1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 1110804 MGR.NO. PAGE 001 CONT 6219 SEC 87 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 621987001 HWY US0180 4250 N. CLACK ABILENE CNTY FISHER DIST 08 CONTRACT PRICE $ 257,208.00 REPORT DATE 12/27/2012 15.25.46 CONTRACTOR GREG SCRUGGS 13560 EST PERIOD JUN 23,2011 TO DEC 11,2012 EST NO 019 & FINAL --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 24, 2011 TIME COMPUTED FROM JUN 23, 2011 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 76 527 141 386 BROUGHT FORWARD ADDL DAYS GRANTED = 76 DEC 12 1 1 SATURDAY TOTAL DAYS ALLOWED = 152 2 1 SUNDAY DATE WORK COMPLETED 12/11/12 3 1 DAYS CHARGED TO DATE = 149 4 1 ASSESSED LIQ DAMAGES = 0 5 1 LIQ DAMAGE RATE $ 500 6 1 7 1 LIQUIDATED DAMAGES 8 1 0 DAYS AT $ 500 PER DAY 9 1 SUNDAY TOTAL = $ .00 10 1 11 1 CONTRACT COMPLETED & ACCEPTED CERTIFIED AS CORRECT AND ONE COPY HAS BEEN GIVEN TO THE CONTRACTOR - ---------------------------- AREA/PROJECT ENGINEER - - - - - ----- ----- ----- 538 149 389 1 SATURDAY 2 SUNDAY 0 HOLIDAY 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 1110804 MGR.NO. PAGE 001 CONT 6219 SEC 87 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 621987001 HWY US0180 4250 N. CLACK ABILENE CNTY FISHER DIST 08 CONTRACT PRICE $ 257,208.00 REPORT DATE 12/27/2012 15.25.46 CONTRACTOR GREG SCRUGGS 13560 EST PERIOD JUN 23,2011 TO DEC 11,2012 EST NO 019 & FINAL DIST. 08 COUNTY FISHER CONTROL 6219-87-001 PROJECT RMC - 621987001 HIGHWAY US0180 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY DEBBIE PAYLOR 0 0055 ALL ITEMS NET LENGTH 0.010 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 9,186.000 18,812.000 28.000 526,736.00 0060 0730 ADJ EST QUANTITY TO DATE 18,372.000 0 SUBTOTAL BID ITEMS $ 526,736.00 0 TOTAL AMOUNT WORK DONE ALL ITEMS $ 526,736.00 0 TOTAL AMOUNT WORK DONE CONTROL 6219-87-001 $ 526,736.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 1110804 MGR.NO. PAGE 001 CONT 6219 SEC 87 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 621987001 HWY US0180 4250 N. CLACK ABILENE CNTY FISHER DIST 08 CONTRACT PRICE $ 257,208.00 REPORT DATE 12/27/2012 15.25.46 CONTRACTOR GREG SCRUGGS 13560 EST PERIOD JUN 23,2011 TO DEC 11,2012 EST NO 019 & FINAL 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JUN 24, 2011 WORKING DAYS USED 149 PERCENT COMPLETE 100.00 PERCENT TIME USED 98.00 DATE COMPLETED DEC 11 2012 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6219-87-001 RMC - 621987001 08 US0180 FISHER - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 9,186.000 18,812.000 28.000 526,736.00 0730 ADJ EST QUANTITY TO DATE 18,372.000 0 SUBTOTAL BID ITEMS $ 526,736.00 0 CONTRACT TOTAL ALL ITEMS $ 526,736.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 1110804 MGR.NO. PAGE 001 CONT 6219 SEC 87 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 621987001 HWY US0180 4250 N. CLACK ABILENE CNTY FISHER DIST 08 CONTRACT PRICE $ 257,208.00 REPORT DATE 12/27/2012 15.25.46 CONTRACTOR GREG SCRUGGS 13560 EST PERIOD JUN 23,2011 TO DEC 11,2012 EST NO 019 & FINAL ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 77 RMC - 621987001 6219-87-001 526,736.00 .00 526,736.00 .00 .00 526,736.00 463,176.00 63,560.00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 526,736.00 .00 526,736.00 .00 .00 526,736.00 463,176.00 63,560.00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 **APPROVED BY** DATE --------------------------------------------- AREA/PROJECT ENGINEER 0 DATE --------------------------------------------- DISTRICT ENGINEER 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 1110804 MGR.NO. PAGE 001 CONT 6219 SEC 87 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 621987001 HWY US0180 4250 N. CLACK ABILENE CNTY FISHER DIST 08 CONTRACT PRICE $ 257,208.00 REPORT DATE 12/27/2012 15.25.46 CONTRACTOR GREG SCRUGGS 13560 EST PERIOD JUN 23,2011 TO DEC 11,2012 EST NO 019 & FINAL ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6219-87-001 RMC - 621987001 08 US0180 FISHER -LIMITS - VARIOUS VARIOUS LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES THIS ESTIMATE PRICE($) ($) 0 60 0730 FULL-WIDTH MOWING AC 9,186.000 2,270.000 28.000 63,560.00 --------------- - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 63,560.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 526,736.00