Monthly State Let Maintenance Report For Tyler District As Of Feb 10, 2017 Page 1 Of 2

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHENDERSON
Highway0000000
From2400 NE LOOP 317, ATHENS, HENDERSON CO
ToTEXAS 75752
CSJ4704-01-343
Proj IDCBC - 470401343
Work TypeRENOVATION OR REPAIR
 
0.001596334.00538073.1099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged199
Percent Time Used165
Contractor(s)
CENTURION INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-343
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07144218
Totals596334.000.00538073.1099.9

CountySMITH
Highway0000000
From2907 WEST FRONT, TYLER, TX 75702
To2907 WEST FRONT, TYLER, TX 75702
CSJ4704-01-428
Proj IDCBC - 470401428
Work TypeRENOVATION OR REPAIR
 
0.001898100.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days210
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HCI GENERAL CONTRACTORS
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-428
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164220
Totals898100.000.000.000.0

CountySMITH
Highway0000000
From2709 W. FRONT STREET, TYLER, TX. 75702
To2709 W. FRONT STREET, TYLER, TX. 75702
CSJ4704-01-503
Proj IDCBC - 470401503
Work TypeRENOVATION OR REPAIR
 
0.001353750.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days120
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VALCORP ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 4704-01-503
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06164212
Totals353750.000.000.000.0

CountySMITH
HighwayUS0069
FromVARIOUS ROADWAYS IN THE TYLER DISTRICT
ToTO INCLUDE SEALCOAT ROADS
CSJ6241-15-001
Proj IDRMC - 624115001
Work TypeSL THERMO AND RAISED PAVEMENT
 
0.010413930.54379811.0691.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-27-12
Work Began08-20-12
Work Completed
Time Computed07-11-12
Contract Working Days255
Addl Days Granted0
Working Days Charged223
Percent Time Used87
Contractor(s)
HIGHWAY TECHNOLOGIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6241-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05124003
Totals413930.540.00379811.0691.7

CountyVAN ZANDT
HighwaySH0019
FromVAN ZANDT COUNTY, ETC
ToDISTRICT WIDE
CSJ6255-21-001
Proj IDRMC - 625521001
Work TypeRESURFACING
 
0.100858848.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days85
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6255-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05134013
Totals858848.600.000.000.0

CountyVAN ZANDT
HighwayIH0020
FromKAUFMAN/VAN ZANDT COUNTY LINE
ToVAN ZANDT/SMITH COUNTY LINE
CSJ6264-16-001
Proj IDRMC - 626416001
Work TypeIH 20 TOTAL MAINTENANCE
 
83.6002104643.041101369.47100.0
CountySMITH
HighwayIH0020
FromVAN ZANDT/SMITH COUNTY LINE
ToSMITH/GREGG COUNTY LINE
CSJ6264-16-002
Proj IDRMC - 626416002
Work TypeIH 20 TOTAL MAINTENANCE
 
83.6002456849.201002917.61100.0
CountyGREGG
HighwayIH0020
FromSMITH/GREGG COUNTY LINE
ToGREGG/HARRISON COUNTY LINE
CSJ6264-16-003
Proj IDRMC - 626416003
Work TypeIH 20 TOTAL MAINTENANCE
 
83.5001707298.103717744.14100.0
CountyZERO COUNTIES
Highway
From
To
CSJ6264-16-004
Proj ID
Work Type
 
0.003985860.750.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-21-14
Work Began09-02-14
Work Completed08-31-16
Time Computed09-01-14
Contract Working Days255
Addl Days Granted255
Working Days Charged497
Percent Time Used97
Contractor(s)
FIREMAN EXCAVATING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6264-16-001
CATOCON, INC. (2.41)
DUSTROL, INC. (4.28)
JASCO (14.58)
TEXANA LAND & ASPHALT, INC. (5.13)
W.O.E. CONSTRUCTION (8.24)
STRIPING TECHNOLOGY, L.P. (24.75)
REYNOLDS & KAY, LTD. (26.40)
O. TREVINO CONSTRUCTION, LLC (10.92)
MADDEN CONTRACTING COMPANY, LLC. (6.38)
BRYDL CONTRACTING, INC. (0.58)
Contract #06144005
Totals6268790.340.009807891.97100.0

CountyRUSK
HighwayFM1797
FromVARIOUS LOCATIONS IN THE TYLER, LONGVIEW
ToAND RUSK MAINTENANCE SECTIONS
CSJ6272-06-001
Proj IDRMC - 627206001
Work TypeDRAINAGE STRUCTURES
 
0.001637373.00434169.9579.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-20-16
Work Completed
Time Computed00-00-00
Contract Working Days86
Addl Days Granted0
Working Days Charged208
Percent Time Used241
Contractor(s)
EAST TEXAS BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154017
Totals637373.000.00434169.9579.7

CountyHENDERSON
HighwaySH0019
FromVARIOUS LOCATIONS IN THE
ToTYLER DISTRICT
CSJ6279-02-001
Proj IDRMC - 627902001
Work TypeCRACKSEAL - HOT POUR
 
756.230385408.610.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS ROAD MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6279-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06154004
Totals385408.610.000.000.0

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6280-45-001
Proj IDRMC - 628045001
Work TypeMILL AND INLAY
 
0.0011390703.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6280-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11164211
Totals1390703.000.000.000.0

