Monthly State Let Construction Report For San Antonio District As Of Apr 11, 2014 Page 1 Of 5

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCOMAL
Highway IH 35
From GUADALUPE / COMAL COUNTY LINE
To SOLMS RD
CSJ 0016-05-106
Proj ID IM 0352(345)
Work Type SEAL COAT, PFC OVERLAY, & PAV MRK
 
6.503 4541084.72 437100.79 437100.79 9.6
CountyGUADALUPE
Highway IH 35
From 0.5 MI S OF FM 3009
To GUADALUPE / COMAL COUNTY LINE
CSJ 0016-06-045
Proj ID IM 0352(345)
Work Type SEAL COAT, PFC OVERLAY & PAV MRK
 
1.834 1306914.55 0.00 0.00 0.0
Work Order 12-10-13
Work Began 00-00-00
Work Completed  
Time Computed 02-08-14
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-106
CHEROKEE SERVICES(0.92%)
FLASHER EQUIPMENT COMPANY(3.05%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.31%)
CLAUDIA SERNA DBA SERNA"S TRUCKING (5.69%)
Contract # 09133217
Totals 5847999.27 437100.79 437100.79 7.4

CountyCOMAL
Highway IH 35
From AT LP 337 INTERSECTION
To .
CSJ 0016-05-107
Proj ID IM 0352(347)
Work Type RECONFIGURE INTERSECTION
 
0.206 2452584.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-12-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0016-05-107
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12133009
Totals 2452584.01 0.00 0.00 0.0

CountyGUADALUPE
Highway IH 35
From BEXAR / GUADALUPE COUNTY LINE
To FM 3009
CSJ 0016-06-046
Proj ID C 16-6-46
Work Type GR, BS, STR, SURF, OVERLAY
 
2.076 9163402.10 44175.80 8778093.94 95.1
CountyBEXAR
Highway IH 35
From JUDSON ROAD
To GUADALUPE / BEXAR COUNTY LINE
CSJ 0016-07-129
Proj ID C 16-7-129
Work Type GR, BS, STR, SURF, OVERLAY
 
3.719 12427317.34 903443.12 8894736.40 71.5
Work Order 09-18-12
Work Began 10-08-12
Work Completed  
Time Computed 10-08-12
Contract Working Days 321
Addl Days Granted 71
Working Days Charged 369
Percent Time Used 94
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0016-06-046
JUST GROOVING, LTD.(0.04%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.15%)
VOGES DRILLING CO. (0.48%)
SCOTT DERR PAINTING CO, LLC(0.11%)
GK CONSTRUCTION, LLC (0.26%)
ENVIRONMENTAL SAFETY SERVICES, INC.(1.05%)
FLASHER EQUIPMENT COMPANY(2.33%)
THE LEVY COMPANY, L.P. (5.67%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.10%)
ANGEL BROTHERS ENTERPRISES, LTD. ( 42.24%)
LIGHT IT UP ELECTRIC (0.07%)
CATO DRILLING COMPANY(0.01%)
R K STEPHENS CONSTRUCTION, LLC (0.43%)
Contract # 08123037
Totals 21590719.44 947618.92 17672830.34 81.5

CountyBEXAR
Highway IH 35
From 0.2 MI N OF TOEPPERWEIN RD
To 0.2 MI S OF LOOP 1604
CSJ 0016-07-132
Proj ID IM 0352(341)
Work Type LANDSCAPE DEVELOPMENT
 
0.800 287874.50 0.00 9985.25 3.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-13-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ALTEX LANDSCAPE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0016-07-132
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133206
Totals 287874.50 0.00 9985.25 3.4

CountyCOMAL
Highway BS 46-C
From IN NEW BRAUNFELS FROM KESSLER ST
To HAMPE ST AT UP RR
CSJ 0016-10-022
Proj ID C 16-10-22
Work Type GR, STRS, BASE & SURF
 
