Monthly State Let Maintenance Report For Wichita Falls District As Of Feb 10, 2017 Page 1 Of 1

Last Update: Friday, February 10, 2017
FTP Icon
page 1

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyARCHER
HighwayFM2846
FromUS 82
ToFM 1180
CSJ6294-73-001
Proj IDRMC - 629473001
Work TypeREPLACE CULVERTS
 
0.001390263.40339927.6587.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-05-16
Work Completed
Time Computed00-00-00
Contract Working Days67
Addl Days Granted0
Working Days Charged29
Percent Time Used43
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09164002
Totals390263.400.00339927.6587.1

CountyWICHITA
HighwayIH0044
FromVARIOUS LOCATIONS
ToDISTRICT WIDE
CSJ6300-25-001
Proj IDRMC - 630025001
Work TypeONCALL GUARDRAIL REPAIR
 
0.001731750.00361974.0049.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted60
Working Days Charged213
Percent Time Used50
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164002
Totals731750.000.00361974.0049.4

CountyWICHITA
HighwayUS0082
FromVARIOUS ROADWAYS
ToDISTRICT WIDE
CSJ6304-00-001
Proj IDRMC - 630400001
Work TypeDW ONCALL PAVEMENT MARKINGS & RPM
 
0.001853660.00298133.7234.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-26-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged94
Percent Time Used25
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6304-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07164013
Totals853660.000.00298133.7234.9

CountyWICHITA
HighwayUS0082
FromVARIOUSE BRIDGES IN COOKE
ToWICHITA & YOUNG COUNTY
CSJ6304-34-001
Proj IDBPM - 630434001
Work TypeBRIDGE MAINTENANCE
 
0.001589293.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174201
Totals589293.700.000.000.0

CountyCOOKE
HighwayFM0372
FromVARIOUS ROADWAYS IN COOKE CLAY
ToMONTAGUE WICHITA & WILBARGER COUNTY
CSJ6308-61-001
Proj IDRMC - 630861001
Work TypeCRACK SEAL - HOT POUR
 
0.001315400.0025770.008.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-16-17
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged8
Percent Time Used17
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6308-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164019
Totals315400.000.0025770.008.1

CountyARCHER
HighwaySH0079
FromVARIOUS ROADWAYS IN ARCHER BAYLOR
ToYOUNG & THROCKMORTON COUNTY
CSJ6308-62-001
Proj IDRMC - 630862001
Work TypeCRACK SEAL - HOT POUR
 
0.001291621.0075068.0025.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-28-16
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged16
Percent Time Used35
Contractor(s)
ARCC CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6308-62-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164221
Totals291621.000.0075068.0025.7

CountyCOOKE
HighwayIH0035
FromVARIOUS ROADWAYS IN
ToCOOKE AND MONTAGUE COUNTY
CSJ6308-65-001
Proj IDRMC - 630865001
Work TypeROUTINE STREET SWEEPING
 
0.001288904.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6308-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164202
Totals288904.000.000.000.0

CountyWICHITA
HighwayIH0044
FromVARIOUS ROADWAYS IN
ToWICHITA & WILBARGER COUNTY
CSJ6308-66-001
Proj IDRMC - 630866001
Work TypeROUTINE STREET SWEEPING & DEBRIS
 
0.001376742.0091410.1524.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began12-13-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged43
Percent Time Used11
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6308-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10164002
Totals376742.000.0091410.1524.2

CountyYOUNG
HighwaySH0016
FromVARIOUS ROADWAYS IN ARCHER BAYLOR
ToCLAY MONTAGUE & WICHITA COUNTY
CSJ6309-82-001
Proj IDRMC - 630982001
Work TypeCULVERT REPLACEMENT
 
0.001956061.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days75
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
3LW MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6309-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174202
Totals956061.000.000.000.0

CountyARCHER
HighwaySH0079
FromVARIOUS ROADWAYS IN
ToARCHER COUNTY
CSJ6309-86-001
Proj IDRMC - 630986001
Work TypeGUARDRAIL UPGRADE
 
0.001632007.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6309-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02174002
Totals632007.500.000.000.0

CountyWICHITA
HighwayUS0082
FromVARIOUS ROADWAYS IN COOKE CLAY
ToMONTAGUE WICHITA & WILBARGER CO
CSJ6311-23-001
Proj IDRMC - 631123001
Work TypeDEBRIS ROMOVAL
 
0.001519787.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days275
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WILSON CONTRACTING
SUBCONTRACTOR(S) FOR CCSJ: 6311-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174203
Totals519787.000.000.000.0

page 1