Monthly State Let Construction Report For San Angelo District As Of Nov 9, 2016 Page 1 Of 2

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRUNNELS
Highway US 83 ETC
From TAYLOR COUNTY LINE
To 6.9 MILES S OF TAYLOR COUNTY LINE
CSJ 0034-03-018
Proj ID NH 2016(283)
Work Type SEAL COAT
 
100.339 4499947.77 0.00 4835185.11 99.9
Work Order 12-21-15
Work Began 05-23-16
Work Completed  
Time Computed 05-01-16
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 52
Contractor(s)
COX PAVING OF TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-03-018
DOUBLE A CONTRACTING, L.P. (5.58%)
Contract # 11153221
Totals 4499947.77 0.00 4835185.11 99.9

CountyRUNNELS
Highway US 83
From AT ELM CREEK AND AT RAILROAD/FM 382
To .
CSJ 0034-05-039
Proj ID BR 2015(182)
Work Type REHABILITATE BRIDGES
 
0.200 14622336.57 477071.36 11473173.56 78.4
Work Order 01-02-15
Work Began 01-26-15
Work Completed  
Time Computed 01-26-15
Contract Working Days 304
Addl Days Granted 90
Working Days Charged 363
Percent Time Used 92
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-05-039
S & S BRIDGE PAINTING, INC.( 13.95%)
CONTRACTORS SERVICE COMPANY(0.42%)
WILLIS ELECTRIC CO., LP(1.99%)
CHOCTAW ERECTORS, INC. (2.70%)
RICE ENVIRONMENTAL SERVICES(0.46%)
AARON CONCRETE CONTRACTORS, L.P. (3.60%)
W. W. FOUNDATION DRILLING, LTD.(2.38%)
DOUBLE A CONTRACTING, L.P. (0.55%)
RUNNING HORSE CONSTRUCTION, INC. (1.23%)
MCL CONTRACTING, LLC (1.52%)
KLP COMMERCIAL, LLC(5.37%)
STRAIGHT LINE SAWING & SEALING (0.20%)
MCL CONTRACTING, LLC (0.11%)
HJC FARMS, INC.(0.15%)
MICA CORPORATION (0.87%)
Contract # 10143203
Totals 14622336.57 477071.36 11473173.56 78.4

CountyKIMBLE
Highway US 83
From AT IH 10 FRONTAGE ROADS IN JUNCTION
To .
CSJ 0035-07-044
Proj ID STP 2016(566)
Work Type CONSTRUCT TRAFFIC SIGNALS
 
0.126 1487816.87 516366.65 1261636.56 85.3
Work Order 03-01-16
Work Began 06-20-16
Work Completed  
Time Computed 05-30-16
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 115
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0035-07-044
THE LEVY COMPANY, L.P. ( 23.99%)
LONE STAR PAVING ( 16.63%)
FLASHER EQUIPMENT COMPANY(4.02%)
Contract # 01163229
Totals 1487816.87 516366.65 1261636.56 85.3

CountyREAL
Highway US 83
From RM 336
To RM 337 IN LEAKEY
CSJ 0036-05-033
Proj ID STP 2015(350)
Work Type REHABILITATE EXISTING ROAD
 
2.055 6989144.86 2212957.55 4503952.78 64.4
Work Order 01-28-15
Work Began 06-08-15
Work Completed  
Time Computed 05-29-15
Contract Working Days 225
Addl Days Granted 8
Working Days Charged 164
Percent Time Used 70
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0036-05-033
RELMCO, INC. ( 14.97%)
FUQUAY, INC. (0.36%)
PELTZ COMPANIES, INC.( 26.55%)
THE LEVY COMPANY, L.P. (0.36%)
Contract # 12143021
Totals 6989144.86 2212957.55 4503952.78 64.4

CountyGLASSCOCK
Highway US 87
From HOWARD COUNTY LINE
To STERLING COUNTY LINE
CSJ 0069-02-028
Proj ID NH 2015(931)
Work Type ACP OVERLAY
 
29.997 15257441.66 2262231.98 15612426.06 99.9
Work Order 05-19-15
Work Began 09-30-15
Work Completed  
Time Computed 08-19-15
Contract Working Days 111
Addl Days Granted 8
Working Days Charged 154
Percent Time Used 129
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0069-02-028
BARRICADES UNLIMITED (1.57%)
TEX OP CONSTRUCTION, LP(1.24%)
SCR CONSTRUCTION CO., INC. (0.58%)
SOUTHEAST GRINDING & GROOVING, LLC (0.14%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.37%)
Contract # 04153202
Totals 15257441.66 2262231.98 15612426.06 99.9

