Monthly State Let Construction Report For Wichita Falls District As Of Sep 15, 2014 Page 1 Of 2

Last Update: Monday, September 15, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWICHITA
Highway IH 44 ETC
From MAURINE STREET
To SP 325 (EAST FRONTAGE ROAD)
CSJ 0043-09-121
Proj ID IM 0448(016)
Work Type SEAL COAT
 
140.976 5404266.01 0.00 5567525.09 99.9
Work Order 01-06-14
Work Began 04-22-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 53
Percent Time Used 106
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0043-09-121
FLAT LINE, INC.( 20.68%)
RED SIXTEEN CONSTRUCTION, INC. (2.55%)
Contract # 10133222
Totals 5404266.01 0.00 5567525.09 99.9

CountyWICHITA
Highway US 82
From GALVESTON STREET
To MCKINNEY ROAD
CSJ 0044-01-098
Proj ID NH 1302(019)
Work Type OVERLAY
 
2.705 1769278.83 208303.63 539328.69 30.4
Work Order 08-12-13
Work Began 10-08-13
Work Completed  
Time Computed 08-28-13
Contract Working Days 30
Addl Days Granted 2
Working Days Charged 20
Percent Time Used 62
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-01-098
COTHRAN TRUCKING, LLC(1.44%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.14%)
O. TREVINO CONSTRUCTION, LLC (3.49%)
WEST TEXAS RUMBLE STRIP(0.23%)
TEX OP CONSTRUCTION, LP(6.78%)
CROSSROADS, L.P. (0.48%)
Contract # 07133248
Totals 1769278.83 208303.63 539328.69 30.4

CountyCLAY
Highway US 82
From EAST CITY LIMITS OF HENRIETTA
To MONTAGUE COUNTY LINE
CSJ 0044-03-047
Proj ID NH 2013(784)
Work Type REHABILITATION OF EXISTING ROAD
 
12.888 5114930.10 197453.53 600721.23 11.7
Work Order 07-01-13
Work Began 12-18-13
Work Completed  
Time Computed 08-30-13
Contract Working Days 177
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 62
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0044-03-047
W.S. CONSTRUCTION COMPANY(4.96%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.09%)
COTHRAN TRUCKING, LLC(0.16%)
Contract # 05133021
Totals 5114930.10 197453.53 600721.23 11.7

CountyMONTAGUE
Highway US 82
From AT UP RR, 0.8 MI WEST OF US 81
To NEAR RINGGOLD
CSJ 0044-04-044
Proj ID STP 1102(216)RGS
Work Type REPLACE EXISTING BRIDGE FACILITY
 
0.589 6249421.47 0.00 6340552.29 99.9
Work Order 09-06-11
Work Began 01-03-12
Work Completed  
Time Computed 11-05-11
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 243
Percent Time Used 95
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-04-044
TEXAS SHAFTS, INC. (2.66%)
NORTH TEXAS REBAR, LLC (0.31%)
CONCRETE CUTTING BY BOND (0.11%)
JM MATERIALS, INC. (0.14%)
PEACHTREE CONSTRUCTION, LTD. (0.53%)
TRAC-WORK, INC.( 10.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.22%)
TEXAS ALTERNATIVE GRASSER, INC.(0.32%)
MOBILE ENTERPRISES, INC. (1.39%)
ERWIN STEEL WORKS, LLC (0.52%)
ODUM SERVICES, L.P.(0.28%)
NORTH TEXAS CONTRACTING, INC.(7.92%)
AR DANIEL SERVICES (0.91%)
J. E. GUZMAN CONSTRUCTION, INC.(0.26%)
MAXIM CRANE WORKS(0.12%)
LINDAMOOD DEMOLITION, INC. (0.60%)
Contract # 08113202
Totals 6249421.47 0.00 6340552.29 99.9

CountyMONTAGUE
Highway US 82
From NEAR THE EAST CITY LIMITS OF NOCONA
To FM 1815 (EB & WB LANES)
CSJ 0044-06-071
Proj ID NH 2014(270)
Work Type OVERLAY
 