0.324 9677386.78 1856440.14 7823884.51 80.8
Work Order 11-09-12
Work Began 01-07-13
Work Completed  
Time Computed 01-07-13
Contract Working Days 243
Addl Days Granted 62
Working Days Charged 197
Percent Time Used 64
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0016-10-022
VOGES DRILLING CO. (4.47%)
ROADWAY SPECIALTIES, INC.(2.22%)
THE LEVY COMPANY, L.P. (2.92%)
R K STEPHENS CONSTRUCTION, LLC (2.70%)
HIGHWAY TECHNOLOGIES, INC. (0.64%)
ANGEL BROTHERS ENTERPRISES, LTD. (8.96%)
FLASHER EQUIPMENT COMPANY(0.56%)
Contract # 08123009
Totals 9677386.78 1856440.14 7823884.51 80.8

CountyBEXAR
Highway IH 35
From AT MEDINA RIVER (NB)
To .
CSJ 0017-02-075
Proj ID BR 2013(030)
Work Type GRAD, BSE, STR, SURFACE, PAV'T MRK
 
0.294 6192762.50 0.00 6082740.30 99.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-01-12
Work Began 01-02-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 31
Working Days Charged 265
Percent Time Used 119
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0017-02-075
F & W ELECTRICAL CONTRACTORS, INC. (0.62%)
RAMMING PAVING COMPANY (9.87%)
FARR FOUNDATION, INC.(3.34%)
ROADWAY SPECIALTIES, INC.(1.03%)
VOGES DRILLING CO. (3.55%)
HIGHWAY TECHNOLOGIES, INC. (0.69%)
GK CONSTRUCTION, LLC (3.36%)
HOUSTON SAWING & DRILLING(0.09%)
FLASHER EQUIPMENT COMPANY(0.32%)
Z & L CONCRETE CONTRACTORS, INC. (2.50%)
FRANK JR REINFORCEMENT LLC (0.24%)
Contract # 09123205
Totals 6192762.50 0.00 6082740.30 99.0

CountyMEDINA
Highway IH 35
From FM 3176
To SH 173
CSJ 0017-05-092
Proj ID C 17-5-92
Work Type GRAD, BSE, SURF, PAVMNT MRK, SIGNS
 
0.733 1564899.84 0.00 1170697.70 74.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-13
Work Began 11-01-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 190
Addl Days Granted 3
Working Days Charged 94
Percent Time Used 48
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0017-05-092
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.74%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.51%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.85%)
FLASHER EQUIPMENT COMPANY(0.94%)
MURRAY CONSTRUCTION(0.70%)
Contract # 07133030
Totals 1564899.84 0.00 1170697.70 74.8

CountyMEDINA
Highway IH 35
From AT FM 471
To .
CSJ 0017-05-093
Proj ID IM 0352(348)
Work Type GRAD, BSE, SURF, PVMT MARKINGS
 
0.570 1339998.78 0.00 211831.32 15.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-03-14
Work Began 03-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 12
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0017-05-093
DOUBLE S PAVING, INC.(3.93%)
FLASHER EQUIPMENT COMPANY(2.51%)
ROADWAY SPECIALTIES, INC.(3.57%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.34%)
Contract # 12133218
Totals 1339998.78 0.00 211831.32 15.8

CountyFRIO
Highway IH 35
From FM 140
To FM 1581
CSJ 0017-07-130
Proj ID IM 0352(346)
Work Type GRAD, BSE, STR, SURF, PAV'T MRK
 
1.302 3224249.18 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 219
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 3
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-07-130
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.72%)
WEST TEXAS RUMBLE STRIP(0.10%)
RICE ENVIRONMENTAL SERVICES(0.25%)
ROADWAY SPECIALTIES, INC.(2.15%)
STAR OPERATIONS, INC.(7.44%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.53%)
Contract # 10133210
Totals 3224249.18 0.00 0.00 0.0

CountyFRIO
Highway IH 35 ETC
From FRONTAGE RDS AT FM 117
To .
CSJ 0017-07-132
Proj ID IM 0352(344)G
Work Type TRAFFIC CONTROL DEVICE
 
0.007 593552.46 0.00 0.00 0.0
Work Order 12-03-13
Work Began 00-00-00
Work Completed  
Time Computed 03-03-14
Contract Working Days 165
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SIEMENS INDUSTRY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-07-132
VACA UNDERGROUND UTILITIES INC (1.78%)
UNITED PAVEMENT & MARKINGS, LLC(3.30%)
YORK & YORK FOUNDATION DRILLING, INC.( 12.06%)
JND CONSTRUCTION CONSULTANTS, LLC( 12.13%)
Contract # 09133219
Totals 593552.46 0.00 0.00 0.0

