Monthly State Let Construction Report For Yoakum District As Of Apr 11, 2014 Page 1 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGONZALES
Highway US 90A ETC
From US 183
To BU 183V
CSJ 0025-06-052
Proj ID STP 2014(050)
Work Type SEAL COAT
 
126.131 5288542.63 0.00 1136546.62 21.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-06-052
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10133212
Totals 5288542.63 0.00 1136546.62 21.4

CountyGONZALES
Highway US 90A
From 1.3 MI. WEST OF FM 2091
To TO US 183
CSJ 0025-06-053
Proj ID STP 2014(510)
Work Type ACP OVERLAY
 
4.567 1207655.31 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-06-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143213
Totals 1207655.31 0.00 0.00 0.0

CountyGONZALES
Highway SH 97 ETC
From SH 304
To 0.4 MI EAST OF FM 2814
CSJ 0025-07-062
Proj ID STP 2014(816)HESG
Work Type ADDING RUMBLE STRIP
 
204.581 669745.79 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-07-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143035
Totals 669745.79 0.00 0.00 0.0

CountyVICTORIA
Highway US 59
From 0.105 MI. WEST OF BU 59-T
To .396 MI. WEST OF LP 463 IN VICTORIA
CSJ 0088-05-087
Proj ID NH 2014(454)
Work Type ACP OVERLAY
 
3.160 1504543.17 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-087
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143029
Totals 1504543.17 0.00 0.00 0.0

CountyVICTORIA
Highway US 59
From 0.02 MI. NORTH OF LOOP 463
To 0.03 MI. NORTH OF US 87
CSJ 0088-05-089
Proj ID C 88-5-89
Work Type CONSTRUCT FRONTAGE ROADS
 
3.446 14995694.93 808652.99 4279470.45 28.5
Work Order 08-19-13
Work Began 10-03-13
Work Completed  
Time Computed 09-15-13
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 30
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-089
FLASHER EQUIPMENT COMPANY(0.68%)
JUST GROOVING, LTD.(0.02%)
THE LEVY COMPANY, L.P. (1.32%)
MURRAY CONSTRUCTION(0.30%)
PRIMATE CONSTRUCTION, INC. (0.24%)
ROADWAY SPECIALTIES, INC.(1.85%)
SHINN & GREGORY, INC.(0.66%)
BILL HALL JR. TRUCKING, LTD. (0.00%)
RAMI MATERIALS TRANSPORT, LLC(0.00%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
Contract # 05133205
Totals 14995694.93 808652.99 4279470.45 28.5

CountyVICTORIA
Highway US 59
From 0.28 MI. SOUTH OF US 87
To 0.25 MI. NORTH OF US 87
CSJ 0088-05-090
Proj ID BR 1302(016)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.530 7826113.14 44723.60 753299.48 9.6
Work Order 10-17-13
Work Began 00-00-00
Work Completed  
Time Computed 02-14-14
Contract Working Days 270
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-090
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07133043
Totals 7826113.14 44723.60 753299.48 9.6

CountyJACKSON
Highway US 59
From WHARTON C/L
To SH 172
CSJ 0089-05-045
Proj ID NH 2014(641)
Work Type ACP OVERLAY
 
4.659 3274455.77 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-05-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143006
Totals 3274455.77 0.00 0.00 0.0

CountyWHARTON
Highway US 59
From AT CR 212
To INTERSECTION
CSJ 0089-08-095
Proj ID NH 2013(917)
Work Type INTERSECTION IMPROVEMENT
 
2.526 2072944.64 422594.45 568809.85 27.4
Work Order 01-06-14
Work Began 02-24-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 13
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-08-095
COWBELL TRAFFIC SERVICES, INC. (0.78%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.36%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.51%)
FUQUAY, INC. (1.00%)
MURRAY CONSTRUCTION(0.64%)
Contract # 09133236
Totals 2072944.64 422594.45 568809.85 27.4

CountyVICTORIA
Highway BU 59-T
From AT INTERSECTION OF BU 77
To IN VICTORIA
CSJ 0089-19-009
Proj ID C 89-19-9
Work Type ADD TURN LANE
 