11.428 4997746.20 1245799.66 1861187.55 37.2
Work Order 01-17-14
Work Began 07-09-14
Work Completed  
Time Computed 03-18-14
Contract Working Days 98
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 37
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0044-06-071
TEXAS ALTERNATIVE GRASSER, INC.(0.61%)
CROSSROADS, L.P. (0.37%)
DUSTROL, INC.(1.66%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.69%)
HJC FARMS, INC.(0.96%)
Contract # 12133219
Totals 4997746.20 1245799.66 1861187.55 37.2

CountyCOOKE
Highway US 82
From NEAR WEBER DRIVE
To NEAR IH 35
CSJ 0044-08-066
Proj ID NH 2013(625)
Work Type MISCELLANEOUS CONSTRUCTION
 
6.004 619413.20 168535.94 411502.94 66.4
Work Order 02-18-14
Work Began 06-16-14
Work Completed  
Time Computed 05-19-14
Contract Working Days 61
Addl Days Granted 11
Working Days Charged 46
Percent Time Used 63
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0044-08-066
LIRA ELECTRIC( 43.71%)
DUSTROL, INC.(5.81%)
STRAIGHT LINE SAWING & SEALING (1.21%)
STRIPING TECHNOLOGY, L.P.(1.95%)
FORTSON CONTRACTING, INC.(1.40%)
Contract # 11133208
Totals 619413.20 168535.94 411502.94 66.4

CountyARCHER
Highway US 277
From 1.69 MILES WEST OF FM 368
To 0.795 MILES EAST OF FERGUSON ROAD
CSJ 0156-05-048
Proj ID NH 2013(621)
Work Type WIDEN NON - FREEWAY
 
9.154 16393546.60 1160536.13 7018456.96 42.8
Work Order 11-08-13
Work Began 01-17-14
Work Completed  
Time Computed 05-07-14
Contract Working Days 330
Addl Days Granted 0
Working Days Charged 68
Percent Time Used 20
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-05-048
W.S. CONSTRUCTION COMPANY(7.45%)
ATCI ELECTRICAL(1.94%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.73%)
TEXAS ALTERNATIVE GRASSER, INC.(0.56%)
BARRICADES UNLIMITED (1.17%)
CONTRACTORS SERVICE COMPANY(0.25%)
WEST TEXAS RUMBLE STRIP(0.07%)
TEX OP CONSTRUCTION, LP(0.33%)
HJC FARMS, INC.(0.74%)
LONGHORN MULCHING, INC.(0.34%)
Contract # 08133210
Totals 16393546.60 1160536.13 7018456.96 42.8

CountyBAYLOR
Highway US 277
From 2.78 MILES EAST OF RM 1919
To 0.64 MILES EAST OF US 183/283
CSJ 0156-06-039
Proj ID C 156-6-39
Work Type WIDEN NON - FREEWAY
 
5.896 10550963.24 3530.40 10710601.63 99.9
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-10-12
Contract Working Days 269
Addl Days Granted 75
Working Days Charged 344
Percent Time Used 100
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-06-039
CONTRACTORS SERVICE COMPANY(0.26%)
TEX OP CONSTRUCTION, LP(0.28%)
W.S. CONSTRUCTION COMPANY(6.55%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.10%)
ZACK BURKETT CO. ( 26.33%)
WILLIS ELECTRIC CO., LP(1.32%)
WEST TEXAS RUMBLE STRIP(0.08%)
Contract # 06123203
Totals 10550963.24 3530.40 10710601.63 99.9

