Monthly Local Let Maintenance Report For San Angelo District As Of Mar 13, 2024 Page 1 Of 5

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTOM GREEN
HighwayUS0087
FromVARIOUS LOCATIONS IN TOM GREEN COUNTY
ToVARIOUS LOCATIONS IN TOM GREEN COUNTY
CSJ6187-12-001
Proj IDRMC - 618712001
Work TypeMOWING THE RIGHT OF WAY
 
0.00137895.200.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days16
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WEST TEXAS CIVIL CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6187-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11080708
Totals37895.200.000.000.0

CountyTOM GREEN
HighwayUS0087
FromVARIOUS LOCATIONS IN TOM GREEN COUNTY
ToVARIOUS LOCATIONS IN TOM GREEN COUNTY
CSJ6192-30-001
Proj IDRMC - 619230001
Work TypeMOWING THE RIGHT OF WAY
 
0.00160490.920.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days16
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DAVIS COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6192-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03090701
Totals60490.920.000.000.0

CountyCROCKETT
HighwaySH0163
FromVARIOUS LOCATIONS IN CROCKETT, ETC.
ToVARIOUS LOCATIONS IN CROCKETT, ETC.
CSJ6197-27-001
Proj IDRMC - 619727001
Work TypeSTRIP MOWING AND ROADSIDE MOWING
 
0.00157765.8030378.2052.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-04-10
Work Began08-09-10
Work Completed
Time Computed08-09-10
Contract Working Days44
Addl Days Granted0
Working Days Charged17
Percent Time Used38
Contractor(s)
GALINDO'S LANDSCAPING
SUBCONTRACTOR(S) FOR CCSJ: 6197-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01100701
Totals57765.800.0030378.2052.5

CountySUTTON
HighwayUS0277
FromVARIOUS LOCATIONS IN SUTTON, ETC.
ToVARIOUS LOCATIONS IN SCHLEICHER, ETC.
CSJ6197-29-001
Proj IDRMC - 619729001
Work TypeSTRIP MOWING AND ROADSIDE MOWING
 
0.00161335.4080846.0599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-12-10
Work Began07-19-10
Work Completed
Time Computed07-19-10
Contract Working Days46
Addl Days Granted0
Working Days Charged17
Percent Time Used36
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6197-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01100703
Totals61335.400.0080846.0599.9

CountyTOM GREEN
HighwayLP0306
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6197-79-001
Proj IDSUP - 619779001
Work TypeLANDSCAPE MAINTENANCE
 
0.001297899.9271696.1924.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-09
Work Began09-01-09
Work Completed
Time Computed09-01-09
Contract Working Days730
Addl Days Granted0
Working Days Charged303
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6197-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08090750
Totals297899.920.0071696.1924.0

CountyTOM GREEN
HighwayUS0067
FromTOM GREEN COUNTY
ToTOM GREEN COUNTY
CSJ6204-72-001
Proj IDRMC - 620472001
Work TypeSWEEPING AND CLEANING OF HIGHWAYS-URBAN
 
0.00134865.580.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days243
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CHARLIE'S CERTIFIED TRANSMISSIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6204-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12090701
Totals34865.580.000.000.0

CountyKIMBLE
HighwayUS0377
FromCONCHO MENARD KIMBLE REAL EDWARDS CO.
ToCONCHO MENARD KIMBLE REAL EDWARDS CO.
CSJ6206-40-001
Proj IDRMC - 620640001
Work TypeCLEANING AND SEALING JOINTS AND CRACKSCL
 
89.30041399.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-09-10
Work Began04-19-10
Work Completed
Time Computed04-19-10
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MENENDEZ-DONNELL & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6206-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03100702
Totals41399.000.000.000.0

CountyTOM GREEN
HighwayRM0584
From4502 KNICKERBOCKER ROAD
To4502 KNICKERBOCKER ROAD
CSJ6207-26-001
Proj IDSUP - 620726001
Work TypeJANITORIAL SERVICES
 
0.01041603.3039350.3094.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-10
Work Began02-01-10
Work Completed
Time Computed02-01-10
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01100750
Totals41603.300.0039350.3094.5

CountyREAGAN
HighwayUS0067
FromVARIOUS LOCATIONS IN REAGAN COUNTY
ToLOCATIONS IN IRION, GLASSCOCK & CROCKETT
CSJ6211-99-001
Proj IDRMC - 621199001
Work TypeMOWING IN THE RIGHT OF WAY
 
0.00133337.3867990.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-09-10
Work Began11-22-10
Work Completed
Time Computed11-22-10
Contract Working Days25
Addl Days Granted25
Working Days Charged35
Percent Time Used70
Contractor(s)
BRANDON DIERINGER
SUBCONTRACTOR(S) FOR CCSJ: 6211-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07100708
Totals33337.380.0067990.1099.9

CountyTOM GREEN
HighwayUS0087
FromVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6212-03-001
Proj IDSUP - 621203001
Work TypePICNIC AREA MAINTENANCE
 
