Monthly State Let Construction Report For San Angelo District As Of Jun 15, 2016 Page 1 Of 2

Last Update: Wednesday, June 15, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRUNNELS
Highway US 83 ETC
From TAYLOR COUNTY LINE
To 6.9 MILES S OF TAYLOR COUNTY LINE
CSJ 0034-03-018
Proj ID NH 2016(283)
Work Type SEAL COAT
 
100.339 4499947.77 977307.10 1830946.77 40.6
Work Order 12-21-15
Work Began 05-23-16
Work Completed  
Time Computed 05-01-16
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 7
Contractor(s)
BLACKTOPPER TECHNOLOGY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-03-018
DOUBLE A CONTRACTING, L.P. (5.58%)
Contract # 11153221
Totals 4499947.77 977307.10 1830946.77 40.6

CountyRUNNELS
Highway US 83
From AT ELM CREEK AND AT RAILROAD/FM 382
To .
CSJ 0034-05-039
Proj ID BR 2015(182)
Work Type REHABILITATE BRIDGES
 
0.200 14622336.57 597994.23 9459351.61 64.6
Work Order 01-02-15
Work Began 01-26-15
Work Completed  
Time Computed 01-26-15
Contract Working Days 304
Addl Days Granted 90
Working Days Charged 270
Percent Time Used 68
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0034-05-039
S & S BRIDGE PAINTING, INC.( 13.95%)
CONTRACTORS SERVICE COMPANY(0.42%)
WILLIS ELECTRIC CO., LP(1.99%)
CHOCTAW ERECTORS, INC. (2.70%)
RICE ENVIRONMENTAL SERVICES(0.46%)
AARON CONCRETE CONTRACTORS, L.P. (3.60%)
W. W. FOUNDATION DRILLING, LTD.(2.38%)
DOUBLE A CONTRACTING, L.P. (0.55%)
RUNNING HORSE CONSTRUCTION, INC. (1.23%)
MCL CONTRACTING, LLC (1.52%)
KLP COMMERCIAL, LLC(5.37%)
STRAIGHT LINE SAWING & SEALING (0.20%)
MCL CONTRACTING, LLC (0.11%)
Contract # 10143203
Totals 14622336.57 597994.23 9459351.61 64.6

CountyKIMBLE
Highway US 83
From AT IH 10 FRONTAGE ROADS IN JUNCTION
To .
CSJ 0035-07-044
Proj ID STP 2016(566)
Work Type CONSTRUCT TRAFFIC SIGNALS
 
0.126 1487816.87 16880.00 29312.00 1.9
Work Order 03-01-16
Work Began 05-30-06
Work Completed  
Time Computed 05-30-16
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RELMCO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0035-07-044
THE LEVY COMPANY, L.P. ( 23.99%)
LONE STAR PAVING ( 16.63%)
FLASHER EQUIPMENT COMPANY(4.02%)
Contract # 01163229
Totals 1487816.87 16880.00 29312.00 1.9

CountyREAL
Highway US 83
From RM 336
To RM 337 IN LEAKEY
CSJ 0036-05-033
Proj ID STP 2015(350)
Work Type REHABILITATE EXISTING ROAD
 
2.055 6989144.86 4310.22 1364865.45 19.5
Work Order 01-28-15
Work Began 06-08-15
Work Completed  
Time Computed 05-29-15
Contract Working Days 225
Addl Days Granted 8
Working Days Charged 112
Percent Time Used 48
Contractor(s)
ALLEN KELLER COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0036-05-033
RELMCO, INC. ( 14.97%)
FUQUAY, INC. (0.36%)
Contract # 12143021
Totals 6989144.86 4310.22 1364865.45 19.5

CountyGLASSCOCK
Highway US 87
From HOWARD COUNTY LINE
To STERLING COUNTY LINE
CSJ 0069-02-028
Proj ID NH 2015(931)
Work Type ACP OVERLAY
 
29.997 15257441.66 244539.30 6737600.78 44.1
Work Order 05-19-15
Work Began 09-30-15
Work Completed  
Time Computed 08-19-15
Contract Working Days 111
Addl Days Granted 8
Working Days Charged 67
Percent Time Used 56
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0069-02-028
BARRICADES UNLIMITED (1.57%)
TEX OP CONSTRUCTION, LP(1.24%)
SCR CONSTRUCTION CO., INC. (0.58%)
SOUTHEAST GRINDING & GROOVING, LLC (0.14%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.37%)
Contract # 04153202
Totals 15257441.66 244539.30 6737600.78 44.1

CountySTERLING
Highway US 87
From SH 158 IN STERLING CITY
To COKE COUNTY LINE
CSJ 0069-04-042
Proj ID NH 2016(403)
Work Type ACP OVERLAY
 
15.751 7904447.76 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 06-01-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0069-04-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153227
Totals 7904447.76 0.00 0.00 0.0

CountyTOM GREEN
Highway US 87
From 33RD STREET
To US 67
CSJ 0069-07-103
Proj ID NH 2016(761)
Work Type ACP OVERLAY
 
