Seq No County Project ID CCSJ Highway Reason for change
001 WEBB CBI 1602(504) 0086-14-065 SL 20 MPO request to reschedule.
003 TERRY NH 2017(462) 0228-01-056 US 62 due to district fund considerations
011 CLAY BR 2017(466) 0282-01-016 SH 79 remove from letting schedule
015 MC CULLOCH STP 2017(458) 0128-04-035 US 190 due to unclear utilities
204 WICHITA C 802-2-53 0802-02-053 FM 369 due to a P.S.&E. revision required
210 MIDLAND NH 2017(475) 1188-02-096 SH 158 due to a P.S.&E. revision required
217 MC LENNAN STP 2017(464)HES 0909-22-173 CS due to district engineer request
222 RAINS STP 2017(515) 0108-11-019 SH 19 due to district funding considerations
224 STEPHENS STP 1602(303) 0257-01-041 US 183 due to unclear utilities
225 TRAVIS C 15-13-377 0015-13-377 IH 35 due to district funding considerations
231 NOLAN NH 2017(456) 0006-03-132 IH 29 Remove PFC from this project and replace with a more durable SMA mix
236 ROBERTSON STP 2017(345)HES 0049-08-063 US 190 Canceled 9-27-16
246 PECOS STP 2017(474) 0139-08-037 US 285 due to unclear Right of Way

 