Tabulation of Bids for Project STP 2019(619)HES
Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months.
The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only.
Text version of this page | |||
County: | SMITH | Let Date: | 03/06/19 |
Type: | CENTERLINE & EDGELINE PROFILE PAV MRK | Seq No: | 3218 |
Time: | 84 WORKING DAYS | Project ID: | STP 2019(619)HES |
Highway: | FM 1253 | Contract #: | 03193218 |
Length: | 11.787 | CCSJ: | 0203-08-016 |
Limits: | |||
From: | US 80, S | Check: | $24,000 |
To: | SH 110 S OF GARDEN VALLEY | Misc Cost: | $7,000.00 |
Estimate | $1,178,935.60 | % Over/Under | Company |
Bidder 1 | $706,776.90 | -40.05% | CENTERLINE TECHNOLOGIES, LLC |
Bidder 2 | $769,486.35 | -34.73% | STRIPE-A-ZONE, INC. |
Bidder 3 | $917,646.70 | -22.16% | STRIPING TECHNOLOGY, L.P. |
Bidder 4 | $979,433.20 | -16.92% | TOTAL HIGHWAY MAINTENANCE, LLC |
Bidder 5 | $1,270,280.40 | +7.75% | TRP CONSTRUCTION GROUP, LLC |
Item Code | Description | Unit | Quantity | Unit Est. | Bidder | Unit Bid |
5006001 | MOBILIZATION | LS | 1.000 | 10.00 | 1 2 3 4 5 | 1.000 26,250.000 75,000.000 55,000.000 100,000.000 |
5026001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | MO | 6.000 | 5,000.00 | 1 2 3 4 5 | 1.000 9,150.000 5,000.000 4,500.000 21,500.000 |
6666224007 | PAVEMENT SEALER 4" | LF | 600.000 | 0.20 | 1 2 3 4 5 | 1.000 1.000 0.500 1.000 5.000 |
6666300007 | RE PM W/RET REQ TY I (W)4"(BRK)(100MIL) | LF | 5,700.000 | 0.30 | 1 2 3 4 5 | 0.270 0.400 0.500 0.470 0.370 |
6666303007 | RE PM W/RET REQ TY I (W)4"(SLD)(100MIL) | LF | 12,100.000 | 0.30 | 1 2 3 4 5 | 0.270 0.310 0.450 0.410 0.320 |
6666312007 | RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL) | LF | 12,040.000 | 0.30 | 1 2 3 4 5 | 0.270 0.400 0.500 0.470 0.370 |
6666315007 | RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL) | LF | 182,790.000 | 0.30 | 1 2 3 4 5 | 0.250 0.310 0.450 0.410 0.320 |
6666342007 | REF PROF PAV MRK TY I(W)4"(SLD)(100MIL) | LF | 715,990.000 | 0.85 | 1 2 3 4 5 | 0.540 0.515 0.580 0.650 0.740 |
6666344007 | REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL) | LF | 16,920.000 | 1.25 | 1 2 3 4 5 | 0.550 0.550 1.000 0.750 0.950 |
6666345007 | REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL) | LF | 390,820.000 | 1.00 | 1 2 3 4 5 | 0.550 0.515 0.580 0.650 0.740 |
6726009 | REFL PAV MRKR TY II-A-A | EA | 8,643.000 | 2.70 | 1 2 3 4 5 | 3.000 2.550 3.400 4.000 3.800 |
6726010 | REFL PAV MRKR TY II-C-R | EA | 553.000 | 3.00 | 1 2 3 4 5 | 3.000 2.550 3.400 4.000 5.000 |
6776001 | ELIM EXT PAV MRK & MRKS (4") | LF | 600.000 | 0.45 | 1 2 3 4 5 | 10.000 1.000 1.000 1.000 17.000 |
60566002 | PREFORMED CENTERLINE RUMBLE STRIP | LF | 1,570.000 | 3.00 | 1 2 3 4 5 | 5.000 7.950 12.000 7.000 9.000 |
61856001001 | TMA (STATIONARY) | EA | 2.000 | 8,000.00 | 1 2 3 4 5 | 1.000 300.000 1,000.000 2,500.000 2,500.000 |
61856005001 | TMA (MOBILE OPERATION) | DAY | 84.000 | 220.00 | 1 2 3 4 5 | 1.000 45.000 50.000 275.000 825.000 |