2.055 1548841.17 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0069-07-103
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163220
Totals 1548841.17 0.00 0.00 0.0

CountyIRION
Highway US 67
From 30.8 MI SOUTH OF TOM GREEN CO LINE
To REAGAN COUNTY LINE
CSJ 0077-02-031
Proj ID STP 1502(413)
Work Type ADD PASSING LANES
 
41.247 30896539.80 348482.57 8579644.60 27.7
Work Order 10-20-15
Work Began 11-16-15
Work Completed  
Time Computed 11-16-15
Contract Working Days 375
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 29
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-02-031
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.14%)
COX PAVING COMPANY, L.P. (6.73%)
PRIMATE CONSTRUCTION, INC. (0.45%)
CONTRACTORS SERVICE COMPANY(0.38%)
DOUBLE A CONTRACTING, L.P. (1.52%)
HJC FARMS, INC.(1.26%)
TEXOP CONSTRUCTION (1.23%)
DELGADO"S CONSTRUCTION (0.97%)
Contract # 07153003
Totals 30896539.80 348482.57 8579644.60 27.7

CountyTOM GREEN
Highway US 67
From CHADBOURNE STREET
To US 87
CSJ 0077-06-090
Proj ID NH 1502(609)
Work Type ACP OVERLAY
 
2.967 6072493.75 368748.88 1572739.86 25.8
Work Order 02-24-16
Work Began 03-28-16
Work Completed  
Time Computed 03-28-16
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 23
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-090
BARRICADES UNLIMITED (2.39%)
CONTRACTORS SERVICE COMPANY(0.40%)
HJC FARMS, INC.(6.77%)
WEST TEXAS RUMBLE STRIP(0.12%)
HUDSON, INC. (2.22%)
O. TREVINO CONSTRUCTION, LLC ( 10.45%)
Contract # 08153247
Totals 6072493.75 368748.88 1572739.86 25.8

CountyTOM GREEN
Highway US 67
From CHAPEL HILL DRIVE
To IRION COUNTY LINE
CSJ 0077-06-094
Proj ID STP 2016(404)
Work Type ACP OVERLAY
 
11.222 8069634.10 0.00 0.00 0.0
Work Order 03-01-16
Work Began 05-31-16
Work Completed  
Time Computed 05-01-06
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0077-06-094
CONTRACTORS SERVICE COMPANY(0.16%)
TEX OP CONSTRUCTION, LP(1.80%)
PRIMATE CONSTRUCTION, INC. (0.43%)
HJC FARMS, INC.(5.05%)
TRP CONSTRUCTION GROUP, LLC(1.60%)
Contract # 12153028
Totals 8069634.10 0.00 0.00 0.0

CountyCROCKETT
Highway IH 10
From 7.52 MILES WEST OF SUTTON CO LINE
To 3.17 MILES WEST OF SUTTON CO LINE
CSJ 0141-01-053
Proj ID NH 2016(858)
Work Type OVERLAY
 
8.833 5457413.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-13-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 0141-01-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163211
Totals 5457413.69 0.00 0.00 0.0

CountySTERLING
Highway SH 158
From GLASSCOCK COUNTY LINE
To US 87
CSJ 0405-02-024
Proj ID NH 2014(078)
Work Type WIDEN ROADWAY TO 4 - LANE UNDIVIDED
 
14.444 22606153.84 858273.10 11719626.22 51.8
CountyZERO COUNTIES
Highway  
From  
To  
CSJ 0405-02-025
Proj ID  
Work Type  
 
  0.00 915878.87 959719.17 0.0
Work Order 01-17-14
Work Began 02-20-14
Work Completed  
Time Computed 02-19-14
Contract Working Days 535
Addl Days Granted 30
Working Days Charged 503
Percent Time Used 89
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0405-02-024
CONTRACTORS SERVICE COMPANY(0.30%)
TEX OP CONSTRUCTION, LP(0.03%)
W.S. CONSTRUCTION COMPANY(6.00%)
W.S. CONSTRUCTION COMPANY(3.57%)
BLACK TOPPER TECHNOLOGY, INC.(5.83%)
WEST TEXAS RUMBLE STRIP(0.16%)
HJC FARMS, INC.(2.33%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.09%)
COPPELL CONSTRUCTION CO., INC. (9.77%)
DOUBLE A CONTRACTING, L.P. (1.03%)
TEXAS SHAFTS, INC. (0.87%)
EAGLE CONCRETE CUTTERS, INC. (0.01%)
RUSSO CORPORATION(0.24%)
MCL CONTRACTING, LLC (0.02%)
MCKINNEY DRILLING COMPANY(0.15%)
GARY A. CRAIN, INC.(0.03%)
WILLIS ELECTRIC CO., LP(0.04%)
Contract # 10133202
Totals 22606153.84 1774151.97 12679345.39 56.0

CountyIRION
Highway SH 163 ETC
From US 67
To CROCKETT COUNTY LINE
CSJ 0412-01-022
Proj ID STP 2015(932)
Work Type SEAL COAT
 