0.001240850.00226735.0094.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-10
Work Began09-01-10
Work Completed
Time Computed09-01-10
Contract Working Days130
Addl Days Granted25
Working Days Charged142
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6212-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08100704
Totals240850.000.00226735.0094.1

CountyTOM GREEN
HighwayRM0584
From4502 KNICKERBOCKER RD
To4502 KNICKERBOCKER RD
CSJ6221-78-001
Proj IDSUP - 622178001
Work TypeREGIONAL AND DISTRICT JANITORIAL
 
0.01069228.6067001.1896.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-11
Work Began02-01-11
Work Completed
Time Computed02-01-11
Contract Working Days576
Addl Days Granted2
Working Days Charged578
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6221-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02110703
Totals69228.600.0067001.1896.7

CountyTOM GREEN
HighwayUS0087
FromVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
ToVARIOUS LOCATIONS IN SNA ANGELO DISTRICT
CSJ6224-32-001
Proj IDSUP - 622432001
Work TypePICNIC AREA MAINTENANCE
 
0.001240600.00228188.5094.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-31-11
Work Began09-01-11
Work Completed
Time Computed09-01-11
Contract Working Days160
Addl Days Granted0
Working Days Charged143
Percent Time Used89
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6224-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08110701
Totals240600.000.00228188.5094.8

CountySUTTON
HighwayUS0277
FromJUNCTION AREA OFFICE
ToSONORA AREA OFFICE
CSJ6231-17-001
Proj IDSUP - 623117001
Work TypeSTATE USE JANITORIAL
 
0.01016940.0013675.0080.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-11
Work Began09-01-11
Work Completed
Time Computed09-01-11
Contract Working Days365
Addl Days Granted1
Working Days Charged366
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6231-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08110709
Totals16940.000.0013675.0080.7

CountyTOM GREEN
HighwaySH0208
FromROBERT LEE
ToROCKSPRINGS
CSJ6231-27-001
Proj IDSUP - 623127001
Work TypeJANITORIAL COKE STERLING RUNNELS EDWARDS
 
0.01034740.9829013.6583.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-01-11
Work Began08-01-11
Work Completed
Time Computed08-01-11
Contract Working Days396
Addl Days Granted63
Working Days Charged459
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6231-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07110703
Totals34740.980.0029013.6583.5

CountyKIMBLE
HighwayUS0083
FromVARIOUS LOCATIONS IN JUNCTION AREA OFF
ToVARIOUS LOCATIONS IN JUNCTION AREA OFF
CSJ6243-19-001
Proj IDSUP - 624319001
Work TypePICNIC AREA MAINTENANCE & LANDSCAPE MOW
 
0.00199520.9396400.2596.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days365
Addl Days Granted61
Working Days Charged395
Percent Time Used92
Contractor(s)
TIBH INDUSTRIES, INC.
CONCHO RESOURCE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6243-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09120704
Totals99520.930.0096400.2596.8

CountyCROCKETT
HighwaySH0163
FromOZONA MAINT OFFICE
ToOZONA MAINT OFFICE
CSJ6243-54-001
Proj IDSUP - 624354001
Work TypeJANITORIAL
 
0.0109401.006101.0064.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-12
Work Began10-01-12
Work Completed
Time Computed10-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged243
Percent Time Used66
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6243-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08120713
Totals9401.000.006101.0064.8

CountyTOM GREEN
HighwayRM0584
FromDISTRICT GROUNDS LANDSCAPE
ToDISTRICT GROUNDS LANDSCAPE
CSJ6246-35-001
Proj IDSUP - 624635001
Work TypeDISTRICT GROUNDS LANDSCAPE
 
0.00134852.0027609.6879.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-31-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days365
Addl Days Granted30
Working Days Charged395
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
ENTERPRISE PROFESSIONAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6246-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08120706
Totals34852.000.0027609.6879.2

CountyCOKE
HighwaySH0208
FromROBERT LEE
ToROBERT LEE
CSJ6247-88-001
Proj IDSUP - 624788001
Work TypeJANITORIAL
 
0.0107294.003880.0053.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6247-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08120712
Totals7294.000.003880.0053.1

CountyRUNNELS
HighwayUS0067
FromBALLINGER
ToBALLINGER
CSJ6247-89-001
Proj IDSUP - 624789001
Work TypeJANITORIAL
 
0.0107880.005559.8070.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6247-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08120710
Totals7880.000.005559.8070.5

CountySTERLING
HighwayUS0087
FromSTERLING CITY
ToSTERLING CITY
CSJ6247-91-001
Proj IDSUP - 624791001
Work TypeJANITORIAL
 
0.0107716.004980.0064.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-26-12
Work Began09-01-12
Work Completed
Time Computed09-01-12
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6247-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08120711
Totals7716.000.004980.0064.5

page 1 | page 2 | page 3 | page 4 | page 5