CountySTERLING
Highway US 87
From SH 158 IN STERLING CITY
To COKE COUNTY LINE
CSJ 0069-04-042
Proj ID NH 2016(403)
Work Type ACP OVERLAY
 
15.751 7904447.76 301234.84 893755.07 11.3
Work Order 03-01-16
Work Began 06-01-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 102
Addl Days Granted 2
Working Days Charged 96
Percent Time Used 92
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0069-04-042
BARRICADES UNLIMITED (1.60%)
CONTRACTORS SERVICE COMPANY(0.26%)
DOUBLE A CONTRACTING, L.P. (0.48%)
HJC FARMS, INC.(7.08%)
PERFORMANCE EQUIPMENT SERVICE(0.12%)
PRIMATE CONSTRUCTION, INC. (1.21%)
Contract # 12153227
Totals 7904447.76 301234.84 893755.07 11.3

CountyTOM GREEN
Highway US 87
From 33RD STREET
To US 67
CSJ 0069-07-103
Proj ID NH 2016(761)
Work Type ACP OVERLAY
 
2.055 1548841.17 174878.29 340234.10 22.9
Work Order 03-15-16
Work Began 10-09-16
Work Completed  
Time Computed 06-13-16
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 91
Percent Time Used 126
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0069-07-103
CONTRACTORS SERVICE COMPANY(0.91%)
PERFORMANCE EQUIPMENT SERVICE(1.91%)
BARRICADES UNLIMITED (4.37%)
Contract # 02163220
Totals 1548841.17 174878.29 340234.10 22.9

CountyIRION
Highway US 67
From 30.8 MI SOUTH OF TOM GREEN CO LINE
To REAGAN COUNTY LINE
CSJ 0077-02-031
Proj ID STP 1502(413)
Work Type ADD PASSING LANES
 
41.247 30896539.80 1220243.28 14379209.21 46.5
Work Order 10-20-15
Work Began 11-16-15
Work Completed  
Time Computed 11-16-15
Contract Working Days 375
Addl Days Granted 5
Working Days Charged 201
Percent Time Used 52
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-02-031
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.14%)
COX PAVING COMPANY, L.P. (6.73%)
PRIMATE CONSTRUCTION, INC. (0.45%)
CONTRACTORS SERVICE COMPANY(0.38%)
DOUBLE A CONTRACTING, L.P. (1.52%)
HJC FARMS, INC.(1.26%)
TEXOP CONSTRUCTION (1.23%)
DELGADO"S CONSTRUCTION (0.97%)
Contract # 07153003
Totals 30896539.80 1220243.28 14379209.21 46.5

CountyTOM GREEN
Highway US 67
From CHADBOURNE STREET
To US 87
CSJ 0077-06-090
Proj ID NH 1502(609)
Work Type ACP OVERLAY
 
2.967 6072493.75 880394.31 3268744.35 53.8
Work Order 02-24-16
Work Began 03-28-16
Work Completed  
Time Computed 03-28-16
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 115
Percent Time Used 74
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-090
BARRICADES UNLIMITED (2.39%)
CONTRACTORS SERVICE COMPANY(0.40%)
HJC FARMS, INC.(6.77%)
WEST TEXAS RUMBLE STRIP(0.12%)
HUDSON, INC. (2.22%)
O. TREVINO CONSTRUCTION, LLC ( 10.45%)
Contract # 08153247
Totals 6072493.75 880394.31 3268744.35 53.8

CountyTOM GREEN
Highway US 67
From CHAPEL HILL DRIVE
To IRION COUNTY LINE
CSJ 0077-06-094
Proj ID STP 2016(404)
Work Type ACP OVERLAY
 
11.222 8069634.10 1066362.60 7461405.92 92.4
Work Order 03-01-16
Work Began 05-31-16
Work Completed  
Time Computed 05-01-16
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 103
Percent Time Used 81
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-094
CONTRACTORS SERVICE COMPANY(0.16%)
TEX OP CONSTRUCTION, LP(1.80%)
PRIMATE CONSTRUCTION, INC. (0.43%)
HJC FARMS, INC.(5.05%)
TRP CONSTRUCTION GROUP, LLC(1.60%)
Contract # 12153028
Totals 8069634.10 1066362.60 7461405.92 92.4

