Monthly State Let Maintenance Report For San Antonio District As Of Feb 10, 2017 Page 1 Of 2

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBEXAR
Highway0000000
From4615 NW LOOP 410
ToSAN ANTONIO TX 78229
CSJ4704-01-595
Proj IDCBC - 470401595
Work TypeRENOVATION OR REPAIR
 
0.0012038650.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
QA CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-595
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164224
Totals2038650.000.000.000.0

CountyBEXAR
Highway0000000
From4615 N. W. LOOP 410 SAN ANTONIO, TEXAS
To4615 N. W. LOOP 410 SAN ANTONIO, TEXAS
CSJ4704-01-602
Proj IDCBC - 470401602
Work TypeRENVOATION OR REPAIR
 
0.001477770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SECURITAS ELECTRONIC SECURITY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-602
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164223
Totals477770.000.000.000.0

CountyUVALDE
Highway0000000
From2231 US 90 WEST
ToUVALDE TX 78801
CSJ4704-01-724
Proj IDCBC - 470401724
Work TypeRENOVATION OR REPAIR
 
0.001337200.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRIGGS BROTHERS ENTERPRISES CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-724
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164221
Totals337200.000.000.000.0

CountyMEDINA
HighwayFM0462
FromFM 462
ToAT HONDO CREEK BRIDGE
CSJ6277-89-001
Proj IDRMC - 627789001
Work TypeDITCH REPAIR
 
0.001290626.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-08-16
Work Began00-00-00
Work Completed
Time Computed11-28-16
Contract Working Days34
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6277-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164220
Totals290626.600.000.000.0

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN BEXAR AND
ToCOMAL COUNTIES
CSJ6278-99-001
Proj IDRMC - 627899001
Work TypePERFORMANCE BASED ROADWAY
 
0.00118456927.7617346689.4093.9
Work Order03-25-15
Work Began04-01-15
Work Completed
Time Computed04-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged672
Percent Time Used92
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6278-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12144208
Totals18456927.76663830.3217346689.4093.9

CountyBEXAR
HighwayIH0010
FromVARIOUS IN EAST BEXAR
ToCOUNTY
CSJ6283-40-001
Proj IDRMC - 628340001
Work TypeROUTINE MAINTENANCE
 
0.0015928997.207384625.1299.9
Work Order03-30-15
Work Began04-07-15
Work Completed
Time Computed04-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged660
Percent Time Used90
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03154220
Totals5928997.20281767.457384625.1299.9

CountyKENDALL
HighwaySH0046
From2.386 MI W OF IH 10
To2.166 MI W OF IH 10
CSJ6284-94-001
Proj IDRMC - 628494001
Work TypeGRADING,HDWLLS,BASE,SURFACING,
 
0.220362708.04317560.3687.5
Work Order09-28-16
Work Began10-03-16
Work Completed
Time Computed10-03-16
Contract Working Days50
Addl Days Granted0
Working Days Charged40
Percent Time Used80
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164016
Totals362708.040.00317560.3687.5

CountyCOMAL
HighwayIH0035
FromVARIOUS COMAL AND
ToGUADALUPE
CSJ6292-01-001
Proj IDBPM - 629201001
Work TypeBRIDGE JOINT REPAIR
 
0.001404169.90293863.0772.7
Work Order09-06-16
Work Began09-13-16
Work Completed
Time Computed09-13-16
Contract Working Days60
Addl Days Granted0
Working Days Charged43
Percent Time Used71
Contractor(s)
LONE STAR PAVING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6292-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164019
Totals404169.900.00293863.0772.7

CountyBEXAR
HighwayIH0035
FromIH 35 NEW INTERSECTION OF MAIN AVE.
ToWEST ELMIRA STREET
CSJ6296-57-001
Proj IDRMC - 629657001
Work TypePUMPSTATION REPAIRS
 
0.0011249435.00871728.0069.7
Work Order09-01-16
Work Began09-08-16
Work Completed
Time Computed09-08-16
Contract Working Days180
Addl Days Granted0
Working Days Charged146
Percent Time Used81
Contractor(s)
AUSTIN ENGINEERING CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164213
Totals1249435.00642496.00871728.0069.7

CountyCOMAL
HighwayIH0035
FromVARIOUS LOCATIONS_IN
ToSAN ANTONIO DISTRICT
CSJ6297-62-001
Proj IDRMC - 629762001
Work TypeGUARDRAIL REPAIR
 
0.0011166990.00633820.5054.3
Work Order06-15-16
Work Began07-06-16
Work Completed
Time Computed06-22-16
Contract Working Days730
Addl Days Granted0
Working Days Charged221
Percent Time Used30
Contractor(s)
SHORT-LINE CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6297-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164020
Totals1166990.00139313.00633820.5054.3