CountyBEXAR
Highway IH 35
From VARIOUS LOCATIONS ON IH 35
To LAREDO ST TO 0.2 MI W OF IH 37
CSJ 0017-10-253
Proj ID BR 2013(757)
Work Type STRUCTURE REPAIR
 
2.867 7975735.00 0.00 867662.40 10.8
CountyBEXAR
Highway IH 10
From VARIOUS LOCATIONS ON IH 10
To MULBERRY TO POPLAR ST
CSJ 0072-12-193
Proj ID BR 2013(757)
Work Type STRUCTURE REPAIR
 
1.792 2727430.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 02-14-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 558
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 5
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-253
DYWIDAG-SYSTEMS INTERNATIONAL_USA,INC. ( 69.61%)
FLASHER EQUIPMENT COMPANY(0.42%)
Contract # 09133211
Totals 10703165.00 0.00 867662.40 8.1

CountyBEXAR
Highway IH 35
From IH 410 SOUTH
To IH 410 NORTH
CSJ 0017-10-261
Proj ID IM 0352(342)
Work Type REFIG INTER, RMP, FRT & ML OP IMPRV
 
4.686 34249407.46 0.00 6392531.52 18.6
CountyBEXAR
Highway IH 35
From AT IH 410 S
To .
CSJ 0017-10-264
Proj ID IM 0352(342)
Work Type GRAD, BSE, STR, SURF, SIGN, PAV'T MRK
 
3.115 26946957.79 0.00 6008210.83 22.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-24-13
Work Began 11-11-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 916
Addl Days Granted 0
Working Days Charged 104
Percent Time Used 11
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0017-10-261
PANTHER CREEK TRANSPORTATION, INC. (1.87%)
JAG PUBLIC SAFETY, LLC (0.11%)
J. R. (JOE) RAMON & SONS, INC. (0.26%)
FARR FOUNDATION, INC.(0.66%)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.09%)
TEXAS HIGHWAY WALLS(6.19%)
DU MOR ENTERPRISES (0.71%)
HOUSTON SAWING & DRILLING(0.01%)
BOMANITE OF AUSTIN, LTD DBA TEXAS BOMANITE (0.04%)
M & M STRIPING & POWER WASHING, LLC(0.08%)
FLASHER EQUIPMENT COMPANY(0.85%)
CP REBAR AND PT INSTALLATION ( 11.66%)
RAMMING PAVING COMPANY ( 13.98%)
ROADWAY SPECIALTIES, INC.(1.18%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (3.41%)
THE LEVY COMPANY, L.P. (7.92%)
W. W. FOUNDATION DRILLING, LTD.(1.00%)
TEXSTAR ENTERPRISES, INC.(0.62%)
ROADWAY SPECIALTIES, INC.(0.16%)
LIGHT IT UP ELECTRIC (0.20%)
CATO DRILLING COMPANY(0.07%)
S & S BRIDGE PAINTING, INC.(0.47%)
G MARIN REBAR, INC.(0.00%)
CALAME CONTRACTING, LLC(0.43%)
WEBBER BARRIER SERVICES, LLC.(3.44%)
Contract # 07133001
Totals 61196365.25 0.00 12400742.35 20.2

CountyFRIO
Highway SP 581 ETC
From FM 1582
To IH 35 SB FRONTAGE ROAD
CSJ 0017-15-022
Proj ID STP 2014(220)
Work Type SEAL COAT & PAVEMENT MARKINGS
 
145.708 3663584.27 0.00 21777.77 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-10-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 146
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0017-15-022
INTERSTATE BARRICADES & MARKINGS, INC. ( 15.68%)
Contract # 11133007
Totals 3663584.27 0.00 21777.77 0.5

CountyMEDINA
Highway US 90
From AVENUE C IN HONDO
To 1.6 MILES EAST OF SH 173
CSJ 0024-05-095
Proj ID NH 2014(361)
Work Type OVERLAY & PAVEMENT MARKINGS
 
