Monthly State Let Construction Report For Yoakum District As Of Feb 11, 2016 Page 1 Of 6

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyGONZALES
Highway US 90A ETC
From SH 80
To 0.25 MI. E. OF CR 143
CSJ 0025-05-020
Proj ID STP 2016(130)
Work Type SEAL COAT
 
219.743 7274576.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-05-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153215
Totals 7274576.88 0.00 0.00 0.0

CountyGONZALES
Highway US 90A
From 1.3 MI. WEST OF FM 2091
To TO US 183
CSJ 0025-06-053
Proj ID STP 2014(510)
Work Type ACP OVERLAY
 
4.567 1207655.31 0.00 1644731.20 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-05-14
Work Began 06-09-14
Work Completed 01-27-15
Time Computed 06-01-14
Contract Working Days 45
Addl Days Granted 7
Working Days Charged 43
Percent Time Used 82
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0025-06-053
COWBELL TRAFFIC SERVICES, INC. (1.07%)
SCR CONSTRUCTION CO., INC. (2.30%)
ROADSAFE TRAFFIC SYSTEMS, INC. (3.43%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
Contract # 03143213
Totals 1207655.31 0.00 1644731.20 100.0

CountyGONZALES
Highway SH 97 ETC
From .16 MI. S. OF S. SANDY FORK CK REL
To US 90
CSJ 0025-07-061
Proj ID STP 2015(238)
Work Type SEAL COAT
 
137.089 5886483.28 0.00 6180676.75 99.9
Work Order 11-10-14
Work Began 05-05-15
Work Completed  
Time Computed 05-05-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 88
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0025-07-061
BATTERSON,LLP( 13.93%)
Contract # 10143206
Totals 5886483.28 0.00 6180676.75 99.9

CountyFAYETTE
Highway US 90
From US 77
To IH 10
CSJ 0026-03-043
Proj ID STP 2016(506)HES
Work Type SAFETY TREAT FIXED OBJECTS
 
3.326 958370.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0026-03-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163220
Totals 958370.00 0.00 0.00 0.0

CountyVICTORIA
Highway US 59
From 0.105 MI. WEST OF BU 59-T
To .396 MI. WEST OF LP 463 IN VICTORIA
CSJ 0088-05-087
Proj ID NH 2014(454)
Work Type ACP OVERLAY
 
3.160 1504543.17 11331.04 1232683.46 81.9
Work Order 04-15-14
Work Began 10-05-15
Work Completed  
Time Computed 09-21-15
Contract Working Days 25
Addl Days Granted 16
Working Days Charged 33
Percent Time Used 80
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-087
COWBELL TRAFFIC SERVICE, INC.(0.67%)
PRIMATE CONSTRUCTION, INC. (2.49%)
ROADSAFE TRAFFIC SYSTEMS, INC. (4.18%)
Contract # 02143029
Totals 1504543.17 11331.04 1232683.46 81.9

CountyVICTORIA
Highway US 59
From 0.02 MI. NORTH OF LOOP 463
To 0.03 MI. NORTH OF US 87
CSJ 0088-05-089
Proj ID C 88-5-89
Work Type CONSTRUCT FRONTAGE ROADS
 
3.446 14995694.93 113408.42 12490292.09 83.4
Work Order 08-19-13
Work Began 10-03-13
Work Completed  
Time Computed 09-15-13
Contract Working Days 270
Addl Days Granted 43
Working Days Charged 331
Percent Time Used 105
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-089
FLASHER EQUIPMENT COMPANY(0.68%)
JUST GROOVING, LTD.(0.02%)
THE LEVY COMPANY, L.P. (1.32%)
MURRAY CONSTRUCTION(0.30%)
PRIMATE CONSTRUCTION, INC. (0.24%)
ROADWAY SPECIALTIES, INC.(1.85%)
SHINN & GREGORY, INC.(0.66%)
BILL HALL JR. TRUCKING, LTD. (0.00%)
RAMI MATERIALS TRANSPORT, LLC(0.00%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
BRANNAN PAVING CO., LTD. (1.58%)
NATIONAL WORKS, INC. (0.41%)
Contract # 05133205
Totals 14995694.93 113408.42 12490292.09 83.4

CountyVICTORIA
Highway US 59
From 0.28 MI. SOUTH OF US 87
To 0.25 MI. NORTH OF US 87
CSJ 0088-05-090
Proj ID BR 1302(016)
Work Type REPLACE BRIDGES AND APPROACHES
 
