINS, AND FRANKLIN COUNTIES
CSJ 6284-12-001
Proj ID RMC - 628412001
Work Type UPGRADE CHEVRON AND CURVE SIGNS
 
0.001 394760.50 0.00 495846.47 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-30-15
Work Began 06-29-15
Work Completed  
Time Computed 07-06-15
Contract Working Days 60
Addl Days Granted 36
Working Days Charged 120
Percent Time Used 125
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-12-001
SAMMY SMALLWOOD COMPANY( 61.88%)
Contract # 04154201
Totals 394760.50 0.00 495846.47 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS THROUGHOUT
To PARIS DISTRICT
CSJ 6284-28-001
Proj ID RMC - 628428001
Work Type ON CALL FULL DEPTH CONCRETE REPAIR
 
0.001 2123625.00 0.00 2635537.89 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-16-15
Work Began 09-14-15
Work Completed  
Time Computed 09-21-15
Contract Working Days 365
Addl Days Granted 30
Working Days Charged 365
Percent Time Used 92
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06154001
Totals 2123625.00 0.00 2635537.89 99.9

CountyGRAYSON
Highway SH0091
From VARIOUS LOCATIONS IN GRAYSON, FANNIN,
To RED RIVER AND RAINS COUNTIES
CSJ 6291-12-001
Proj ID BPM - 629112001
Work Type ENCASEMENT AND WINGWALL REPAIR / REPLACE
 
0.001 476292.00 0.00 302739.92 63.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-04-16
Work Began 04-25-16
Work Completed  
Time Computed 04-25-16
Contract Working Days 75
Addl Days Granted 10
Working Days Charged 85
Percent Time Used 100
Contractor(s)
REVEGETATION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6291-12-001
ROSS TREE SERVICE(1.07%)
S&S BRIDGE PAINTING(4.22%)
Contract # 01164201
Totals 476292.00 0.00 302739.92 63.5

CountyLAMAR
Highway US0082
From LAMAR, DELTA, RED RIVER
To GRAYSON, FANNIN COUNTIES
CSJ 6292-43-001
Proj ID RMC - 629243001
Work Type ON CALL STRIPING
 
0.001 633100.00 27678.82 121551.51 19.1
Work Order 01-13-16
Work Began 00-00-00
Work Completed  
Time Computed 01-19-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 317
Percent Time Used 86
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6292-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11154201
Totals 633100.00 27678.82 121551.51 19.1

CountyHUNT
Highway IH0030
From VARIOUS LOCATIONS IN HUNT, RAINS,
To HOPKINS AND FRANKLIN COUNTIES
CSJ 6292-44-001
Proj ID RMC - 629244001
Work Type ON CALL TY II STRIPING
 
0.001 427700.00 0.00 80330.93 18.7
Work Order 01-13-16
Work Began 00-00-00
Work Completed  
Time Computed 01-15-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 321
Percent Time Used 87
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11154001
Totals 427700.00 0.00 80330.93 18.7

CountyLAMAR
Highway US0082
From PARIS DISTRICT
To ALL LOCATIONS
CSJ 6292-45-001
Proj ID RMC - 629245001
Work Type ON CALL RPM'S
 
0.001 294594.00 90760.95 199526.99 67.7
Work Order 01-07-16
Work Began 00-00-00
Work Completed  
Time Computed 01-15-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 320
Percent Time Used 87
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11154202
Totals 294594.00 90760.95 199526.99 67.7

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS THROUGHOUT ENTIRE
To PARIS DISTRICT
CSJ 6293-14-001
Proj ID RMC - 629314001
Work Type ON CALL MILL & INLAY
 
0.001 5790782.50 0.00 7146080.23 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-29-15
Work Began 00-00-00
Work Completed  
Time Computed 01-11-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 303
Percent Time Used 83
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6293-14-001
TEX OP CONSTRUCTION, LP(4.61%)
Contract # 10154001
Totals 5790782.50 0.00 7146080.23 99.9

CountyGRAYSON
Highway US0082
From COOKE COUNTY LINE TO
To FM 1417 IN GRAYSON COUNTY
CSJ 6299-52-001
Proj ID RMC - 629952001
Work Type MILL & HOTMIX INLAY
 
0.001 887245.20 11160.00 978538.55 99.9
Work Order 06-21-16
Work Began 06-27-16
Work Completed  
Time Computed 06-27-16
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 196
Contractor(s)
OVERLAND CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6299-52-001
TOTAL HIGHWAY MAINTENANCE, LLC (4.40%)
Contract # 04164201
Totals 887245.20 11160.00 978538.55 99.9

CountyHOPKINS
Highway IH0030
From VARIOUS LOCATIONS IN HOPKINS, FRANKLIN,
To LAMAR, DELAT, AND RED RIVER COUNTIES
CSJ 6300-57-001
Proj ID RMC - 630057001
Work Type ON CALL FULL DEPTH CONCRETE REPAIR
 
0.001 1571293.00 0.00 0.00 0.0
Work Order 10-20-16
Work Began 00-00-00
Work Completed  
Time Computed 11-08-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07164201
Totals 1571293.00 0.00 0.00 0.0

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS THROUGHOUT ENTIRE
To PARIS DISTRICT
CSJ 6301-86-001
Proj ID RMC - 630186001
Work Type ON CALL TRAFFIC CONTROL SERVICES
 
0.001 2302678.75 108035.60 108035.60 4.6
Work Order 10-10-16
Work Began 00-00-00
Work Completed  
Time Computed 11-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6301-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08164201
Totals 2302678.75 108035.60 108035.60 4.6

CountyGRAYSON
Highway US0075
From VARIOUS LOCATIONS IN GRAYSON, FANNIN,
To HUNT COUNTIES
CSJ 6302-68-001
Proj ID RMC - 630268001
Work Type ON CALL FULL DEPTH CONCRETE REPAIR
 
0.001 1369980.00 0.00 609949.26 44.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-19-16
Work Began 00-00-00
Work Completed  
Time Computed 09-23-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 16
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07164001
Totals 1369980.00 0.00 609949.26 44.5

CountyLAMAR
Highway US0082
From VARIOUS LOCATIONS THROUGHOUT
To PARIS DISTRICT
CSJ 6308-45-001
Proj ID RMC - 630845001
Work Type ON CALL MILL AND INLAY
 
0.001 4370668.54 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11164001
Totals 4370668.54 0.00 0.00 0.0