0.043 204613.44 92352.88 104990.31 51.3
Work Order 09-17-13
Work Began 02-25-14
Work Completed  
Time Computed 10-03-13
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 9
Percent Time Used 36
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-19-009
HIGHWAY BARRICADES AND SERVICES, LLC (3.18%)
D&S TEXAS ICON CONSTRUCTION, LLC (4.17%)
Contract # 08133268
Totals 204613.44 92352.88 104990.31 51.3

CountyDEWITT
Highway US 183
From EMIL BLANK ROAD
To 0.20 MI. NORTH OF US 77A
CSJ 0154-04-030
Proj ID C 154-4-30
Work Type CONSTRUCT AUX. LANES FOR SUPER 2
 
13.549 9614974.97 223726.32 4883139.42 50.7
Work Order 04-26-13
Work Began 06-13-13
Work Completed  
Time Computed 05-12-13
Contract Working Days 255
Addl Days Granted 0
Working Days Charged 150
Percent Time Used 58
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0154-04-030
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.23%)
FLASHER EQUIPMENT COMPANY(1.84%)
M.V. HENKE ENTERPRISES, INC. (0.14%)
MPB, INC.(0.33%)
MURRAY CONSTRUCTION(0.39%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.41%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.71%)
Contract # 02133003
Totals 9614974.97 223726.32 4883139.42 50.7

CountyJACKSON
Highway SH 35
From MATAGORDA COUNTY LINE
To SH 172
CSJ 0179-09-033
Proj ID STP 2014(589)
Work Type ACP OVERLAY
 
8.109 2381189.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0179-09-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143214
Totals 2381189.69 0.00 0.00 0.0

CountyAUSTIN
Highway SH 36
From SH 159 NORTH OF BELLVILLE
To WASHINGTON COUNTY LINE
CSJ 0187-02-064
Proj ID C 187-2-64
Work Type CONSTRUCT AUXILLARY LANES
 
8.540 10689701.03 135664.00 8109449.59 75.8
Work Order 10-24-12
Work Began 01-14-13
Work Completed  
Time Computed 12-23-12
Contract Working Days 270
Addl Days Granted 14
Working Days Charged 231
Percent Time Used 81
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0187-02-064
BATTERSON,LLP(2.16%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.19%)
TEXAS ALTERNATIVE GRASSER, INC.(0.35%)
CEN TEX HYDROSEED, INC.(0.10%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (0.83%)
WEST TEXAS RUMBLE STRIP(0.06%)
MURRAY CONSTRUCTION(0.48%)
PEDRO CARLOS CONSTRUCTION CO.(2.35%)
FARR FOUNDATION, INC.(0.51%)
JEFFERY BAILEY TRUCKING, INC.(1.04%)
Contract # 08123209
Totals 10689701.03 135664.00 8109449.59 75.8

CountyAUSTIN
Highway SH 36
From 0.1 MI. NORTH OF US 90
To 0.1 MI. NORTH OF FM 1094
CSJ 0187-03-061
Proj ID NH 2012(466)
Work Type REHABILITATE ROADWAY
 
1.000 3799066.71 1447.00 4054009.21 99.9
Work Order 06-29-12
Work Began 08-29-12
Work Completed  
Time Computed 08-28-12
Contract Working Days 210
Addl Days Granted 4
Working Days Charged 202
Percent Time Used 94
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0187-03-061
WOLFF CONSTRUCTION ( 16.03%)
ENVIRONMENTAL SAFETY SERVICES, INC.(0.74%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.34%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.07%)
MURRAY CONSTRUCTION(0.45%)
ROGER"S TREE SERVICE (0.15%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.48%)
BILL HALL JR. TRUCKING, LTD. (1.34%)
Contract # 04123202
Totals 3799066.71 1447.00 4054009.21 99.9

CountyWHARTON
Highway SH 60
From 0.215 MI. S. OF AUSTIN COUNTY LINE
To US 90A
CSJ 0240-02-030
Proj ID STP 2013(485)
Work Type RESTORE ROADWAY
 
