Monthly State Let Maintenance Report For Tyler District As Of Aug 10, 2015 Page 1 Of 1

Last Update: Monday, August 10, 2015
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHENDERSON
Highway 0000000
From 2400 NE LOOP 317, ATHENS, HENDERSON CO
To TEXAS 75752
CSJ 4704-01-343
Proj ID CBC - 470401343
Work Type RENOVATION OR REPAIR
 
0.001 596334.00 0.00 538073.10 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 199
Percent Time Used 165
Contractor(s)
CENTURION INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-343
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144218
Totals 596334.00 0.00 538073.10 99.9

CountySMITH
Highway US0069
From VARIOUS ROADWAYS IN THE TYLER DISTRICT
To TO INCLUDE SEALCOAT ROADS
CSJ 6241-15-001
Proj ID RMC - 624115001
Work Type SL THERMO AND RAISED PAVEMENT MARKERS
 
0.010 413930.54 0.00 379811.06 91.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-27-12
Work Began 08-20-12
Work Completed  
Time Computed 07-11-12
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 223
Percent Time Used 87
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6241-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05124003
Totals 413930.54 0.00 379811.06 91.7

CountyWOOD
Highway FM2869
From LAKE HAWKINS BRIDGE
To FM 14
CSJ 6244-35-001
Proj ID RMC - 624435001
Work Type REHABILITATION OF EXISTING ROAD
 
2.419 926296.73 0.00 907337.70 97.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-09-14
Work Began 05-28-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 88
Addl Days Granted 0
Working Days Charged 87
Percent Time Used 98
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6244-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144036
Totals 926296.73 0.00 907337.70 97.9

CountySMITH
Highway US0069
From 5TH STREET SOUTH
To SL 323
CSJ 6251-62-001
Proj ID RMC - 625162001
Work Type MILL AND INLAY
 
1.972 2366195.13 0.00 2586823.77 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-22-14
Work Began 06-10-14
Work Completed 12-31-14
Time Computed 06-09-14
Contract Working Days 40
Addl Days Granted 12
Working Days Charged 62
Percent Time Used 119
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-62-001
DUSTROL, INC.(9.42%)
ALTUS TRAFFIC MANAGEMENT LLC (0.15%)
L. S. EQUIPMENT CO., INC.(8.14%)
STRIPING TECHNOLOGY, L.P.(2.42%)
Contract # 03144038
Totals 2366195.13 0.00 2586823.77 100.0

CountyGREGG
Highway US0080
From VARIOUS ROADS IN GREGG COUNTY
To AND RUSK COUNTY
CSJ 6254-60-001
Proj ID RMC - 625460001
Work Type HMAC OVERLAY
 
0.100 1649680.00 0.00 2611413.48 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-30-13
Work Began 00-00-00
Work Completed  
Time Computed 11-06-13
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 18
Percent Time Used 90
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6254-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09134015
Totals 1649680.00 0.00 2611413.48 99.9

CountyVAN ZANDT
Highway SH0019
From VAN ZANDT COUNTY, ETC
To DISTRICT WIDE
CSJ 6255-21-001
Proj ID RMC - 625521001
Work Type RESURFACING
 
0.100 858848.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6255-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05134013
Totals 858848.60 0.00 0.00 0.0

CountySMITH
Highway US0069
From VARIES
To VARIES
CSJ 6255-71-001
Proj ID RMC - 625571001
Work Type LONG LINE THERMOPLASTIC STRIPING
 
0.100 1386600.00 157825.46 2976574.39 99.9
Work Order 06-28-13
Work Began 07-23-13
Work Completed  
Time Computed 07-11-13
Contract Working Days 255
Addl Days Granted 255
Working Days Charged 508
Percent Time Used 99
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6255-71-001
ANDREWS DIVERSIFIED INDUSTRIES (0.00%)
Contract # 04134037
Totals 1386600.00 157825.46 2976574.39 99.9

CountySMITH
Highway US0069
From VARIOUS LOCATIONS IN
To THE TYLER DISTRICT
CSJ 6262-03-001
Proj ID RMC - 626203001
Work Type SIGNAL MAINTENANCE
 
0.010 271295.00 0.00 278510.40 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-06-13
Work Began 01-03-14
Work Completed 01-07-15
Time Computed 01-20-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 255
Percent Time Used 100
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6262-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10134012
Totals 271295.00 0.00 278510.40 100.0

CountySMITH
Highway US0069
From ANDERSON, CHEROKEE, HENDERSON, RUSK
To SMITH, VAN ZANDT, GREGG & WOOD CO.
CSJ 6262-07-001
Proj ID RMC - 626207001
Work Type GUARDRAIL REPAIR / REPLACE
 
0.100 410640.00 28805.00 502963.25 99.9
Work Order 02-26-14
Work Began 03-05-14
Work Completed  
Time Computed 03-10-14
Contract Working Days 255
Addl Days Granted 120
Working Days Charged 354
Percent Time Used 94
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6262-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11134014
Totals 410640.00 28805.00 502963.25 99.9

CountyVAN ZANDT
Highway IH0020
From KAUFMAN/VAN ZANDT COUNTY LINE
To VAN ZANDT/SMITH COUNTY LINE
CSJ 6264-16-001
Proj ID RMC - 626416001
Work Type IH 20 TOTAL MAINTENANCE
 