1.398 911816.80 0.00 0.00 0.0
Work Order 02-14-14
Work Began 00-00-00
Work Completed  
Time Computed 03-02-14
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RAMMING PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0024-05-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01143018
Totals 911816.80 0.00 0.00 0.0

CountyBEXAR
Highway IH 10
From AT HOUSTON STREET
To .
CSJ 0025-02-192
Proj ID IM 0352(339)
Work Type GRAD, BASE, STR, SURF & PAV'T MRKNG
 
0.317 1073789.27 0.00 1074214.60 99.9
Work Order 02-22-13
Work Began 06-26-13
Work Completed  
Time Computed 06-03-13
Contract Working Days 97
Addl Days Granted 0
Working Days Charged 97
Percent Time Used 100
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-192
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (3.01%)
FLASHER EQUIPMENT COMPANY(1.76%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.66%)
FUQUAY, INC. (1.18%)
Contract # 12123008
Totals 1073789.27 0.00 1074214.60 99.9

CountyBEXAR
Highway IH 10
From S PINE STREET
To ROLAND AVENUE
CSJ 0025-02-194
Proj ID C 25-2-194
Work Type MILL, RETAINING WALL, SURFACE
 
0.800 12027793.24 0.00 1180280.53 9.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-13
Work Began 08-12-13
Work Completed  
Time Computed 00-00-00
Contract Working Days 349
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 1
Contractor(s)
AUSTIN BRIDGE & ROAD, LP
SUBCONTRACTOR(S) FOR CCSJ: 0025-02-194
ANGEL BROTHERS ENTERPRISES, LTD. ( 22.61%)
DANRIDGE CONSTRUCTION, LLC.(0.67%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.79%)
FLASHER EQUIPMENT COMPANY(0.75%)
HALL AND SONS TRANSPORT, INC.(7.88%)
RICE ENVIRONMENTAL SERVICES(0.60%)
THE LEVY COMPANY, L.P. ( 12.82%)
LIGHT IT UP ELECTRIC (0.22%)
TEXSTAR ENTERPRISES, INC.(1.62%)
ANTIGO CONSTRUCTION, INC.(0.20%)
CALAME CONTRACTING, LLC(1.95%)
DU-MOR ENTERPRISES_INC.(0.81%)
Contract # 04133217
Totals 12027793.24 0.00 1180280.53 9.8

CountyGUADALUPE
Highway US 90
From AT GUADALUPE RIVER
To .
CSJ 0025-03-092
Proj ID BR 2013(707)
Work Type SCOUR REPAIR
 
0.398 3965069.00 115443.01 3933868.14 99.2
Work Order 06-28-13
Work Began 09-09-13
Work Completed  
Time Computed 09-09-13
Contract Working Days 117
Addl Days Granted 6
Working Days Charged 119
Percent Time Used 96
Contractor(s)
ATS DRILLING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-03-092
RICE ENVIRONMENTAL SERVICES(1.48%)
MCL CONTRACTING, LLC (4.99%)
AUSTIN BRIDGE & ROAD, LP ( 16.84%)
Contract # 05133216
Totals 3965069.00 115443.01 3933868.14 99.2

CountyGUADALUPE
Highway FM 78
From SANTA CLARA CREEK, WEST OF MARION
To SANTA CLARA CREEK, EAST OF MARION
CSJ 0025-10-073
Proj ID STP 2013(348)
Work Type GRAD, STRS, BASE & SURF
 
1.080 4136146.75 125841.34 689000.21 16.6
Work Order 07-16-13
Work Began 11-11-13
Work Completed  
Time Computed 11-11-13
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 5
Contractor(s)
DEAN WORD COMPANY, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-10-073
FLASHER EQUIPMENT COMPANY(0.31%)
LANDSCAPE CONTRACTING AND IRRIGATION, INC. (2.51%)
E-Z BEL CONSTRUCTION, LLC(1.02%)
MURRAY CONSTRUCTION(0.53%)
RICE ENVIRONMENTAL SERVICES(0.56%)
C & C ALCOSER TRUCKING (0.00%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.53%)
Contract # 01133220
Totals 4136146.75 125841.34 689000.21 16.6

CountyBEXAR
Highway IH 10
From FM 3351 (RALPH FAIR RD)
To BOERNE STAGE RD
CSJ 0072-07-060
Proj ID C 72-7-60
Work Type GRAD, BS, STR, PVMT MRKG
 