CountyWICHITA
Highway IH 44
From ON W FRONTAGE RD/OLD BACON SWITCH
To ROAD AT TRIBUTARY OF GILBERT CREEK
CSJ 0156-07-102
Proj ID BR 2014(783)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.065 393766.00 0.00 0.00 0.0
Work Order 07-18-14
Work Began 09-09-14
Work Completed  
Time Computed 08-03-14
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0156-07-102
DUSTIN ALLEN, INC. (3.80%)
ALTUS TRAFFIC MANAGEMENT LLC (0.62%)
PENHALL COMPANY(0.70%)
LANCO TURF & SEEDING, INC. (1.01%)
Contract # 06143240
Totals 393766.00 0.00 0.00 0.0

CountyBAYLOR
Highway US 277
From KNOX COUNTY LINE
To 2.155 MILES WEST OF US 183
CSJ 0157-01-062
Proj ID NH 2013(235)
Work Type WIDEN NON - FREEWAY
 
11.161 11926754.60 92345.11 11124867.12 93.2
Work Order 02-06-13
Work Began 03-25-13
Work Completed  
Time Computed 03-25-13
Contract Working Days 385
Addl Days Granted 3
Working Days Charged 294
Percent Time Used 75
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0157-01-062
W.S. CONSTRUCTION COMPANY(5.68%)
CONTRACTORS SERVICE COMPANY(0.34%)
WEST TEXAS RUMBLE STRIP(0.07%)
ZACK BURKETT CO. ( 26.21%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.40%)
WILLIS ELECTRIC CO., LP(0.84%)
Contract # 12123202
Totals 11926754.60 92345.11 11124867.12 93.2

CountyBAYLOR
Highway US 277
From NEAR SEYMOUR
To KNOX COUNTY LINE (NB LANES)
CSJ 0157-01-071
Proj ID NH 2014(791)
Work Type OVERLAY
 
11.862 2581730.36 0.00 0.00 0.0
Work Order 07-10-14
Work Began 00-00-00
Work Completed  
Time Computed 07-26-14
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0157-01-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143205
Totals 2581730.36 0.00 0.00 0.0

CountyMONTAGUE
Highway SH 59
From SH 175
To FM 1758
CSJ 0239-02-034
Proj ID STP 2014(792)
Work Type REHABILITATION OF EXISTING ROAD
 
7.660 2026292.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-09-14
Work Began 00-00-00
Work Completed  
Time Computed 09-25-14
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0239-02-034
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143247
Totals 2026292.53 0.00 0.00 0.0

CountyCOOKE
Highway FM 51
From FM 1306
To FM 922
CSJ 0312-01-072
Proj ID STP 2013(469)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
11.855 2224039.60 0.00 2341183.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-13
Work Began 10-07-13
Work Completed  
Time Computed 09-30-13
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 92
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0312-01-072
CROSSROADS, L.P. (0.13%)
DUSTROL, INC.(1.07%)
TOTAL HIGHWAY MAINTENANCE, LLC (4.56%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
DALE BROWN, INC. (0.69%)
Contract # 03133212
Totals 2224039.60 0.00 2341183.18 99.9

CountyYOUNG
Highway SH 16
From GRAHAM CITY LIMITS
To PALO PINTO COUNTY LINE
CSJ 0362-01-046
Proj ID STP 2014(784)HES
Work Type HAZARD ELIMINATION AND SAFETY
 
10.385 183344.50 0.00 0.00 0.0
Work Order 07-10-14
Work Began 00-00-00
Work Completed  
Time Computed 07-26-14
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0362-01-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143044
Totals 183344.50 0.00 0.00 0.0

CountyWICHITA
Highway SH 258
From 0.2 MILES WEST OF FM 2226
To US 82
CSJ 0544-01-020
Proj ID STP 2013(903)HES
Work Type REHABILITATION OF EXISTING ROAD
 
7.000 3882193.04 4455.62 785322.53 20.2
CountyWICHITA
Highway SH 258
From SH 25
To 0.2 MILES WEST OF FM 2226
CSJ 0544-01-021
Proj ID STP 2013(904)
Work Type REHABILITATION OF EXISTING ROAD
 
