1MIS.CIS.01 CONTRACT TIME STATEMENT CONTRACT 11120804 MGR.NO. PAGE 001 CONT 6249 SEC 29 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624929001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 176,160.00 REPORT DATE 07/02/2014 09.36.19 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 013 --------------------------------------------------------------------------------------------------------- DATE WORK BEGAN JUN 17, 2013 TIME COMPUTED FROM JUN 24, 2013 SUMMARY INFORMATION 0 DATE WORKING REASONS FOR DAYS CREDITED MONTH/YEAR OR DAYS DAYS /COMMENTS FOR DAYS CHARGED PHASE I DAYS CHARGED CREDITED CONTRACT WORK DAYS = 65 349 60 289 BROUGHT FORWARD ADDL DAYS GRANTED = 65 JUN 14 1 1 SUNDAY TOTAL DAYS ALLOWED = 130 2 1 CYCLE NOT STARTED DATE WORK COMPLETED 3 1 CYCLE NOT STARTED DAYS CHARGED TO DATE = 60 4 1 CYCLE NOT STARTED ASSESSED LIQ DAMAGES = 0 5 1 CYCLE NOT STARTED LIQ DAMAGE RATE $ 590 6 1 CYCLE NOT STARTED 7 1 SATURDAY LIQUIDATED DAMAGES 8 1 SUNDAY 0 DAYS AT $ 590 PER DAY 9 1 CYCLE NOT STARTED TOTAL = $ .00 10 1 CYCLE NOT STARTED 11 1 CYCLE NOT STARTED CERTIFIED AS CORRECT AND 12 1 CYCLE NOT STARTED ONE COPY HAS BEEN GIVEN 13 1 CYCLE NOT STARTED TO THE CONTRACTOR 14 1 SATURDAY 15 1 SUNDAY 16 1 CYCLE NOT STARTED ---------------------------- 17 1 CYCLE NOT STARTED AREA/PROJECT ENGINEER 18 1 CYCLE NOT STARTED 19 1 CYCLE NOT STARTED 20 1 CYCLE NOT STARTED 21 1 SATURDAY 22 1 SUNDAY 23 1 CYCLE NOT STARTED 24 1 CYCLE NOT STARTED 25 1 CYCLE NOT STARTED 26 1 CYCLE NOT STARTED 27 1 CYCLE NOT STARTED 28 1 SATURDAY 29 1 SUNDAY 30 1 CYCLE NOT STARTED 0 ----- ----- ----- 379 60 319 4 SATURDAY 5 SUNDAY 0 HOLIDAY 21 CYCLE NOT STARTED 1MIS.CIS.03 CONSTRUCTN ESTIMATE BREAKDOWN CONTRACT 11120804 MGR.NO. PAGE 001 CONT 6249 SEC 29 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624929001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 176,160.00 REPORT DATE 07/02/2014 09.36.19 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 013 DIST. 08 COUNTY JONES CONTROL 6249-29-001 PROJECT RMC - 624929001 HIGHWAY US0083 0LIMITS- VARIOUS VARIOUS 0TYPE OF WORK- MOWING HIGHWAY RIGHT OF WAY 0 0005 PREPARED BY DEBBIE PAYLOR 0 0055 ALL ITEMS NET LENGTH 0.001 MILES 0 LINE ITEM ESTIMATED WORK DONE CONTRACT AMOUNT NO. NO. DESCRIPTION UNIT QUANTITIES ON CONTRACT PRICE($) ($) - 0060 0730 FULL-WIDTH MOWING AC 7,290.000 7,298.000 24.000 175,152.00 0060 0730 ADJ EST QUANTITY TO DATE 14,580.000 0065 0730 SPOT MOWING AC 50.000 0.000 24.000 .00 0065 0730 ADJ EST QUANTITY TO DATE 100.000 0 SUBTOTAL BID ITEMS $ 175,152.00 0 TOTAL AMOUNT WORK DONE ALL ITEMS $ 175,152.00 0 TOTAL AMOUNT WORK DONE CONTROL 6249-29-001 $ 175,152.00 1MIS.CIS.04 CONSTRUCTION ESTIMATE COMBINED CONTRACT 11120804 MGR.NO. PAGE 001 CONT 6249 SEC 29 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624929001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 176,160.00 REPORT DATE 07/02/2014 09.36.20 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 013 0*********************************************************************************************************************************** -LIMITS - VARIOUS 0 VARIOUS DATE WORK BEGAN JUN 17, 2013 WORKING DAYS USED 60 PERCENT COMPLETE 99.42 PERCENT TIME USED 46.10 DATE COMPLETED 0 CONTROL PROJECT DISTRICT HIGHWAY COUNTY 0 6249-29-001 RMC - 624929001 08 US0083 JONES - ITEM DESCRIPTION UNIT ESTIMATED WORK DONE CONTRACT AMOUNT NO. QUANTITIES ON CONTRACT PRICE($) ($) -0730 FULL-WIDTH MOWING AC 7,290.000 7,298.000 24.000 175,152.00 0730 ADJ EST QUANTITY TO DATE 14,580.000 0 SUBTOTAL BID ITEMS $ 175,152.00 0 CONTRACT TOTAL ALL ITEMS $ 175,152.00 1MIS.CIS.05 CONSTR ESTIMATE DISTRIBUTION CONTRACT 11120804 MGR.NO. PAGE 001 CONT 6249 SEC 29 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624929001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 176,160.00 REPORT DATE 07/02/2014 09.36.20 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 013 ********************************************************************************************************************************** CO NO PROJECT CONT SEC JOB LINE NO TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 128 RMC - 624929001 6249-29-001 175,152.00 .00 175,152.00 .00 .00 175,152.00 175,152.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0********************************** TOTALS ***************************************************************************** TOTAL AMOUNT .00 % DIFFERENCE LESS TOTAL LESS LIQ DIFFERENCE LESS PREV AMOUNT DUE WORK DONE RETAINAGE SPL DEDUCTS DAMAGE PAYMENTS THIS EST ********************************************************************************************************************************** 175,152.00 .00 175,152.00 .00 .00 175,152.00 175,152.00 .00 ---------------------------------------------------------------------------------------------------------------------------------- 0INPUT PROOF READ BY- SUPPORTING PAPERS OK ------------------------------ ---------------------------- 0 APPROVED DATE --------------------------------- ----------------- 1MIS.CIS.07 WORK PERFORMED THIS PERIOD CONTRACT 11120804 MGR.NO. PAGE 001 CONT 6249 SEC 29 JOB 001 RES ENGR PAYLOR, DEBBIE PROJ RMC - 624929001 HWY US0083 4250 N. CLACK ABILENE CNTY JONES DIST 08 CONTRACT PRICE $ 176,160.00 REPORT DATE 07/02/2014 09.36.20 CONTRACTOR KENNETH THOMASON 11017 EST PERIOD JUN 01,2014 TO JUN 30,2014 EST NO 013 ********************************************************************************************************************* - CONTROL PROJECT DISTRICT HIGHWAY COUNTY 6249-29-001 RMC - 624929001 08 US0083 JONES -LIMITS - VARIOUS VARIOUS - TOTAL BID ITEMS DONE THIS ESTIMATE - $ 0.00 0 TOTAL AMOUNT WORK DONE TO DATE - $ 175,152.00