Monthly State Let Maintenance Report For Paris District As Of Jan 11, 2017 Page 1 Of 1

Last Update: Thursday, January 12, 2017
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLAMAR
HighwayUS0082
FromUS 82 W
ToUS 271 N
CSJ6203-38-001
Proj IDRMC - 620338001
Work TypeSEAL COAT SHOULDERS/CLEAN & SEAL
 
3.560372768.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6203-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05104002
Totals372768.260.000.000.0

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN
ToPARIS DISTRICT
CSJ6259-31-001
Proj IDRMC - 625931001
Work TypeTRAFFIC SIGNAL MAINTENANCE
 
0.001605150.00529583.0087.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-01-14
Work Began04-01-14
Work Completed
Time Computed04-08-14
Contract Working Days250
Addl Days Granted240
Working Days Charged388
Percent Time Used79
Contractor(s)
NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6259-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12134025
Totals605150.000.00529583.0087.5

CountyHUNT
HighwayFM0499
FromFM 499
ToIN HUNT COUNTY
CSJ6266-53-001
Proj IDRMC - 626653001
Work TypeDRAINAGE DESIGN
 
0.001964757.00967214.3399.9
Work Order09-25-15
Work Began10-12-15
Work Completed
Time Computed10-19-15
Contract Working Days60
Addl Days Granted0
Working Days Charged93
Percent Time Used155
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6266-53-001
TOTAL HIGHWAY MAINTENANCE, LLC (0.46)
MOORE CONSTRUCTION, INC. (6.30)
WITHERS CONSTRUCTION, LLC (2.79)
Contract #07154201
Totals964757.000.00967214.3399.9

CountyGRAYSON
HighwayUS0075
FromVARIOUS ROADWAYS IN GRAYSON, FANNIN,
ToLAMAR, DELTA, AND RED RIVER COUNTY
CSJ6269-45-001
Proj IDRMC - 626945001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.0011167978.75607772.3852.0
Work Order01-13-16
Work Began00-00-00
Work Completed
Time Computed01-19-16
Contract Working Days365
Addl Days Granted365
Working Days Charged348
Percent Time Used47
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6269-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154002
Totals1167978.7539311.62607772.3852.0

CountyLAMAR
HighwayUS0082
FromDISTRICT WIDE
ToFLAGGING AND TRAFFIC CONTROL
CSJ6272-45-001
Proj IDRMC - 627245001
Work TypeON CALL TRAFFIC CONTROL SERVICES
 
0.0012299990.004989767.0899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-14-14
Work Began09-02-14
Work Completed
Time Computed09-09-14
Contract Working Days365
Addl Days Granted419
Working Days Charged783
Percent Time Used99
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6272-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06144001
Totals2299990.000.004989767.0899.9

CountyGRAYSON
HighwaySH0056
FromVARIOUS LOCATIONS IN
ToGRAYSON COUNTY
CSJ6281-31-001
Proj IDRMC - 628131001
Work TypeHIGH EDGE REMOVAL
 
0.001543753.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GHB EQUIPMENT COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6281-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02154001
Totals543753.750.000.000.0

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN HUNT, RAINS,
ToHOPKINS AND FRANKLIN COUNTIES
CSJ6283-76-001
Proj IDRMC - 628376001
Work TypeON CALL TY I & SPECIALTY STRIPING
 
0.001772192.15634907.3782.2
Work Order01-13-16
Work Began00-00-00
Work Completed
Time Computed01-19-16
Contract Working Days365
Addl Days Granted365
Working Days Charged348
Percent Time Used47
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6283-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154003
Totals772192.1562897.10634907.3782.2

CountyLAMAR
HighwayFM0137
FromVARIOUS LOCATIONS IN LAMAR, RED RIVER,
ToDELTA, HOPKINS, AND FRANKLIN COUNTIES
CSJ6284-12-001
Proj IDRMC - 628412001
Work TypeUPGRADE CHEVRON AND CURVE SIGNS
 
0.001394760.50520075.8499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-30-15
Work Began06-29-15
Work Completed
Time Computed07-06-15
Contract Working Days60
Addl Days Granted36
Working Days Charged120
Percent Time Used125
Contractor(s)
SAMMY GIST ENTERPRISES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-12-001
SAMMY SMALLWOOD COMPANY (61.88)
Contract #04154201
Totals394760.500.00520075.8499.9

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS THROUGHOUT
ToPARIS DISTRICT
CSJ6284-28-001
Proj IDRMC - 628428001
Work TypeON CALL FULL DEPTH CONCRETE REPAIR
 
0.0012123625.002635537.8999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-15
Work Began09-14-15
Work Completed
Time Computed09-21-15
Contract Working Days365
Addl Days Granted30
Working Days Charged365
Percent Time Used92
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154001
Totals2123625.000.002635537.8999.9

CountyGRAYSON
HighwaySH0091
FromVARIOUS LOCATIONS IN GRAYSON, FANNIN,
ToRED RIVER AND RAINS COUNTIES
CSJ6291-12-001
Proj IDBPM - 629112001
Work TypeENCASEMENT AND WINGWALL
 