0.530 7826113.14 250966.46 7723329.15 98.9
Work Order 10-17-13
Work Began 06-02-14
Work Completed  
Time Computed 02-14-14
Contract Working Days 270
Addl Days Granted 10
Working Days Charged 301
Percent Time Used 107
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-090
N-LINE TRAFFIC MAINTENANCE, L.P. (0.36%)
ATS DRILLING, INC. ( 10.18%)
HAYWARD BAKER, INC.(1.25%)
PRIMATE CONSTRUCTION, INC. (0.13%)
WEST TEXAS RUMBLE STRIP(0.04%)
A & R DEMOLITION (1.59%)
ROADWAY SPECIALTIES, INC.(2.49%)
FLASHER EQUIPMENT COMPANY(0.43%)
THE LEVY COMPANY, L.P. (1.49%)
MCL CONTRACTING, LLC (0.79%)
BILL HALL JR. TRUCKING, LTD. (0.00%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (0.00%)
VALCO CONSTRUCTION (0.06%)
Contract # 07133043
Totals 7826113.14 250966.46 7723329.15 98.9

CountyVICTORIA
Highway US 59
From SP 91_________________0446020
To 0.157 MI. NORTH OF FM 446
CSJ 0088-05-093
Proj ID NH 2015(996)
Work Type ACP OVERLAY
 
3.359 2446596.31 405717.29 453342.73 18.5
Work Order 05-21-15
Work Began 00-00-00
Work Completed  
Time Computed 07-01-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 5
Percent Time Used 11
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0088-05-093
COWBELL TRAFFIC SERVICES, INC. (0.61%)
SCR CONSTRUCTION CO., INC. (2.56%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.41%)
Contract # 04153041
Totals 2446596.31 405717.29 453342.73 18.5

CountyJACKSON
Highway US 59
From FROM 0.5 MI. NORTH OF LAVACA RIVER
To VICTORIA COUNTY LINE
CSJ 0089-03-088
Proj ID NH 2016(508)
Work Type ACP OVERLAY
 
6.564 6620873.22 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-03-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01163029
Totals 6620873.22 0.00 0.00 0.0

CountyJACKSON
Highway US 59
From WHARTON C/L
To SH 172
CSJ 0089-05-045
Proj ID NH 2014(641)
Work Type ACP OVERLAY
 
4.659 3274455.77 0.00 3525618.29 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-20-14
Work Began 10-01-14
Work Completed 09-02-15
Time Computed 08-01-14
Contract Working Days 75
Addl Days Granted 15
Working Days Charged 90
Percent Time Used 100
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-05-045
PRIMATE CONSTRUCTION, INC. ( 11.39%)
PENHALL COMPANY(0.19%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.54%)
R & A TRANSPORT, INC.(0.00%)
KL DURHAM CONSTRUCTION, LLC(3.83%)
Contract # 04143006
Totals 3274455.77 0.00 3525618.29 100.0

CountyWHARTON
Highway US 59
From FM 647 (NORTHBOUND ONLY)
To JACKSON COUNTY LINE
CSJ 0089-06-079
Proj ID NH 2016(700)
Work Type PAVEMENT REPAIR & ACP OVERLAY
 
8.974 3681313.69 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163029
Totals 3681313.69 0.00 0.00 0.0

CountyWHARTON
Highway US 59
From BU 59 SOUTH OF EL CAMPO
To FM 1163
CSJ 0089-06-081
Proj ID NH 1502(476)
Work Type CONSTRUCT FRONTAGE RO025809111
 
2.602 18889263.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 324
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-081
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153007
Totals 18889263.03 0.00 0.00 0.0

CountyWHARTON
Highway US 59
From SL 523 NORTH OF LOUSIE
To SL 523 SOUTH OF LOUISE
CSJ 0089-06-082
Proj ID STP 2014(788)HES
Work Type INSTALL CABLE MEDIAN BARRIER
 
3.670 490190.00 0.00 474030.25 100.0
CountyCOLORADO
Highway SH 71
From 0.4 MI WEST OF FM 1890
To 0.4 MI SOUTH OF US 90
CSJ 0266-02-062
Proj ID STP 2014(789)HES
Work Type INSTALL MEDIAN BARRIER
 
4.006 391124.00 0.00 368276.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-02-14
Work Began 11-07-14
Work Completed 03-12-15
Time Computed 09-18-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 35
Percent Time Used 58
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-082
POTTS DISTRIBUTING CO. (0.00%)
Contract # 06143043
Totals 881314.00 0.00 842306.75 100.0

CountyWHARTON
Highway US 59
From AT FM 647, FM 1160 & FM 441
To UNDERPASSES
CSJ 0089-06-083
Proj ID NH 2014(996)
Work Type RAISE STRUCTURES
 