CountyTOM GREEN
Highway US 67
From US 87
To SHERWOOD WAY
CSJ 0077-06-095
Proj ID NH 1602(524)
Work Type ACP OVERLAY
 
5.435 6339169.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-095
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11163207
Totals 6339169.42 0.00 0.00 0.0

CountyTOM GREEN
Highway US 67
From SL 306
To FM 2288
CSJ 0077-06-098
Proj ID NH 1602(297)
Work Type UPGRADE NON - FREEWAY
 
0.400 3805303.54 247296.91 279882.91 7.3
Work Order 09-14-16
Work Began 09-28-16
Work Completed  
Time Computed 12-13-16
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 3
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-098
T.C. TRUCKING & CONSTRUCTION, LLC(1.58%)
A BROTHERS MILLING, LLC(0.38%)
DYNAMIC VISION CO., INC. (3.24%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.32%)
CONTRACTORS SERVICE COMPANY(1.02%)
FLASHER EQUIPMENT COMPANY(1.01%)
WILLIS ELECTRIC CO., LP( 21.83%)
Contract # 07163015
Totals 3805303.54 247296.91 279882.91 7.3

CountyCROCKETT
Highway IH 10
From 33.1 MI E OF PECOS COUNTY LINE
To 38.0 MI E OF PECOS COUNTY LINE
CSJ 0140-11-043
Proj ID NH 1602(298)
Work Type UPGRADE FREEWAY
 
9.923 14033551.44 36200.00 36200.00 0.2
Work Order 09-06-16
Work Began 10-24-16
Work Completed  
Time Computed 11-05-16
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 2
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0140-11-043
AARON CONCRETE CONTRACTORS, L.P. (6.86%)
BRANNAN PAVING CO., LTD. (7.08%)
CHEROKEE SERVICES(1.05%)
DIAMOND SURFACE, INC.(0.09%)
KIOWA PEAK INDUSTRIES INC(0.95%)
SAENZ TRANSPORT, LLC ( 10.16%)
N-LINE TRAFFIC MAINTENANCE, L.P. (1.69%)
DOUBLE A CONTRACTING, L.P. (1.52%)
TEXOP CONSTRUCTION (1.71%)
HJC FARMS, INC.(3.48%)
Contract # 07163215
Totals 14033551.44 36200.00 36200.00 0.2

CountyCROCKETT
Highway IH 10
From 7.52 MILES WEST OF SUTTON CO LINE
To 3.17 MILES WEST OF SUTTON CO LINE
CSJ 0141-01-053
Proj ID NH 2016(858)
Work Type OVERLAY
 
8.833 5457413.69 2442794.15 7542742.38 99.9
Work Order 04-13-16
Work Began 07-22-16
Work Completed  
Time Computed 07-12-16
Contract Working Days 65
Addl Days Granted 19
Working Days Charged 70
Percent Time Used 83
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0141-01-053
COX PAVING OF TEXAS, INC.( 11.14%)
DOUBLE A CONTRACTING, L.P. (0.98%)
DUSTROL, INC.(1.46%)
FLASHER EQUIPMENT COMPANY(0.42%)
FUQUAY, INC. (0.33%)
WEST TEXAS RUMBLE STRIP(0.17%)
ALLEN KELLER COMPANY (4.16%)
TEXAS ALTERNATIVE GRASSER, INC.(0.13%)
Contract # 03163211
Totals 5457413.69 2442794.15 7542742.38 99.9

CountySTERLING
Highway SH 158
From GLASSCOCK COUNTY LINE
To US 87
CSJ 0405-02-024
Proj ID NH 2014(078)
Work Type WIDEN ROADWAY TO 4 - LANE UNDIVIDED
 
14.444 22606153.84 2071222.11 20681331.24 91.6
CountyZERO COUNTIES
Highway  
From  
To  
CSJ 0405-02-025
Proj ID  
Work Type  
 