0.001476292.00302739.9263.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-04-16
Work Began04-25-16
Work Completed
Time Computed04-25-16
Contract Working Days75
Addl Days Granted10
Working Days Charged85
Percent Time Used100
Contractor(s)
REVEGETATION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6291-12-001
ROSS TREE SERVICE (1.07)
S&S BRIDGE PAINTING (4.22)
Contract #01164201
Totals476292.000.00302739.9263.5

CountyLAMAR
HighwayUS0082
FromLAMAR, DELTA, RED RIVER
ToGRAYSON, FANNIN COUNTIES
CSJ6292-43-001
Proj IDRMC - 629243001
Work TypeON CALL STRIPING
 
0.001633100.00136086.6821.4
Work Order01-13-16
Work Began00-00-00
Work Completed
Time Computed01-19-16
Contract Working Days365
Addl Days Granted365
Working Days Charged348
Percent Time Used47
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6292-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154201
Totals633100.0014535.17136086.6821.4

CountyHUNT
HighwayIH0030
FromVARIOUS LOCATIONS IN HUNT, RAINS,
ToHOPKINS AND FRANKLIN COUNTIES
CSJ6292-44-001
Proj IDRMC - 629244001
Work TypeON CALL TY II STRIPING
 
0.001427700.0080330.9318.7
Work Order01-13-16
Work Began00-00-00
Work Completed
Time Computed01-15-16
Contract Working Days365
Addl Days Granted365
Working Days Charged352
Percent Time Used48
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154001
Totals427700.000.0080330.9318.7

CountyLAMAR
HighwayUS0082
FromPARIS DISTRICT
ToALL LOCATIONS
CSJ6292-45-001
Proj IDRMC - 629245001
Work TypeON CALL RPM'S
 
0.001294594.00277746.0094.2
Work Order01-07-16
Work Began00-00-00
Work Completed
Time Computed01-15-16
Contract Working Days365
Addl Days Granted365
Working Days Charged351
Percent Time Used48
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11154202
Totals294594.0078219.01277746.0094.2

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT ENTIRE
ToPARIS DISTRICT
CSJ6293-14-001
Proj IDRMC - 629314001
Work TypeON CALL MILL & INLAY
 
0.0015790782.507146080.2399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-29-15
Work Began00-00-00
Work Completed
Time Computed01-11-16
Contract Working Days365
Addl Days Granted0
Working Days Charged303
Percent Time Used83
Contractor(s)
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6293-14-001
TEX OP CONSTRUCTION, LP (4.61)
Contract #10154001
Totals5790782.500.007146080.2399.9

CountyGRAYSON
HighwayUS0082
FromCOOKE COUNTY LINE TO
ToFM 1417 IN GRAYSON COUNTY
CSJ6299-52-001
Proj IDRMC - 629952001
Work TypeMILL & HOTMIX INLAY
 
0.001887245.20978538.5599.9
Work Order06-21-16
Work Began06-27-16
Work Completed
Time Computed06-27-16
Contract Working Days25
Addl Days Granted0
Working Days Charged49
Percent Time Used196
Contractor(s)
OVERLAND CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6299-52-001
TOTAL HIGHWAY MAINTENANCE, LLC (4.40)
Contract #04164201
Totals887245.2011160.00978538.5599.9

CountyHOPKINS
HighwayIH0030
FromVARIOUS LOCATIONS IN HOPKINS, FRANKLIN,
ToLAMAR, DELAT, AND RED RIVER COUNTIES
CSJ6300-57-001
Proj IDRMC - 630057001
Work TypeON CALL FULL DEPTH CONCRETE REPAIR
 
0.0011571293.000.000.0
Work Order10-20-16
Work Began00-00-00
Work Completed
Time Computed11-08-16
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164201
Totals1571293.000.000.000.0

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT ENTIRE
ToPARIS DISTRICT
CSJ6301-86-001
Proj IDRMC - 630186001
Work TypeON CALL TRAFFIC CONTROL SERVICES
 
0.0012302678.75232804.1710.1
Work Order10-10-16
Work Began00-00-00
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6301-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164201
Totals2302678.75124768.57232804.1710.1

CountyGRAYSON
HighwayUS0075
FromVARIOUS LOCATIONS IN GRAYSON, FANNIN,
ToHUNT COUNTIES
CSJ6302-68-001
Proj IDRMC - 630268001
Work TypeON CALL FULL DEPTH CONCRETE REPAIR
 
0.0011369980.00724500.2652.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-16
Work Began00-00-00
Work Completed
Time Computed09-23-16
Contract Working Days365
Addl Days Granted0
Working Days Charged93
Percent Time Used25
Contractor(s)
WINDING ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164001
Totals1369980.000.00724500.2652.8

CountyLAMAR
HighwayUS0082
FromVARIOUS LOCATIONS THROUGHOUT
ToPARIS DISTRICT
CSJ6308-45-001
Proj IDRMC - 630845001
Work TypeON CALL MILL AND INLAY
 
0.0014370668.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164001
Totals4370668.540.000.000.0

page 1