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToFRIO, ATASCOSA AND LASALLE COUNTIES
CSJ6298-17-001
Proj IDRMC - 629817001
Work TypeMOWING AND LITTER REMOVAL
 
0.001524372.82215887.4041.1
Work Order00-00-00
Work Began05-23-16
Work Completed
Time Computed05-23-16
Contract Working Days212
Addl Days Granted0
Working Days Charged47
Percent Time Used22
Contractor(s)
MISSOURI-TEXAS FARMS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164008
Totals524372.820.00215887.4041.1

CountyATASCOSA
HighwayIH0037
FromVARIOUS LOCATIONS IN
ToATASCOSA COUNTY
CSJ6298-19-001
Proj IDRMC - 629819001
Work TypeMOWING AND LITTER REMOVAL
 
0.001421464.00155097.3038.2
Work Order06-07-16
Work Began06-28-16
Work Completed
Time Computed06-14-16
Contract Working Days191
Addl Days Granted0
Working Days Charged56
Percent Time Used29
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01164009
Totals421464.000.00155097.3038.2

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN_BEXAR,KERR,UVALDE
ToKENDALL,BANDERA,COMAL,GUADALUPE
CSJ6299-37-001
Proj IDRMC - 629937001
Work TypeCALL OUT PAVEMENT REPAIR
 
0.0014990875.401731657.1434.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-31-16
Work Began09-22-16
Work Completed
Time Computed09-07-16
Contract Working Days365
Addl Days Granted0
Working Days Charged116
Percent Time Used31
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6299-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164219
Totals4990875.400.001731657.1434.6

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6300-78-001
Proj IDRMC - 630078001
Work TypePAVEMENT REPAIR
 
0.0012637085.633125214.2799.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-02-16
Work Began06-08-16
Work Completed
Time Computed06-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged154
Percent Time Used42
Contractor(s)
CLARK CONSTRUCTION OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-78-001
INTERSTATE BARRICADES & MARKINGS, INC. (4.56)
Contract #04164006
Totals2637085.630.003125214.2799.9

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6303-03-001
Proj IDRMC - 630303001
Work TypeTRAFFIC CONTROL
 
0.001972749.0077895.258.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-07-16
Work Began11-14-16
Work Completed
Time Computed11-14-16
Contract Working Days365
Addl Days Granted0
Working Days Charged48
Percent Time Used13
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164011
Totals972749.000.0077895.258.0

CountyBEXAR
HighwayIH0035
FromVARIOUS LOCATIONS IN
ToBEXAR COUNTY
CSJ6303-32-001
Proj IDRMC - 630332001
Work TypePAV MARKINGS & MRKRS CENTERLINE
 
0.001947692.50278039.5529.3
Work Order08-19-16
Work Began09-07-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
FLASHER EQUIPMENT COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6303-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164015
Totals947692.50101255.59278039.5529.3

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS IN THE
ToSAN ANTONIO DISTRICT
CSJ6303-33-001
Proj IDRMC - 630333001
Work TypePAV MARKINGS & MRKRS CENTERLINE
 
0.0011515344.30836224.1755.1
Work Order08-24-16
Work Began09-23-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
INTERSTATE BARRICADES & MARKINGS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164214
Totals1515344.30203790.17836224.1755.1

CountyFRIO
HighwayIH0035
FromVARIOUS LOCATIONS
ToVARIOUS LOCATIONS
CSJ6304-81-001
Proj IDRMC - 630481001
Work TypeTRAFFIC CONTROL
 
0.001616539.0026502.504.2
Work Order11-29-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged62
Percent Time Used16
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6304-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164208
Totals616539.0017597.5026502.504.2

CountyBEXAR
HighwayIH0035
FromIH 410
ToSPUR 422
CSJ6304-98-001
Proj IDRMC - 630498001
Work TypeREMOVE AND REPLACE MBGF
 
1.000568940.00125203.0022.0
Work Order01-10-17
Work Began01-17-17
Work Completed
Time Computed01-17-17
Contract Working Days34
Addl Days Granted0
Working Days Charged7
Percent Time Used20
Contractor(s)
K-BAR SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164215
Totals568940.00125203.00125203.0022.0

CountyBEXAR
HighwayIH0035
FromVARIOUS_LOCATIONS IN
ToBEXAR COUNTY
CSJ6307-50-001
Proj IDRMC - 630750001
Work TypeBRIDGE RAIL RETROFIT
 
0.001893837.72163372.8918.2
Work Order01-10-17
Work Began01-20-17
Work Completed
Time Computed01-17-17
Contract Working Days104
Addl Days Granted0
Working Days Charged8
Percent Time Used7
Contractor(s)
DAN WILLIAMS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6307-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164219
Totals893837.72163372.89163372.8918.2

page 1 | page 2