74.644 12380994.03 1368340.38 9075627.89 73.3
Work Order 05-12-15
Work Began 07-13-15
Work Completed  
Time Computed 06-12-15
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 136
Percent Time Used 59
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0412-01-022
ALTUS TRAFFIC MANAGEMENT LLC (0.19%)
CACTUS ASPHALT, A DIVISION OF CACTUS TRANSPORT, INC. ( 20.25%)
STRIPE-A-ZONE, INC.(9.71%)
RICE ENVIRONMENTAL SERVICES(0.06%)
BRYDL CONTRACTING, INC.(0.15%)
MURRAY CONSTRUCTION(0.06%)
D S TEXAS ICON CONSTRUCTION, LLC (0.03%)
Contract # 04153001
Totals 12380994.03 1368340.38 9075627.89 73.3

CountyGLASSCOCK
Highway SH 158
From MIDLAND COUNTY LINE
To 0.3 MILES WEST OF RM 33
CSJ 0463-04-025
Proj ID NH 2016(901)
Work Type ACP OVERLAY
 
17.587 8716678.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0463-04-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163002
Totals 8716678.75 0.00 0.00 0.0

CountyCONCHO
Highway FM 765
From FM 2134
To MCCULLOCH COUNTY LINE
CSJ 0870-04-038
Proj ID STP 2016(071)
Work Type RESTORATION OF EXISTING ROAD
 
9.317 3629462.34 456754.44 1727967.06 47.6
Work Order 10-21-15
Work Began 01-18-16
Work Completed  
Time Computed 12-21-05
Contract Working Days 192
Addl Days Granted 0
Working Days Charged 84
Percent Time Used 43
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0870-04-038
CONTRACTORS SERVICE COMPANY(1.07%)
Contract # 09153012
Totals 3629462.34 456754.44 1727967.06 47.6

CountyTOM GREEN
Highway VA
From VARIOUS ROADWAYS IN SJT DISTRICT
To .
CSJ 0907-00-161
Proj ID STP 1502(163)
Work Type UPGRADE SIGNALS AND ILLUMINATION
 
0.001 1275751.00 43583.00 43583.00 3.4
Work Order 11-16-15
Work Began 00-00-00
Work Completed  
Time Computed 03-18-16
Contract Working Days 174
Addl Days Granted 0
Working Days Charged 17
Percent Time Used 9
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0907-00-161
D. I. J. CONSTRUCTION, INC.(3.58%)
Contract # 09153227
Totals 1275751.00 43583.00 43583.00 3.4

CountyTOM GREEN
Highway VA
From VARIOUS LOCATIONS IN SJT DISTRICT
To .
CSJ 0907-00-165
Proj ID STP 2016(405)
Work Type PAVEMENT MARKINGS
 
0.001 601483.60 220549.61 425905.66 70.8
Work Order 01-29-16
Work Began 04-04-16
Work Completed  
Time Computed 03-29-16
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 41
Contractor(s)
FLASHER EQUIPMENT COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0907-00-165
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12153216
Totals 601483.60 220549.61 425905.66 70.8

CountyTOM GREEN
Highway VA
From VARIOUS ROADWAYS IN SJT DISTRICT
To .
CSJ 0907-00-168
Proj ID NH 1602(048)
Work Type SAFETY IMPROVEMENTS
 
0.134 646028.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 113
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0907-00-168
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163230
Totals 646028.79 0.00 0.00 0.0

CountyRUNNELS
Highway CR
From AT FUZZY CREEK
To .
CSJ 0907-13-011
Proj ID BR 1402(116)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.066 596307.72 5806.72 567464.05 96.2
Work Order 07-16-15
Work Began 11-30-15
Work Completed  
Time Computed 09-15-15
Contract Working Days 54
Addl Days Granted 20
Working Days Charged 86
Percent Time Used 116
Contractor(s)
ACME BRIDGE COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0907-13-011
CONTRACTORS SERVICE COMPANY(0.65%)
RICE ENVIRONMENTAL SERVICES(1.29%)
ROADWAY SPECIALTIES, INC.(0.69%)
Contract # 06153250
Totals 596307.72 5806.72 567464.05 96.2

CountyTOM GREEN
Highway VA
From BU 67-H (SHERWOOD WAY)
To RM 584 (KNICKERBOCKER ROAD)
CSJ 0907-24-036
Proj ID STP 2011(267)TE
Work Type RED ARROYO SHARED - USE PATH
 
3.976 4124673.00 5010.00 3721178.09 91.9
Work Order 08-07-14
Work Began 11-10-14
Work Completed  
Time Computed 11-06-14
Contract Working Days 190
Addl Days Granted 35
Working Days Charged 294
Percent Time Used 130
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0907-24-036
CLASSIC TEJAS CONSTRUCTION, INC. (5.33%)
ANGELO TRUCKING AND CONSTRUCTION INC.( 17.65%)
MUNOZ FOUNDATION DRILLING, INC.(0.36%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.08%)
FIVE STAR ELECTRIC (0.12%)
Contract # 06143038
Totals 4124673.00 5010.00 3721178.09 91.9