0.871 6345951.80 480240.55 622958.44 9.8
Work Order 08-06-13
Work Began 00-00-00
Work Completed  
Time Computed 08-22-13
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 1
Contractor(s)
SUNDT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0072-07-060
J.D. RAMMING PAVING CO., LTD.( 15.45%)
SIEMENS INDUSTRY, INC. (3.77%)
PRESIDIO CONTRACTING, LLC(2.35%)
FARR FOUNDATION, INC.(2.29%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.90%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.44%)
D GUERRA CONSTRUCTION, LLC (1.68%)
FLASHER EQUIPMENT COMPANY(1.19%)
VOGES DRILLING CO. (1.20%)
A-Z REBAR CONTRACTOR (0.37%)
SCOTT DERR PAINTING CO (0.08%)
Contract # 06133205
Totals 6345951.80 480240.55 622958.44 9.8

CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-120
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
2.513 25923457.53 0.00 9562482.37 37.1
CountyBEXAR
Highway IH 10
From LP 1604
To 1.0 MI N OF HUEBNER RD
CSJ 0072-08-125
Proj ID NH 1102(524)
Work Type UTIL & UTIL IN CONSTR CONTRACT
 
3.980 408971.75 0.00 364462.91 89.1
CountyBEXAR
Highway IH 10
From 1.0 MI N OF HUEBNER RD
To S. OF HUEBNER RD
CSJ 0072-12-179
Proj ID STP 1102(442)MM
Work Type GRAD, BASE, SC, OV & PAV'T MRKNGS
 
1.464 9635856.12 0.00 3205087.39 33.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-19-11
Work Began 01-02-12
Work Completed  
Time Computed 00-00-00
Contract Working Days 698
Addl Days Granted 73
Working Days Charged 553
Percent Time Used 71
Contractor(s)
LIBERTY MUTUAL INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0072-08-120
LONE STAR TRAFFIC SERVICE, INC.(0.20%)
FUQUAY, INC. (0.07%)
ROADWAY SPECIALTIES, INC.(0.69%)
SITESAFE PRODUCTS TEXAS(0.99%)
PRIMATE CONSTRUCTION, INC. (0.03%)
J. R. (JOE) RAMON & SONS, INC. (0.60%)
GEOSOURCE, INC.(0.50%)
FARR FOUNDATION, INC.(1.09%)
DUSTROL, INC.(0.20%)
BEAIRD DRILLING(0.37%)
CP REBAR AND PT INSTALLATION (0.25%)
COLLECTIVE CONTRACTING (1.01%)
FLASHER EQUIPMENT COMPANY(1.35%)
STAR OPERATIONS, INC.( 15.22%)
S & S BRIDGE PAINTING, INC.(0.16%)
A & L UNDERGROUND, INC.(0.03%)
DU-MOR ENTERPRISES_INC.(0.55%)
DRILL TECH DRILLING & SHORING, INC.(2.82%)
T & D SOLUTIONS, LTD (1.55%)
WEBBER, LLC(112.09%)
FARR FOUNDATION, INC.(1.25%)
TEXAS HIGHWAY WALLS(2.73%)
BEAIRD DRILLING(0.35%)
FLASHER EQUIPMENT COMPANY(1.25%)
STAR OPERATIONS, INC.( 10.76%)
GIBSON & ASSOCIATES, INC.(0.13%)
HOLES OF SAN ANTONIO (0.01%)
M & M CONTRACTING, LTD.(1.04%)
TEXAS CURB CUT, LP (0.07%)
ANGEL BROTHERS ENTERPRISES, LTD. ( 36.16%)
WEBBER BARRIER SERVICES, LLC.(2.34%)
HOUSTON SAWING & DRILLING(0.02%)
CP REBAR AND PT INSTALLATION (0.14%)
SIGNATURE CONTRACTING SERVICES, L.L.C. (5.48%)
CRAIG OLDEN, INC.(0.99%)
PENHALL COMPANY (AUSTIN) (0.00%)
Contract # 08113003
Totals 35968285.40 0.00 13132032.67 36.6

page 1 | page 2 | page 3 | page 4 | page 5