  0.00 -69160.50 1061116.32 0.0
Work Order 01-17-14
Work Began 02-20-14
Work Completed  
Time Computed 02-19-14
Contract Working Days 535
Addl Days Granted 51
Working Days Charged 604
Percent Time Used 103
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0405-02-024
CONTRACTORS SERVICE COMPANY(0.30%)
TEX OP CONSTRUCTION, LP(0.03%)
W.S. CONSTRUCTION COMPANY(6.00%)
W.S. CONSTRUCTION COMPANY(3.57%)
BLACK TOPPER TECHNOLOGY, INC.(5.83%)
WEST TEXAS RUMBLE STRIP(0.16%)
HJC FARMS, INC.(2.33%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.09%)
COPPELL CONSTRUCTION CO., INC. (9.77%)
DOUBLE A CONTRACTING, L.P. (1.03%)
TEXAS SHAFTS, INC. (0.87%)
EAGLE CONCRETE CUTTERS, INC. (0.01%)
RUSSO CORPORATION(0.24%)
MCL CONTRACTING, LLC (0.02%)
MCKINNEY DRILLING COMPANY(0.15%)
GARY A. CRAIN, INC.(0.03%)
WILLIS ELECTRIC CO., LP(0.04%)
Contract # 10133202
Totals 22606153.84 2002061.61 21742447.56 96.3

CountyGLASSCOCK
Highway SH 158
From MIDLAND COUNTY LINE
To 0.3 MILES WEST OF RM 33
CSJ 0463-04-025
Proj ID NH 2016(901)
Work Type ACP OVERLAY
 
17.587 8716678.75 68950.00 68950.00 0.7
Work Order 07-15-16
Work Began 11-01-16
Work Completed  
Time Computed 09-14-16
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 24
Percent Time Used 33
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0463-04-025
A BROTHERS MILLING, LLC(0.15%)
BARRICADES UNLIMITED (1.66%)
CONTRACTORS SERVICE COMPANY(0.14%)
DOUBLE A CONTRACTING, L.P. (0.50%)
HJC FARMS, INC.(0.58%)
HUDSON, INC. (0.15%)
LITTLE MANUFACTURING (0.09%)
Contract # 04163002
Totals 8716678.75 68950.00 68950.00 0.7

CountyCONCHO
Highway FM 380
From AT KICKAPOO CREEK
To .
CSJ 0555-02-020
Proj ID BR 1602(525)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.105 2162110.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0555-02-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08163218
Totals 2162110.60 0.00 0.00 0.0

CountyCONCHO
Highway FM 765
From FM 2134
To MCCULLOCH COUNTY LINE
CSJ 0870-04-038
Proj ID STP 2016(071)
Work Type RESTORATION OF EXISTING ROAD
 
9.317 3629462.34 553605.07 3771414.82 99.9
Work Order 10-21-15
Work Began 01-18-16
Work Completed  
Time Computed 12-21-15
Contract Working Days 192
Addl Days Granted 7
Working Days Charged 180
Percent Time Used 90
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0870-04-038
CONTRACTORS SERVICE COMPANY(1.07%)
FLASHER EQUIPMENT COMPANY(2.28%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.18%)
TITAN MILLING INC. (2.45%)
Contract # 09153012
Totals 3629462.34 553605.07 3771414.82 99.9

CountyCONCHO
Highway FM 765
From US 83
To FM 2134
CSJ 0870-04-039
Proj ID STP 2017(033)
Work Type RESTORATION OF EXISTING ROAD
 
7.912 2858761.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-27-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0870-04-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163208
Totals 2858761.68 0.00 0.00 0.0

CountyTOM GREEN
Highway VA
From VARIOUS ROADWAYS IN SJT DISTRICT
To .
CSJ 0907-00-161
Proj ID STP 1502(163)
Work Type UPGRADE SIGNALS AND ILLUMINATION
 
0.001 1275751.00 39987.48 343415.55 26.9
Work Order 11-16-15
Work Began 07-18-16
Work Completed  
Time Computed 03-18-16
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 117
Percent Time Used 67
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0907-00-161
D. I. J. CONSTRUCTION, INC.(3.58%)
HOUSLEY COMMUNICATIONS, INC. (4.08%)
B & B ELECTRICAL & UTILITY CONTRACTORS, INC. (0.28%)
SIGNAL SERVICES GROUP INC. ( 17.79%)
Contract # 09153227
Totals 1275751.00 39987.48 343415.55 26.9

page 1 | page 2