CountyRUSK
HighwayUS0259
FromUS 259 IN RUSK COUNTY
ToFROM FM 315 TO FM 1798
CSJ6284-92-001
Proj IDRMC - 628492001
Work TypeMILL AND INLAY
 
5.9904309817.274700815.85100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-13-15
Work Completed04-15-16
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged52
Percent Time Used120
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-92-001
STRIPING TECHNOLOGY, L.P. (3.47)
SOUTHWEST ENVIRONMENT SERVICES LLC (10.57)
Contract #05154011
Totals4309817.270.004700815.85100.0

CountySMITH
HighwaySH0110
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6288-53-001
Proj IDRMC - 628853001
Work TypeDITCH CLEANING
 
277.9702062527.841825680.3088.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-20-16
Work Completed
Time Computed00-00-00
Contract Working Days190
Addl Days Granted86
Working Days Charged244
Percent Time Used88
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10154004
Totals2062527.840.001825680.3088.5

CountyHENDERSON
HighwayFM0317
FromFM 317 TRM 646 - 648
ToATHENS FISH & GAME LAKE DAM
CSJ6296-25-001
Proj IDRMC - 629625001
Work TypeROADWAY REHAB
 
0.170446216.00352593.7179.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-09-16
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted5
Working Days Charged56
Percent Time Used112
Contractor(s)
FRITCHER CONSTRUCTION SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6296-25-001
DUSTIN ALLEN, INC. (5.26)
SOUTHWEST ENVIRONMENT SERVICES LLC (3.20)
STRIPING TECHNOLOGY, L.P. (0.82)
FLEX SUPPLY, LLC (0.73)
Contract #02164011
Totals446216.000.00352593.7179.8

CountyVAN ZANDT
HighwayIH0020
FromIH-20
ToTOLL 49
CSJ6298-51-001
Proj IDRMC - 629851001
Work TypeTOTAL MAINTENANCE
 
0.0015248720.061393777.5626.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged105
Percent Time Used41
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6298-51-001
W.O.E. CONSTRUCTION (1.37)
CATOCON, INC. (4.11)
TEXANA LAND & ASPHALT, INC. (31.75)
FIREMAN EXCAVATING, INC. (13.50)
STRIPING TECHNOLOGY, L.P. (3.77)
JASCO (10.37)
DUSTROL, INC. (0.05)
FLEX SUPPLY, LLC (2.39)
BRYDL CONTRACTING, INC. (0.26)
STRIPING SYSTEMS, INC. (0.02)
Contract #04164218
Totals5248720.060.001393777.5626.5

CountyWOOD
HighwayFM0014
FromVARIOUS ROADWAYS IN
ToWOOD COUNTY
CSJ6301-14-001
Proj IDRMC - 630114001
Work TypeTREE REMOVAL
 
0.001328110.0023472.007.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-03-17
Work Completed
Time Computed00-00-00
Contract Working Days255
Addl Days Granted0
Working Days Charged21
Percent Time Used8
Contractor(s)
CATOCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164017
Totals328110.000.0023472.007.1

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6301-15-001
Proj IDRMC - 630115001
Work TypeCRACKSEAL
 
0.001597302.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged7
Percent Time Used8
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164216
Totals597302.880.000.000.0

CountyHENDERSON
HighwaySH0031
FromVARIOUS ROADWAYS IN
ToHENDERSON AND ANDERSON COUNTIES
CSJ6303-36-001
Proj IDRMC - 630336001
Work TypeTRAFFIC CONTROL
 
0.001784380.00100325.2512.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-06-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged58
Percent Time Used15
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164003
Totals784380.000.00100325.2512.7

CountyWOOD
HighwayUS0080
FromVARIOUS ROADWAYS IN
ToWOOD AND VAN ZANDT COUNTIES
CSJ6303-37-001
Proj IDRMC - 630337001
Work TypeTRAFFIC CONTROL
 
0.001745751.34127021.5217.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-06-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged58
Percent Time Used15
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164203
Totals745751.340.00127021.5217.0

CountyGREGG
HighwayUS0259
FromVARIOUS ROADWAYS IN
ToGREGG AND RUSK COUNTIES
CSJ6303-38-001
Proj IDRMC - 630338001
Work TypeTRAFFIC CONTROL
 
0.001743152.69206307.3827.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-03-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
N-LINE TRAFFIC MAINTENANCE, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6303-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164016
Totals743152.690.00206307.3827.7

CountySMITH
HighwayUS0069
FromVARIOUS ROADWAYS IN
ToSMITH AND CHEROKEE COUNTIES
CSJ6303-39-001
Proj IDRMC - 630339001
Work TypeTRAFFIC CONTROL
 
0.001739402.69142633.5419.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-05-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged58
Percent Time Used15
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164204
Totals739402.690.00142633.5419.2

CountySMITH
HighwaySH0064
FromVARIOUS ROADWAYS IN
ToTHE TYLER DISTRICT
CSJ6306-16-001
Proj IDRMC - 630616001
Work TypeEAST MILL & INLAY
 
0.0012872970.930.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days31
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MADDEN CONTRACTING COMPANY, LLC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-16-001
PANOLA SIGN & BARRICADE, INC. (0.99)
STRIPING TECHNOLOGY, L.P. (2.80)
STRIPING SYSTEMS, INC. (0.00)
Contract #11164024
Totals2872970.930.000.000.0

page 1 | page 2