83.600 2104643.04 1348932.00 1736666.23 82.5
CountySMITH
Highway IH0020
From VAN ZANDT/SMITH COUNTY LINE
To SMITH/GREGG COUNTY LINE
CSJ 6264-16-002
Proj ID RMC - 626416002
Work Type IH 20 TOTAL MAINTENANCE
 
83.600 2456849.20 37654.50 560045.19 22.7
CountyGREGG
Highway IH0020
From SMITH/GREGG COUNTY LINE
To GREGG/HARRISON COUNTY LINE
CSJ 6264-16-003
Proj ID RMC - 626416003
Work Type IH 20 TOTAL MAINTENANCE
 
83.500 1707298.10 23415.00 439956.08 25.7
Work Order 08-21-14
Work Began 09-02-14
Work Completed  
Time Computed 09-01-14
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 208
Percent Time Used 81
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-16-001
CATOCON, INC.(1.32%)
DUSTROL, INC.(4.05%)
JASCO(6.65%)
TEXANA LAND & ASPHALT, INC.(0.52%)
W.O.E. CONSTRUCTION(3.20%)
STRIPING TECHNOLOGY, L.P.( 13.92%)
REYNOLDS & KAY, LTD. ( 21.53%)
O. TREVINO CONSTRUCTION, LLC (6.38%)
Contract # 06144005
Totals 6268790.34 1410001.50 2736667.50 43.6

CountyVAN ZANDT
Highway SH0019
From IH 20
To SH 64
CSJ 6269-68-001
Proj ID RMC - 626968001
Work Type RESURFACING
 
1.577 763161.34 0.00 778713.99 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-12-14
Work Began 08-11-14
Work Completed 02-04-15
Time Computed 07-21-14
Contract Working Days 19
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 273
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6269-68-001
ALTUS TRAFFIC MANAGEMENT LLC (0.33%)
STRIPING TECHNOLOGY, L.P.(4.37%)
Contract # 04144022
Totals 763161.34 0.00 778713.99 100.0

CountyRUSK
Highway FM0095
From VARIOUS LOCATIONS IN THE
To HENDERSON MAINTENACE SECTION
CSJ 6272-07-001
Proj ID RMC - 627207001
Work Type DITCH CLEANING
 
0.010 245179.40 0.00 245179.40 100.0
CountySMITH
Highway FM2015
From VARIOUS LOCATIONS IN THE
To TYLER MAINTENANCE SECTION
CSJ 6272-07-002
Proj ID RMC - 627207002
Work Type DITCH CLEANING
 
0.010 266189.80 0.00 268048.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-01-14
Work Began 10-15-14
Work Completed 01-22-15
Time Computed 10-13-14
Contract Working Days 188
Addl Days Granted 0
Working Days Charged 66
Percent Time Used 35
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144201
Totals 511369.20 0.00 513227.40 100.0

CountyWOOD
Highway US0069
From VARIOUS ROADWAYS IN THE
To MINEOLA MAINTENANCE SECTION
CSJ 6272-08-001
Proj ID RMC - 627208001
Work Type TREE AND BRUSH REMOVAL
 
0.010 262987.53 8592.27 227306.01 86.4
Work Order 11-19-14
Work Began 12-01-14
Work Completed  
Time Computed 12-08-14
Contract Working Days 255
Addl Days Granted 255
Working Days Charged 161
Percent Time Used 31
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07144005
Totals 262987.53 8592.27 227306.01 86.4

CountyANDERSON
Highway US0084
From VARIOUS ROADWAYS
To WITHIN THE TYLER DISTRICT
CSJ 6278-76-001
Proj ID RMC - 627876001
Work Type RAISED PAVEMENT MARKERS
 
0.001 551815.10 0.00 28761.50 5.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 07-20-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 173
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 8
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6278-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03154005
Totals 551815.10 0.00 28761.50 5.2

CountySMITH
Highway US0069
From VARIOUS LOCATIONS IN
To THE TYLER DISTRICT
CSJ 6279-00-001
Proj ID RMC - 627900001
Work Type LONGLINE THERMO
 
0.010 717547.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6279-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05154204
Totals 717547.50 0.00 0.00 0.0

CountyHENDERSON
Highway SH0031
From VARIOUS LOCATIONS IN
To THE TYLER DISTRICT
CSJ 6279-01-001
Proj ID RMC - 627901001
Work Type SHORTLINE THERMO & RPM'S
 
0.001 387364.01 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
STRIPING TECHNOLOGY, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6279-01-001
BRYDL CONTRACTING, INC.( 28.32%)
Contract # 05154003
Totals 387364.01 0.00 0.00 0.0

CountyHENDERSON
Highway SH0019
From VARIOUS LOCATIONS IN THE
To TYLER DISTRICT
CSJ 6279-02-001
Proj ID RMC - 627902001
Work Type CRACKSEAL - HOT POUR
 
756.230 385408.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS ROAD MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6279-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06154004
Totals 385408.61 0.00 0.00 0.0

CountyRUSK
Highway US0259
From US 259 IN RUSK COUNTY
To FROM FM 315 TO FM 1798
CSJ 6284-92-001
Proj ID RMC - 628492001
Work Type MILL AND INLAY
 
5.990 4309817.27 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 43
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05154011
Totals 4309817.27 0.00 0.00 0.0