4.819 2921571.83 161884.15 1074530.58 36.7
Work Order 05-29-13
Work Began 09-11-13
Work Completed  
Time Computed 07-28-13
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 105
Percent Time Used 87
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0240-02-030
RICE ENVIRONMENTAL SERVICES(1.00%)
D. I. J. CONSTRUCTION, INC.(2.90%)
MURRAY CONSTRUCTION(0.68%)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.51%)
A.J.J.A . TRUCKING, INC. (2.83%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
STAFF CONCRETE (4.37%)
MPB, INC.(0.28%)
DEVTEX INC.(0.14%)
Contract # 03133234
Totals 2921571.83 161884.15 1074530.58 36.7

CountyWHARTON
Highway SH 71
From AT TRES PALACIOS RIVER IN EL CAMPO
To STR # 0266-06-036
CSJ 0266-06-044
Proj ID BR 2013(593)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.164 1218475.90 137318.00 500925.55 41.1
Work Order 09-10-13
Work Began 11-13-13
Work Completed  
Time Computed 11-09-13
Contract Working Days 135
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 38
Contractor(s)
MENADE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-06-044
ENVIRONMENTAL ALLIES, L.P. (0.13%)
WILLOW CITY SIGN & RAIL, INC.(1.28%)
PROFESSIONAL TRAFFIC CONTROL, LLC(1.21%)
LONE STAR HIGHWAY PRODUCTS, INC. (0.00%)
MESA ROD BUSTERS, INC. (0.89%)
YORK & YORK FOUNDATION DRILLING, INC.(7.13%)
Contract # 04133229
Totals 1218475.90 137318.00 500925.55 41.1

CountyWHARTON
Highway SH 71
From WCR 405
To MATAGORDA COUNTY LINE
CSJ 0266-06-045
Proj ID STP 2014(740)
Work Type PAVEMENT REPAIR AND SURFACING
 
5.473 2333301.84 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REXCO CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0266-06-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143236
Totals 2333301.84 0.00 0.00 0.0

CountyFAYETTE
Highway US 77
From SCHULENBURG SOUTH CITY LIMITS
To LAVACA COUNTY LINE
CSJ 0269-01-027
Proj ID C 269-1-27
Work Type CONSTRUCT AUXILLARY LANES
 
14.309 6078391.95 65032.36 6134359.32 99.9
Work Order 09-13-12
Work Began 12-11-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 210
Addl Days Granted 4
Working Days Charged 211
Percent Time Used 98
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0269-01-027
FLASHER EQUIPMENT COMPANY(2.84%)
MURRAY CONSTRUCTION(0.54%)
M.V. HENKE ENTERPRISES, INC. (0.11%)
TEXAS ALTERNATIVE GRASSER, INC.(0.22%)
ROADWAY SPECIALTIES, INC.(3.10%)
RELMCO, INC. (5.29%)
COWBELL TRAFFIC SERVICES, INC. (0.37%)
Contract # 07123214
Totals 6078391.95 65032.36 6134359.32 99.9

CountyLAVACA
Highway US 77A
From 0.821 MI. WEST OF US 77
To US 90A
CSJ 0269-03-033
Proj ID STP 2013(592)
Work Type ACP OVERLAY
 
10.501 2314921.52 586360.85 2684410.43 99.9
Work Order 06-20-13
Work Began 09-09-13
Work Completed  
Time Computed 07-01-13
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 64
Percent Time Used 142
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0269-03-033
RAMI MATERIALS TRANSPORT, LLC(3.10%)
DUSTROL, INC.(0.44%)
FLASHER EQUIPMENT COMPANY(5.25%)
PRIMATE CONSTRUCTION, INC. (1.95%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.20%)
Contract # 04133019
Totals 2314921.52 586360.85 2684410.43 99.9

CountyGONZALES
Highway SH 80
From FM 446
To 1.23 MI. NORTH OF FM 1682
CSJ 0287-03-029
Proj ID STP 2014(591)
Work Type ACP OVERLAY
 
10.399 2198746.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0287-03-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143209
Totals 2198746.80 0.00 0.00 0.0

CountyFAYETTE
Highway SH 95
From FLATONIA CITY LIMITS
To LAVACA COUNTY LINE
CSJ 0324-01-024
Proj ID STP 2014(550)
Work Type PAVEMENT REPAIR AND SURFACING
 
3.706 2459856.61 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0324-01-024
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143210
Totals 2459856.61 0.00 0.00 0.0

page 1 | page 2 | page 3