3.353 1941339.06 211900.00 294806.50 15.1
Work Order 12-19-13
Work Began 03-06-14
Work Completed  
Time Computed 02-17-14
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 68
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0544-01-020
ALTUS TRAFFIC MANAGEMENT LLC (0.48%)
ZACK BURKETT CO. ( 42.92%)
FLAT LINE, INC.(0.83%)
J.V. CONCRETE CONSTRUCTION ( 15.00%)
MARCOM"S MOWING SERVICE, LLC (2.74%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
Contract # 09133206
Totals 5823532.10 216355.62 1080129.03 18.5

CountyBAYLOR
Highway FM 422
From US 82
To EAST CITY LIMITS OF SEYMOUR
CSJ 0814-01-027
Proj ID C 814-1-27
Work Type UPGRADING OF A NON - FREEWAY FACILITY
 
0.847 3332046.95 21670.00 3400067.47 99.9
Work Order 09-13-12
Work Began 02-11-13
Work Completed  
Time Computed 02-11-13
Contract Working Days 245
Addl Days Granted 21
Working Days Charged 244
Percent Time Used 91
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0814-01-027
W.S. CONSTRUCTION COMPANY( 37.37%)
CONTRACTORS SERVICE COMPANY(0.56%)
TEXAS ALTERNATIVE GRASSER, INC.(0.55%)
ZACK BURKETT CO. ( 26.68%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.02%)
WILLIS ELECTRIC CO., LP(8.41%)
Contract # 07123006
Totals 3332046.95 21670.00 3400067.47 99.9

CountyMONTAGUE
Highway FM 455
From MONTAGUE
To FM 1749
CSJ 0845-01-016
Proj ID STP 2013(686)
Work Type REHABILTATION OF EXISTING ROADWAY
 
14.179 3371976.79 93235.25 3837668.37 99.9
Work Order 09-04-13
Work Began 11-13-13
Work Completed  
Time Computed 09-20-13
Contract Working Days 151
Addl Days Granted 30
Working Days Charged 111
Percent Time Used 61
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0845-01-016
CROSSROADS, L.P. (1.42%)
W.S. CONSTRUCTION COMPANY(1.54%)
MARCOM"S MOWING SERVICE, LLC (0.55%)
LANCO TURF & SEEDING, INC. (1.74%)
TOTAL HIGHWAY MAINTENANCE, LLC (3.22%)
EAGLE AGGREGATE TRANSPORTATION, LLC. (1.32%)
ALLIED DRILLING COMPANY(0.03%)
MCRYAN HAULING, INC. (1.01%)
INDEPENDENT UTILITY CONSTRUCTION INCORPORATED(0.12%)
Contract # 05133231
Totals 3371976.79 93235.25 3837668.37 99.9

CountyCOOKE
Highway FM 922
From MONTAGUE COUNTY LINE
To FM 373
CSJ 0845-03-056
Proj ID STP 2014(357)
Work Type RESTORATION
 
13.082 4230047.49 0.00 0.00 0.0
Work Order 04-15-14
Work Began 00-00-00
Work Completed  
Time Computed 06-14-14
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0845-03-056
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143007
Totals 4230047.49 0.00 0.00 0.0

CountyWICHITA
Highway VA
From VARIOUS LOCATIONS DISTRICT WIDE
To .
CSJ 0903-00-072
Proj ID STP 2014(086)
Work Type MISCELLANEOUS WORK
 
1.000 399924.61 66675.53 66675.53 16.6
Work Order 04-15-14
Work Began 08-25-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 4
Percent Time Used 8
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-072
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143032
Totals 399924.61 66675.53 66675.53 16.6

CountyWICHITA
Highway VA
From AT VARIOUS LOCATIONS IN WICHITA
To FALLS DISTRICT
CSJ 0903-00-075
Proj ID NH 2015(078)
Work Type CONSTRUCT ADA CURB RAMPS
 
0.001 3132333.32 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 223
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0903-00-075
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143037
Totals 3132333.32 0.00 0.00 0.0

page 1 | page 2