Tabulation of Bids for Project BPM - 627622001
Text version of this page | |||
County: | WILLIAMSON | Let Date: | 01/10/17 |
Type: | REPAIR STEEL PILES, REGRADE AND ARMOR CHANNEL | Seq No: | 1405 |
Time: | 39 W | Project ID: | BPM - 627622001 |
Highway: | FM0970 | Contract #: | 01171405 |
Length: | 0.000 | CCSJ: | 6276-22-001 |
Limits: | |||
From: | AT BERRY CREEK | Check: | $2,000 |
To: | . | Misc Cost: | $4,600.00 |
Estimate | $94,858.28 | % Over/Under | Company |
Bidder 1 | $86,740.00 | -8.56% | TREVWAY, INC. |
Bidder 2 | $110,674.59 | +16.67% | SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
1006002 | PREPARING ROW | STA | 2.000 | 1,165.53 | 1 2 | 2,000.000 1,688.000 |
4016001 | FLOWABLE BACKFILL | CY | 75.000 | 118.21 | 1 2 | 184.000 112.500 |
4206071 | CL C CONC (COLLAR) | EA | 12.000 | 1,295.00 | 1 2 | 1,700.000 1,660.000 |
4296009 | CONC STR REPAIR (STANDARD) | SF | 28.000 | 206.00 | 1 2 | 500.000 213.750 |
4326033 | RIPRAP (STONE PROTECTION)(18 IN) | CY | 132.000 | 151.28 | 1 2 | 105.000 253.120 |
4466008 | CLEAN & PAINT EXIST PILING (SYS II) | LS | 1.000 | 30,000.00 | 1 2 | 6,000.000 16,875.000 |
5006001 | MOBILIZATION | LS | 1.000 | 5,854.41 | 1 2 | 8,000.000 11,250.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 1.000 | 3,000.00 | 1 2 | 1,500.000 4,500.000 |
5066038002 | TEMP SEDMT CONT FENCE (INSTALL) | LF | 100.000 | 2.20 | 1 2 | 3.000 2.250 |
5066039002 | TEMP SEDMT CONT FENCE (REMOVE) | LF | 100.000 | 0.77 | 1 2 | 2.000 1.130 |
60016001 | PORTABLE CHANGEABLE MESSAGE SIGN | DAY | 39.000 | 82.90 | 1 2 | 120.000 168.750 |