0.719 1645644.60 80656.07 786528.36 47.7
Work Order 08-04-14
Work Began 04-08-15
Work Completed  
Time Computed 10-03-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 45
Percent Time Used 100
Contractor(s)
LONE STAR ROAD CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-06-083
GMJ PAVING CO. ( 26.32%)
ODUM SERVICES, L.P.(4.22%)
A-1 EROSION CONTROL, LLC (0.85%)
LONESTAR TRAFFIC SAFETY, LLC (0.45%)
NBG CONSTRUCTORS, INC. ( 14.70%)
AGGREGATE TECHNOLOGIES, INC. (2.67%)
PROFFESSIONAL TRAFFIC CONTROL, LLC.(1.15%)
Contract # 06143058
Totals 1645644.60 80656.07 786528.36 47.7

CountyWHARTON
Highway US 59
From AT INTERSECTION OF SH 71
To IN EL CAMPO
CSJ 0089-07-147
Proj ID NH 1402(107)
Work Type GREEN RIBBON LANDSCAPING
 
0.001 160087.79 412.67 159061.50 100.0
Work Order 10-17-14
Work Began 12-05-14
Work Completed 01-27-16
Time Computed 12-05-14
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 64
Contractor(s)
GEORGE MEEKS LANDPRO, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0089-07-147
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143027
Totals 160087.79 412.67 159061.50 100.0

CountyWHARTON
Highway US 59
From AT CR 212
To INTERSECTION
CSJ 0089-08-095
Proj ID NH 2013(917)
Work Type INTERSECTION IMPROVEMENT
 
2.526 2072944.64 0.00 2032302.12 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-06-14
Work Began 02-24-14
Work Completed 12-31-14
Time Computed 01-22-14
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 43
Percent Time Used 71
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0089-08-095
COWBELL TRAFFIC SERVICES, INC. (0.78%)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.36%)
INTERSTATE BARRICADES & MARKINGS, INC. (1.51%)
FUQUAY, INC. (1.00%)
MURRAY CONSTRUCTION(0.64%)
JUAN DEANDA TRUCKING, LLC DBA JUAN DEANDA TRUCKING (2.45%)
Contract # 09133236
Totals 2072944.64 0.00 2032302.12 100.0

CountyFAYETTE
Highway US 290
From WASHINGTON COUNTY LINE
To LEE COUNTY LINE
CSJ 0114-08-034
Proj ID NH 2015(698)
Work Type PAVEMENT REPAIR & ACP OVERLAY
 
7.640 3140617.52 0.00 3361145.49 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-18-15
Work Began 04-20-15
Work Completed 09-21-15
Time Computed 04-20-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 83
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 0114-08-034
DUSTROL, INC.(0.47%)
HUDSON, INC. (3.53%)
ROADSAFE TRAFFIC SYSTEMS, INC. (2.86%)
Contract # 02153237
Totals 3140617.52 0.00 3361145.49 100.0

CountyGONZALES
Highway US 87
From WILSON COUNTY LINE
To FM 77
CSJ 0143-06-029
Proj ID NH 2015(532)
Work Type PAVEMENT REPAIR AND SURFACING
 
3.254 5409576.71 50102.27 1199712.85 22.1
Work Order 02-26-15
Work Began 07-20-15
Work Completed  
Time Computed 06-26-15
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 61
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-06-029
FLASHER EQUIPMENT COMPANY(1.77%)
ALTUS TRAFFIC MANAGEMENT LLC (0.46%)
Contract # 01153207
Totals 5409576.71 50102.27 1199712.85 22.1

CountyDEWITT
Highway US 87
From US 183 IN CUERO
To TO SH 72
CSJ 0143-08-087
Proj ID NH 1502(122)
Work Type UPGRADE TRAFFIC SIGNALS
 
0.002 930045.00 56329.82 229714.01 24.6
Work Order 07-01-15
Work Began 12-03-15
Work Completed  
Time Computed 10-30-15
Contract Working Days 149
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 19
Contractor(s)
MIDASCO, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0143-08-087
SOUTH RANGER CONSTRUCTION, INC.( 17.12%)
BAY CITY TRAFFIC ( 10.19%)
M & M STRIPING & POWER WASHING, LLC(4.62%)
Contract # 05153216
Totals 930045.00 56329.82 229714.01 24.6

CountyDEWITT
Highway US 87
From SH 72
To US 183 IN CUERO
CSJ 0143-08-089
Proj ID NH 2015(425)
Work Type ACP OVERLAY
 
6.986 2789989.26 2567.44 3125974.91 99.9
Work Order 02-13-15
Work Began 06-29-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 45
Addl Days Granted 0
Working Days Charged 54
Percent Time Used 120
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0143-08-089
CHEROKEE SERVICES(0.69%)
COWBELL TRAFFIC SERVICE, INC.(0.51%)
ROADSAFE TRAFFIC SYSTEMS, INC. (3.03%)
Contract # 12143008
Totals 2789989.26 2567.44 3125974.91 99.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6